419 S SPRING ST 90013

Certificate Information: 419 S SPRING ST 90013

Application / Permit
13016-10000-26325
Plan Check / Job No.
B13LA16345
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(11) Hotel
Work Description
ADAPTIVE REUSE OF AN EXISTING OFFICE BUILDING TO BE CONVERTED TO A 180 ROOM HOTEL . CHANGE OF USE FROM OFFICE TO HOTEL , FIRST FLOOR RESTAURANT CORE AND SHELL ONLY. (NO EXCAVATION BEFORE JAN 17, 2017)
Permit Issued
Issued on 12/20/2016
Issuing Office
Metro
Current Status
Issued on 12/20/2016
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/26/2013 APPLICANT
Assigned to Plan Check Engineer 1/9/2014 LIPING TENG
Green Plans Picked Up 1/21/2014 APPLICANT
Corrections Issued 1/24/2014 LIPING TENG
Building Plans Picked Up 2/7/2014 APPLICANT
Disabled Access Plans Picked Up 2/7/2014 APPLICANT
Quality Review Completed 12/17/2014 JAMESON LEE
Plan Check Approved 12/19/2016 SUEN LIEU
Issued 12/20/2016 LADBS

Permit Application Clearance Information

"D" conditions Cleared 8/30/2016 ULISES GONZALEZ
"Q" conditions Cleared 8/30/2016 ULISES GONZALEZ
Highway dedication Cleared 8/30/2016 ALFREDO JARA
Sewer availability Cleared 8/30/2016 ALFREDO JARA
ZA Case Cleared 8/30/2016 ULISES GONZALEZ
Low Impact Development Cleared 9/1/2016 MICHAEL SCADUTO
Roof/Waste drainage to street Cleared 9/1/2016 RAVIL MANAPOV
Stormwater Pollution Mitigatn Cleared 9/1/2016 MICHAEL SCADUTO
Eng Process Fee Ord 176,300 Cleared 9/8/2016 SHANNON CAMPBELL
Miscellaneous Cleared 9/23/2016 LIPING TENG
ZA Case Cleared 9/23/2016 LIPING TENG
City hist. mon. (ZI145- <1000) Cleared 10/21/2016 LAMBERT GIESSINGER
Hist. Property Cntrct Mgr Appr Cleared 10/21/2016 LAMBERT GIESSINGER
Historic monument Cleared 10/21/2016 LAMBERT GIESSINGER
Historical monument Cleared 11/17/2016 JIM URQUHART
Historical monument Cleared 11/17/2016 JIM URQUHART
DAS Clearance Cleared 12/1/2016 LIPING TENG
Driveway location Cleared 12/1/2016 WESTON PRINGLE
Internal circulation Cleared 12/1/2016 WESTON PRINGLE
Hydrant and Access approval Cleared 12/7/2016 ROBERT DUFF
Green Code Cleared 12/8/2016 SEAN DANG
Title 19 building approval Cleared 12/16/2016 SUSIE ADAMIAN
Building over 3-story or 35-ft Cleared 12/19/2016 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 12/19/2016 CALOSHA APPROVED
Work Adjacent to Public Way Cleared 12/19/2016 RAVIL MANAPOV

Contact Information

Architect Yonkin, Dale N; Lic. No.: C8376 1128 TIGERTAIL ROAD      LOS ANGELES, CA 90049
Contractor K C S West Inc; Lic. No.: 908480-B 250 EAST 1ST STREET STE 600      LOS ANGELES, CA 90012
Engineer Bech, Daniel Terence Tasm; Lic. No.: S5243 8930 SENECA      OAKLAND, CA 94605
Engineer Daneshfar, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306
Geologist Feffer, Joshua Rafael; Lic. No.: GEO6861 12253 GORHAM AVENUE      LOS ANGELES, CA 90049

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 12/18/2017 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 12/19/2017 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 1/31/2019 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 2/1/2019 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 2/21/2019 Conditional Approval KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 9/12/2019 Partial Approval JAMES POWERS
Footing/Foundation/Slab 9/12/2019 Partial Inspection KATY RAMIREZ
Deputy Reinf. Concrete 9/13/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 9/20/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 9/23/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 9/24/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 9/25/2019 No Access for Inspection KATY RAMIREZ
Deputy Reinf. Concrete 9/26/2019 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 10/7/2019 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 10/8/2019 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 10/8/2019 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 10/9/2019 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 10/10/2019 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 10/11/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 10/15/2019 Conditional Approval KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 10/28/2019 Partial Approval KATY RAMIREZ
Footing/Foundation/Slab 10/28/2019 Partial Approval KATY RAMIREZ
Deputy Reinf. Concrete 10/30/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 11/7/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 11/8/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 11/13/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 11/14/2019 Conditional Approval KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 11/14/2019 Partial Inspection KATY RAMIREZ
Deputy Other (see comments) 11/15/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 11/15/2019 Conditional Approval KATY RAMIREZ
Light Gage Steel Frame 11/20/2019 Not Ready for Inspection KATY RAMIREZ
Structural Steel Frame 11/22/2019 Partial Approval KATY RAMIREZ
Deputy Drilled-In Anchors 12/3/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 12/3/2019 Conditional Approval KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 12/3/2019 Not Ready for Inspection KATY RAMIREZ
Footing/Foundation/Slab 12/3/2019 Not Ready for Inspection KATY RAMIREZ
Deputy Drilled-In Anchors 12/4/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 12/4/2019 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 12/5/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 12/5/2019 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 12/6/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 12/6/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 12/9/2019 Conditional Approval KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 12/9/2019 Partial Approval KATY RAMIREZ
Deputy Reinf. Concrete 12/11/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 12/17/2019 Conditional Approval KATY RAMIREZ
Light Gage Steel Frame 12/18/2019 Partial Approval KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 12/27/2019 Partial Approval RAFAEL ESPINOZA
Deputy Drilled-In Anchors 12/30/2019 Conditional Approval DANIEL MC AULIFFE
Deputy Drilled-In Anchors 12/31/2019 Conditional Approval JONATHAN QUACH
Deputy Drilled-In Anchors 1/2/2020 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 1/3/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 1/7/2020 Conditional Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 1/10/2020 Partial Approval KATY RAMIREZ
Footing/Foundation/Slab 1/10/2020 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 1/15/2020 Partial Approval DANIEL VARNUM
Deputy Reinf. Concrete 1/16/2020 Conditional Approval KATY RAMIREZ
Light Gage Steel Frame 3/5/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 3/18/2020 Partial Approval DANIEL VARNUM
Deputy Reinf. Concrete 4/24/2020 Conditional Approval DANIEL COLLINS
Green Building Rough 4/24/2020 Approved KATY RAMIREZ
Reinforced Concrete Frame 4/24/2020 Partial Inspection KATY RAMIREZ
Footing/Foundation/Slab 5/21/2020 Partial Approval KATY RAMIREZ
Deputy Shotcrete 5/22/2020 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 5/29/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 6/10/2020 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 6/10/2020 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 6/10/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 6/11/2020 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 6/11/2020 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 6/11/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 6/12/2020 Conditional Approval DANIEL COLLINS
Deputy Shotcrete 6/12/2020 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 6/12/2020 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 6/15/2020 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 6/15/2020 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 6/15/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 6/16/2020 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 6/16/2020 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 6/16/2020 Conditional Approval KATY RAMIREZ
Floor/Roof Diaphrgm/Shear Wall 6/16/2020 Partial Approval KATY RAMIREZ
Deputy Reinf. Concrete 6/22/2020 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 6/22/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 6/23/2020 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 6/23/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 6/24/2020 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 6/24/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 6/25/2020 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 6/25/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 6/26/2020 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 6/26/2020 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 7/23/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/31/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 8/3/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 8/4/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 8/5/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 8/6/2020 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 8/6/2020 No Access for Inspection KATY RAMIREZ
Deputy Steel/Welding 8/6/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 8/7/2020 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 8/7/2020 No Access for Inspection KATY RAMIREZ
Deputy Steel/Welding 8/7/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 8/10/2020 Conditional Approval RONALD PACHECO
Deputy Shotcrete 8/10/2020 Conditional Approval RONALD PACHECO
Deputy Steel/Welding 8/10/2020 Conditional Approval RONALD PACHECO
Deputy Reinf. Concrete 8/11/2020 Conditional Approval DANIEL COLLINS
Deputy Shotcrete 8/11/2020 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 8/11/2020 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 8/12/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 8/12/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/12/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/13/2020 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 8/13/2020 No Access for Inspection KATY RAMIREZ
Deputy Steel/Welding 8/13/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 8/14/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 8/14/2020 No Access for Inspection KATY RAMIREZ
Deputy Shotcrete 8/14/2020 No Access for Inspection KATY RAMIREZ
Deputy Steel/Welding 8/14/2020 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 8/17/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 8/18/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 8/19/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 8/20/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 8/21/2020 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 8/24/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 8/25/2020 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 8/25/2020 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 8/25/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 8/26/2020 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 8/26/2020 No Access for Inspection KATY RAMIREZ
Deputy Steel/Welding 8/26/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 8/27/2020 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 8/27/2020 No Access for Inspection KATY RAMIREZ
Deputy Steel/Welding 8/27/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 8/28/2020 Conditional Approval DANIEL COLLINS
Deputy Shotcrete 8/28/2020 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 8/28/2020 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 8/31/2020 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 8/31/2020 No Access for Inspection KATY RAMIREZ
Deputy Steel/Welding 8/31/2020 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 9/1/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 9/1/2020 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 9/1/2020 No Access for Inspection KATY RAMIREZ
Deputy Drilled-In Anchors 9/2/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 9/2/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 9/2/2020 No Access for Inspection KATY RAMIREZ
Deputy Shotcrete 9/2/2020 No Access for Inspection KATY RAMIREZ
Deputy Drilled-In Anchors 9/3/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 9/3/2020 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 9/3/2020 No Access for Inspection KATY RAMIREZ
Deputy Drilled-In Anchors 9/4/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 9/4/2020 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 9/4/2020 No Access for Inspection KATY RAMIREZ
Deputy Drilled-In Anchors 9/8/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 9/8/2020 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 9/8/2020 No Access for Inspection KATY RAMIREZ
Deputy Drilled-In Anchors 9/9/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 9/9/2020 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 9/10/2020 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 9/10/2020 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 9/11/2020 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 9/11/2020 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 9/14/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 9/14/2020 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 9/15/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 9/15/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 9/16/2020 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 9/18/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 9/18/2020 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 9/18/2020 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 9/21/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 9/21/2020 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 9/21/2020 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 9/22/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 9/22/2020 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 9/22/2020 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 9/23/2020 No Access for Inspection KATY RAMIREZ
Deputy Reinf. Concrete 9/23/2020 No Access for Inspection KATY RAMIREZ
Deputy Steel/Welding 9/23/2020 No Access for Inspection KATY RAMIREZ
Deputy Drilled-In Anchors 9/24/2020 No Access for Inspection KATY RAMIREZ
Deputy Reinf. Concrete 9/24/2020 No Access for Inspection KATY RAMIREZ
Deputy Steel/Welding 9/24/2020 No Access for Inspection KATY RAMIREZ
Deputy Reinf. Concrete 10/1/2020 Conditional Approval KATY RAMIREZ
Insulation 10/1/2020 Not Ready for Inspection KATY RAMIREZ
Deputy Reinf. Concrete 10/8/2020 Conditional Approval DANIEL COLLINS
Insulation 10/8/2020 Partial Approval DANIEL COLLINS
Deputy Reinf. Concrete 10/9/2020 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 10/13/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 10/14/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 10/15/2020 Conditional Approval KATY RAMIREZ
Structural Steel Frame 10/15/2020 Partial Approval KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 10/22/2020 Partial Approval KATY RAMIREZ
Floor/Roof Diaphrgm/Shear Wall 10/22/2020 Partial Approval KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 10/23/2020 Partial Approval KATY RAMIREZ
Deputy Reinf. Concrete 10/26/2020 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 10/27/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 10/27/2020 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 10/27/2020 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 10/28/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 10/28/2020 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 10/28/2020 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 10/29/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 10/29/2020 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 10/29/2020 No Access for Inspection KATY RAMIREZ
Deputy Drilled-In Anchors 10/30/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 10/30/2020 No Access for Inspection KATY RAMIREZ
Deputy Shotcrete 10/30/2020 No Access for Inspection KATY RAMIREZ
Piling/Pier/Caisson 10/30/2020 Partial Approval KATY RAMIREZ
Deputy Drilled-In Anchors 11/2/2020 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 11/2/2020 Conditional Approval DANIEL COLLINS
Deputy Shotcrete 11/2/2020 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 11/5/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 11/5/2020 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 11/6/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 11/6/2020 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 11/9/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 11/9/2020 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 11/10/2020 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 11/10/2020 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 11/12/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 11/12/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 11/20/2020 Conditional Approval DANIEL COLLINS
Reinforced Concrete Frame 11/20/2020 Partial Approval DANIEL COLLINS
Deputy Reinf. Concrete 11/23/2020 Conditional Approval DANIEL COLLINS
Interior/Exterior Lathing 12/7/2020 Partial Approval KATY RAMIREZ
Deputy Reinf. Concrete 2/22/2021 Conditional Approval KATY RAMIREZ
Footing/Foundation/Slab 2/22/2021 Partial Approval KATY RAMIREZ
Deputy Reinf. Concrete 2/23/2021 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 2/24/2021 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 2/25/2021 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 2/26/2021 Conditional Approval KATY RAMIREZ
Pre-Inspection 3/8/2021 No Access for Inspection KATY RAMIREZ
Deputy Reinf. Concrete 3/11/2021 Conditional Approval RONALD PACHECO
Deputy Shotcrete 3/11/2021 Conditional Approval DANIEL COLLINS
Reinforced Concrete Frame 3/12/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 3/15/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 4/6/2021 Conditional Approval KATY RAMIREZ
Floor/Roof Diaphrgm/Shear Wall 4/6/2021 Not Ready for Inspection KATY RAMIREZ
Reinforced Concrete Frame 4/6/2021 Not Ready for Inspection KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 4/8/2021 Partial Approval KATY RAMIREZ
Reinforced Concrete Frame 4/8/2021 Partial Approval KATY RAMIREZ
Deputy Shotcrete 4/9/2021 No Access for Inspection KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 4/9/2021 Partial Approval KATY RAMIREZ
Deputy Shotcrete 4/12/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 4/13/2021 Conditional Approval DANIEL COLLINS
Deputy Shotcrete 4/13/2021 Conditional Approval DANIEL COLLINS
Reinforced Concrete Frame 4/13/2021 Partial Approval DANIEL COLLINS
Deputy Reinf. Concrete 4/14/2021 Conditional Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 4/26/2021 No Access for Inspection KATY RAMIREZ
Deputy Reinf. Concrete 4/27/2021 Conditional Approval KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 4/27/2021 No Access for Inspection KATY RAMIREZ
Piling/Pier/Caisson 4/27/2021 Not Ready for Inspection KATY RAMIREZ
Reinforced Concrete Frame 4/27/2021 No Access for Inspection KATY RAMIREZ
Piling/Pier/Caisson 4/28/2021 No Access for Inspection KATY RAMIREZ
Deputy Reinf. Concrete 5/10/2021 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 5/11/2021 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 5/12/2021 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 5/13/2021 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 5/14/2021 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 5/26/2021 Conditional Approval DANIEL COLLINS
Piling/Pier/Caisson 5/26/2021 Partial Approval NICK DANERI
Reinforced Concrete Frame 6/23/2021 Partial Approval KATY RAMIREZ
Deputy Shotcrete 6/24/2021 No Access for Inspection KATY RAMIREZ
Floor/Roof Diaphrgm/Shear Wall 6/24/2021 Partial Approval KATY RAMIREZ
Reinforced Concrete Frame 4/1/2022 Not Ready for Inspection KATY RAMIREZ
Deputy Shotcrete 4/4/2022 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 4/5/2022 Conditional Approval KATY RAMIREZ
Deputy Shotcrete 4/5/2022 Conditional Approval TIMOTHY BUXTON
Reinforced Concrete Frame 4/5/2022 Partial Approval KATY RAMIREZ
Deputy Shotcrete 4/6/2022 Conditional Approval KATY RAMIREZ
Floor/Roof Diaphrgm/Shear Wall 4/6/2022 Not Ready for Inspection KATY RAMIREZ
Deputy Shotcrete 4/7/2022 Conditional Approval KATY RAMIREZ
Floor/Roof Diaphrgm/Shear Wall 4/8/2022 Partial Approval KATY RAMIREZ
Deputy Shotcrete 4/12/2022 Conditional Approval KATY RAMIREZ
Special/Order Compliance 8/19/2022 Corrections Issued KATY RAMIREZ
Special/Order Compliance 11/18/2022 Approved TED RIES
Special/Order Compliance 11/18/2022 Partial Inspection KATY RAMIREZ
Pre-Inspection 3/31/2023 Partial Inspection KATY RAMIREZ
Special/Order Compliance 6/4/2024 Corrections Issued NICK DANERI
Special/Order Compliance 6/12/2024 Partial Inspection NICK DANERI
Special/Order Compliance 2/5/2025 Corrections Issued NICK DANERI
Pre-Inspection 5/29/2025 Not Ready for Inspection PAUL BAZERKANIAN
Pre-Inspection 10/22/2025 Not Ready for Inspection PAUL BAZERKANIAN