11571 W SUNSET BLVD 90049

Certificate Information: 11571 W SUNSET BLVD 90049

Application / Permit
13014-10001-02739
Plan Check / Job No.
B14LA11031
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL TO 13014-10001-02739: TO RECALCULATE FLOOR AREA AND REVISE STRUCTURAL INVENTORY FOR SQUARE FOOTAGE AND ADD (N) 2316 SF ATTACHED OPEN TRELLIS [SEE COMMENTS].
Permit Issued
Issued on 8/27/2018
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 4/15/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/27/2014 APPLICANT
Assigned to Plan Check Engineer 10/27/2014 DAWN MC NULTY
Plan Check Approved 10/27/2014 DAWN MCNULTY
No Progress 3/8/2018 DAWN MCNULTY
Plan Check Approved 8/20/2018 DAWN MCNULTY
Issued 8/27/2018 LADBS
Permit Finaled 4/14/2025 JOHN MATTILLO

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/14/2014 AVALYN KAMACHI
Green Code Cleared 10/14/2014 DAWN MCNULTY
Low Impact Development Cleared 10/14/2014 MICHAEL SCADUTO
Private street Cleared 10/14/2014 ANDY RODRIGUEZ
Roof/Waste drainage to street Cleared 10/14/2014 AVALYN KAMACHI

Contact Information

Contractor Owner-Builder       ,
Engineer , ; Lic. No.: C88998 7020 LANEWOOD AVE   #204    LOS ANGELES, CA

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 11/5/2024 Approved JOHN MATTILLO
Drywall Nailing 11/5/2024 Approved JOHN MATTILLO
FLOOD-Elevation Certificate 11/5/2024 Approved JOHN MATTILLO
FLOOD-Proofing Certificate 11/5/2024 Approved JOHN MATTILLO
Final 11/5/2024 Conditional Approval JOHN MATTILLO
Footing/Foundation/Slab 11/5/2024 Approved JOHN MATTILLO
Green Building Final 11/5/2024 Approved JOHN MATTILLO
Green Building Rough 11/5/2024 Approved JOHN MATTILLO
Smoke Detectors 11/5/2024 Approved JOHN MATTILLO
Verify Sprinkler Sign Off 11/5/2024 Approved JOHN MATTILLO
Final 4/14/2025 Permit Finaled JOHN MATTILLO