9509 W GLOAMING DR 90210
Certificate Information: 9509 W GLOAMING DR 90210
- Application / Permit
- 13014-20000-01660
- Plan Check / Job No.
- B13VN04927
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- RENOVATION AND ADDITION OF 271 SF TO (E) SFD
- Permit Issued
- Issued on 7/30/2013
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/26/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/2/2013 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2013 | CHON CHIO KUO |
| Corrections Issued | 5/13/2013 | CHON CHIO KUO |
| Quality Review Completed | 5/16/2013 | TAMERA SVETICH |
| Building Plans Picked Up | 5/16/2013 | APPLICANT |
| Green Plans Picked Up | 5/17/2013 | APPLICANT |
| Applicant returned to address corrections | 6/6/2013 | CHON CHIO KUO |
| Applicant returned to address corrections | 6/13/2013 | CHON CHIO KUO |
| Applicant returned to address corrections | 7/17/2013 | CHON CHIO KUO |
| Plan Check Approved | 7/24/2013 | CHON-CHIO KUO |
| Issued | 7/30/2013 | LADBS |
| CofO in Progress | 3/26/2020 | DEROLD HAUFF |
| Permit Finaled | 3/26/2020 | DEROLD HAUFF |
| CofO Issued | 3/26/2020 | DEROLD HAUFF |
| Permit Finaled | 3/26/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Specific Plan | Cleared | 6/13/2013 | COURTNEY SCHOENWALD |
| Eng Process Fee Ord 176,300 | Cleared | 6/20/2013 | AVALYN KAMACHI |
| Green Code | Cleared | 6/20/2013 | MICHAEL AYERS |
| Low Impact Development | Cleared | 6/20/2013 | IDA MEISAMI-FARD |
| Roof/Waste drainage to street | Cleared | 6/20/2013 | AVALYN KAMACHI |
| Sewer availability | Cleared | 6/20/2013 | AVALYN KAMACHI |
| Miscellaneous | Cleared | 7/17/2013 | CHON-CHIO KUO |
Contact Information
| No Data Available. |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 9/17/2013 | Partial Approval | ROBERT MINASSIANS |
| Deputy Reinf. Concrete | 9/18/2013 | Approved | ROBERT MINASSIANS |
| Piling/Pier/Caisson | 9/19/2013 | Approved | ROBERT MINASSIANS |
| Footing/Foundation/Slab | 10/11/2013 | Partial Approval | RAUL BARAJAS |
| Pre-Inspection | 9/29/2017 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 7/22/2019 | Approved | RICHARD STEINBACH |
| Gas Test | 11/21/2019 | Not Ready for Inspection | RAUL BARAJAS |
| Service/Power Release | 11/21/2019 | Not Ready for Inspection | RAUL BARAJAS |
| Service/Power Release | 12/11/2019 | Conditional Approval | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 2/13/2020 | Approved | RICHARD STEINBACH |
| ELECTRICAL-Final | 2/13/2020 | Corrections Issued | RICHARD STEINBACH |
| Final | 2/13/2020 | Corrections Issued | RICHARD STEINBACH |
| Footing/Foundation/Slab | 2/13/2020 | Approved | RICHARD STEINBACH |
| Green Building Final | 2/13/2020 | Approved | RICHARD STEINBACH |
| Green Building Rough | 2/13/2020 | Approved | RICHARD STEINBACH |
| HVAC-Final | 2/13/2020 | Corrections Issued | RICHARD STEINBACH |
| PLUMBING-Final | 2/13/2020 | Corrections Issued | RICHARD STEINBACH |
| SGSOV-Seismic Gas S/O Valve | 2/13/2020 | SGSOV Approved | RICHARD STEINBACH |
| Smoke Detectors | 2/13/2020 | Approved | RICHARD STEINBACH |
| ELECTRICAL-Final | 3/13/2020 | Approved | RICHARD STEINBACH |
| Final | 3/13/2020 | Partial Approval | RICHARD STEINBACH |
| HVAC-Final | 3/13/2020 | Not Ready for Inspection | RICHARD STEINBACH |
| PLUMBING-Final | 3/13/2020 | Approved | RICHARD STEINBACH |