7607-7609 S MAIN ST 90003

Certificate Information: 7607-7609 S MAIN ST 90003

Application / Permit
13014-70000-01587
Plan Check / Job No.
B13SL00557
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
Add 19'6" X 80'0" retail at 2nd floor
Permit Issued
Issued on 7/3/2013
Issuing Office
Metro
Current Status
CofO Issued on 2/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2013 APPLICANT
Assigned to Plan Check Engineer 5/9/2013 BINH PHAN
Corrections Issued 5/14/2013 BINH PHAN
Quality Review Completed 5/21/2013 BILL STUTSMAN
Building Plans Picked Up 5/22/2013 APPLICANT
Disabled Access Plans Picked Up 5/22/2013 APPLICANT
Applicant returned to address corrections 5/31/2013 BINH PHAN
Applicant returned to address corrections 6/25/2013 BINH PHAN
Plan Check Approved 7/3/2013 BINH PHAN
Issued 7/3/2013 LADBS
CofO in Progress 2/15/2024 WINSTON DUNNING
CofO Issued 2/15/2024 WINSTON DUNNING
Permit Finaled 2/15/2024 WINSTON DUNNING

Permit Application Clearance Information

"Q" conditions Cleared 6/19/2013 MINDY NGUYEN
Address approval Cleared 6/19/2013 DAVID CHIN
Comm Cor/Mini-Mall Cleared 6/19/2013 MINDY NGUYEN
Comm Cor/Mini-Mall Cleared 6/21/2013 HERMAN VAN BUREN
Eng Process Fee Ord 176,300 Cleared 6/21/2013 ANGENEE REYGADAS
Low Impact Development Cleared 6/21/2013 IDA MEISAMI-FARD
Highway dedication Cleared 6/25/2013 VALENTINO PUEBLOS
Roof/Waste drainage to street Cleared 6/25/2013 VALENTINO PUEBLOS
Sewer availability Cleared 6/25/2013 VALENTINO PUEBLOS
Green Code Cleared 6/26/2013 ALDO UBAU
DAS Clearance Cleared 6/27/2013 WAI LAU

Contact Information

Contractor Owner-Builder       ,
Engineer Goitom, Tesfai; Lic. No.: C38166 7011 STEARNS ST      LONG BEACH, CA 90815

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Rough 7/5/2013 Corrections Issued DEROLD HAUFF
Wood Frame 7/5/2013 Partial Approval DERRICK SPENCER
Drywall Nailing 9/20/2013 Not Ready for Inspection WINFIELD HINKSON
Green Building Rough 9/20/2013 Not Ready for Inspection MICHAEL TUCK
Drywall Nailing 2/4/2020 Approved JAMES POWERS
Final 2/4/2020 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 2/4/2020 Approved JAMES POWERS
Green Building Final 2/4/2020 Approved JAMES POWERS
Green Building Rough 2/4/2020 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 2/4/2020 SGSOV Not Ready JAMES POWERS
Smoke Detectors 2/4/2020 Approved JAMES POWERS
Wood Frame 2/4/2020 Approved JAMES POWERS
Final 6/14/2021 Not Ready for Inspection LEOPOLDO MENDOZA
SGSOV-Seismic Gas S/O Valve 6/14/2021 SGSOV Approved LEOPOLDO MENDOZA
Final 4/27/2022 No Access for Inspection RUSSELL BONVOULOIR
Final 1/31/2023 Partial Approval MARTIN TAVITIAN
Final 4/3/2023 OK for TCO MARTIN TAVITIAN
Special/Order Compliance 10/20/2023 No Access for Inspection DARRYL ARNOLD
Final 1/12/2024 Conditional Approval DARRYL ARNOLD