430 N HIGHLAND AVE 90004

Certificate Information: 430 N HIGHLAND AVE 90004

Application / Permit
13014-10001-04867
Plan Check / Job No.
B15LA15143
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL TO 13014-10000-04867 TO INCREASE NEW BASEMENT SIZE.
Permit Issued
Issued on 2/17/2016
Issuing Office
Metro
Current Status
Permit Finaled on 5/8/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/27/2015 APPLICANT
Assigned to Plan Check Engineer 11/19/2015 PRANITA SHAH
Corrections Issued 12/14/2015 PRANITA SHAH
Quality Review Completed 12/15/2015 LAWRENCE QUIRANTE
Building Plans Picked Up 12/16/2015 APPLICANT
Applicant returned to address corrections 2/9/2016 PRANITA SHAH
Plan Check Approved 2/17/2016 PRANITA SHAH
Issued 2/17/2016 LADBS
Permit Finaled 5/8/2020 ARTHUR SARGSYAN

Permit Application Clearance Information

CPC Cleared 2/2/2016 RENATA DRAGLAND
City Hist. Cultural Monument Cleared 2/2/2016 RENATA DRAGLAND
HPOZ Cleared 2/2/2016 RENATA DRAGLAND
Historic monument Cleared 2/2/2016 RENATA DRAGLAND
Miscellaneous Cleared 2/2/2016 RENATA DRAGLAND
ZI Cleared 2/2/2016 RENATA DRAGLAND
Abandoned oil well Cleared 2/17/2016 ROBERT DUFF
Hydrant and Access approval Cleared 2/17/2016 ROBERT DUFF

Contact Information

Architect Leishman, Thomas Edward; Lic. No.: C15059 6100 DE SOTO AVENUE # 1134      WOODLAND HILLS, CA 91364
Contractor Owner-Builder       ,
Engineer Choi, David; Lic. No.: S4784 1327 LOMA AVENUE      LONG BEACH, CA 90804

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/15/2016 Conditional Approval RAUL BARAJAS
Reinforced Concrete Frame 9/15/2016 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 4/26/2017 Not Ready for Inspection DANNY TOLENTINO
Special/Order Compliance 7/12/2017 Approved DANNY TOLENTINO
Final 8/22/2018 Partial Inspection DANNY TOLENTINO
Final 3/3/2020 Not Ready for Inspection ARTHUR SARGSYAN
Footing/Foundation/Slab 3/3/2020 Not Ready for Inspection ARTHUR SARGSYAN
METHANE-Barrier 3/3/2020 Not Ready for Inspection ARTHUR SARGSYAN
METHANE-Final 3/3/2020 Not Ready for Inspection ARTHUR SARGSYAN
METHANE-Rough 3/3/2020 Not Ready for Inspection ARTHUR SARGSYAN
METHANE-Subgrade 3/3/2020 Not Ready for Inspection ARTHUR SARGSYAN
Smoke Detectors 3/3/2020 Not Ready for Inspection ARTHUR SARGSYAN
Wood Frame 3/3/2020 Not Ready for Inspection ARTHUR SARGSYAN
Special/Order Compliance 4/21/2020 Corrections Issued ARTHUR SARGSYAN