1753 N VIEWMONT DR 90069
Certificate Information: 1753 N VIEWMONT DR 90069
- Application / Permit
- 13014-40000-01818
- Plan Check / Job No.
- B13SP00316
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1st AND 2nd STORY ADDITION AND REMODEL TO AN EXISTING SFD AS PER ZA-2012-0903 ( ZAD ) ( F )
- Permit Issued
- Issued on 11/15/2016
- Issuing Office
- Metro
- Current Status
- Issued on 11/15/2016
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/15/2013 | APPLICANT |
| Assigned to Plan Check Engineer | 6/20/2013 | JAMES DETCHMENDY |
| Corrections Issued | 6/26/2013 | JAMES DETCHMENDY |
| Quality Review Completed | 7/1/2013 | FELIX FIGUEROA |
| Green Plans Picked Up | 9/3/2013 | APPLICANT |
| Applicant returned to address corrections | 10/2/2013 | JAMES DETCHMENDY |
| Applicant returned to address corrections | 4/2/2014 | JAMES DETCHMENDY |
| Applicant returned to address corrections | 8/5/2015 | JAMES DETCHMENDY |
| Applicant returned to address corrections | 5/13/2016 | JAMES DETCHMENDY |
| Applicant returned to address corrections | 9/9/2016 | JAMES DETCHMENDY |
| Plan Check Approved | 11/15/2016 | JAMES DETCHMENDY |
| Issued | 11/15/2016 | LADBS |
| Permit Expired-Status Void | 12/6/2024 | RAUL BARAJAS |
| Re-Activate Permit | 2/11/2025 | BRIAN SULLIVAN |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/2/2013 | JAMES DETCHMENDY |
| BHO/Hillside ordinance | Cleared | 2/11/2014 | AVALYN KAMACHI |
| BHO/Hillside ordinance | Cleared | 2/11/2014 | AVALYN KAMACHI |
| BHO/Hillside ordinance | Cleared | 2/11/2014 | AVALYN KAMACHI |
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2014 | AVALYN KAMACHI |
| Hydrant and Access approval | Cleared | 2/11/2014 | ROBERT DUFF |
| Sewer availability | Cleared | 2/11/2014 | AVALYN KAMACHI |
| BHO/Hillside ordinance | Cleared | 3/7/2014 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 3/7/2014 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 3/18/2014 | KOSTA KAPORIS |
| Green Code | Cleared | 3/19/2014 | DEROLD HAUFF |
| Roof/Waste drainage to street | Cleared | 3/19/2014 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 3/21/2014 | RONY GIRON |
| Miscellaneous | Cleared | 3/21/2014 | RONY GIRON |
| Miscellaneous | Cleared | 3/21/2014 | RONY GIRON |
| ZA Case | Cleared | 3/21/2014 | RONY GIRON |
| ZA Case | Cleared | 3/21/2014 | RONY GIRON |
| ZA Case | Cleared | 3/21/2014 | RONY GIRON |
| ZA Case | Cleared | 3/21/2014 | RONY GIRON |
| ZA Case | Cleared | 3/21/2014 | RONY GIRON |
| ZI | Cleared | 3/28/2014 | MARITZA PRZEKOP |
| Hydrant and Access approval | Cleared | 7/27/2016 | ROBERT DUFF |
| Green Code | Cleared | 8/15/2016 | JONATHAN QUACH |
| Low Impact Development | Cleared | 8/15/2016 | SAM NAVID |
| ZA Case | Cleared | 9/15/2016 | TREVOR MARTIN |
| ZA Case | Cleared | 9/15/2016 | TREVOR MARTIN |
Contact Information
| Architect | Ashai, Tony; Lic. No.: C24154 | 21515 HAWTHORNE BLVD #975 TORRANCE, CA 90503 |
| Contractor | Clasico Construction; Lic. No.: 640521-B | 105 WEST WALNUT STREET GARDENA, CA 90248 |
| Engineer | Dedmari, Wajahat Hafiz; Lic. No.: C66819 | 5541 GRAYLOG ST RANCHO PALOS VERDES, CA 90275 |
Inspector Information
| ROY SPAULDING, (213) 202-3244 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/16/2017 | Corrections Issued | BRAD BESCOS |
| Deputy Reinf. Concrete | 3/17/2017 | Approved | BRAD BESCOS |
| Excavation/Setback/Form/Re-Bar | 3/17/2017 | Corrections Issued | BRAD BESCOS |
| Deputy Reinf. Concrete | 3/21/2017 | Approved | BRAD BESCOS |
| Excavation/Setback/Form/Re-Bar | 3/21/2017 | Partial Approval | BRAD BESCOS |
| Excavation/Setback/Form/Re-Bar | 4/18/2017 | Partial Approval | ROBERT MINASSIANS |
| Footing/Foundation/Slab | 4/18/2017 | Partial Approval | ROBERT MINASSIANS |
| Excavation/Setback/Form/Re-Bar | 5/1/2017 | Partial Approval | JOEL WILLIAMS |
| Deputy Steel/Welding | 5/25/2017 | No Access for Inspection | BRAD BESCOS |
| Deputy Reinf. Concrete | 6/14/2017 | No Access for Inspection | BRAD BESCOS |
| Excavation/Setback/Form/Re-Bar | 6/15/2017 | Corrections Issued | DANIEL GONZALEZ |
| Underground Mechanical | 6/15/2017 | Not Ready for Inspection | DANIEL GONZALEZ |
| Excavation/Setback/Form/Re-Bar | 6/19/2017 | Partial Approval | JOEL WILLIAMS |
| Underground Mechanical | 6/19/2017 | Partial Approval | JOEL WILLIAMS |
| Excavation/Setback/Form/Re-Bar | 7/14/2017 | Partial Approval | DANIEL GONZALEZ |
| Reinforced Concrete Frame | 7/14/2017 | Partial Approval | DANIEL GONZALEZ |
| Excavation/Setback/Form/Re-Bar | 8/14/2017 | Partial Approval | JOEL WILLIAMS |
| Footing/Foundation/Slab | 8/14/2017 | Partial Approval | JOEL WILLIAMS |
| Pre-Inspection | 4/12/2019 | Partial Inspection | RAUL BARAJAS |
| Special/Order Compliance | 4/18/2019 | Partial Inspection | DANNY TOLENTINO |
| Deputy Steel/Welding | 5/9/2019 | No Access for Inspection | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 8/9/2019 | Partial Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 10/15/2019 | Conditional Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 10/18/2019 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 10/21/2019 | Conditional Approval | RAUL BARAJAS |
| Structural Steel Frame | 3/31/2020 | Partial Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 8/20/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Special/Order Compliance | 9/17/2021 | Corrections Issued | BRAD BESCOS |
| Excavation/Setback/Form/Re-Bar | 4/4/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Piling/Pier/Caisson | 4/4/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Pre-Inspection | 4/4/2024 | Corrections Issued | RAUL BARAJAS |
| Pre-Inspection | 10/24/2024 | Corrections Issued | RAUL BARAJAS |
| Structural Steel Frame | 12/6/2024 | Permit Expired-Status Void | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 3/19/2025 | Partial Approval | ROY SPAULDING |