17880 W VICINO WAY 90272

Certificate Information: 17880 W VICINO WAY 90272

Application / Permit
13014-10000-02403
Plan Check / Job No.
B13LA07520
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL 1380 SF OF SOUTH PORTION OF EXISTING ONE SINGLE FAMILY RESIDENCE BY REMOVING AND REPLACING WITH NEW BASEMENT AND FIRST FLOOR AT EXISTING FOOTPRINT; ADD 34 SF TO 1ST FLOOR; INTERIOR REMODEL THROUGHOUT; NEW ROOF THROUGHOUT; <SEE COMMENTS>
Permit Issued
Issued on 2/5/2016
Issuing Office
Metro
Current Status
CofO Issued on 3/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/20/2013 APPLICANT
Assigned to Plan Check Engineer 6/27/2013 BOK GOH
Corrections Issued 6/30/2013 BOK GOH
Green Plans Picked Up 7/8/2013 APPLICANT
Quality Review Completed 7/9/2013 TIEN JEN WANG
Building Plans Picked Up 7/10/2013 APPLICANT
Applicant returned to address corrections 8/5/2014 BOK GOH
Plan Check Approved 12/28/2015 BOK GOH
Issued 2/5/2016 LADBS
CofO in Progress 2/21/2024 EVAN COOPER
CofO in Progress 3/4/2024 KENNETH NAGLE
Permit Finaled 3/9/2024 DANIEL ORRANTE
CofO Issued 3/9/2024 DANIEL ORRANTE
Permit Finaled 3/9/2024 DANIEL ORRANTE

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 8/5/2014 RICHARD SOUTHERLAND
BHO/Hillside ordinance Cleared 8/5/2014 RICHARD SOUTHERLAND
BHO/Hillside ordinance Cleared 8/5/2014 RICHARD SOUTHERLAND
BHO/Hillside ordinance Cleared 8/5/2014 RICHARD SOUTHERLAND
BHO/Hillside ordinance Cleared 8/5/2014 RICHARD SOUTHERLAND
Eng Process Fee Ord 176,300 Cleared 8/5/2014 RICHARD SOUTHERLAND
Sewer availability Cleared 8/5/2014 RICHARD SOUTHERLAND
Green Code Cleared 9/1/2015 RUSSELL KELLY
Hydrant and Access approval Cleared 11/24/2015 ROBERT DUFF
VHFHSZ Cleared 11/24/2015 ROBERT DUFF
Excavation more than 5-ft deep Cleared 12/4/2015 CALOSHA APPROVED
Low Impact Development Cleared 12/21/2015 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 12/21/2015 RAVIL MANAPOV
Coastal Zone Cleared 12/28/2015 LAURA FRAZIN-STEELE
ZA Case Cleared 12/28/2015 LAURA FRAZIN-STEELE

Contact Information

Architect Noteware, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Gibson Construction; Lic. No.: 524012-B 3000 31 STREET SUITE G      SANTA MONICA, CA 90405
Engineer Lieurance, Martin Ellis; Lic. No.: C54323 31129 VIA COLINAS 707      WESTLAKE VILLAGE, CA 91362

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/4/2016 Partial Approval VINCENT SCIPIONI
Pre-Inspection 12/23/2016 Partial Inspection VINCENT SCIPIONI
Piling/Pier/Caisson 6/20/2017 Partial Approval VINCENT SCIPIONI
Deputy Grading 6/23/2017 Conditional Approval VINCENT SCIPIONI
Piling/Pier/Caisson 6/26/2017 Partial Approval VINCENT SCIPIONI
Deputy Reinf. Concrete 6/27/2017 No Access for Inspection VINCENT SCIPIONI
Deputy Reinf. Concrete 6/28/2017 Conditional Approval VINCENT SCIPIONI
Piling/Pier/Caisson 6/28/2017 Partial Approval VINCENT SCIPIONI
Deputy Grading 7/28/2017 No Access for Inspection KENNETH NAGLE
Deputy Grading 8/23/2017 Conditional Approval VINCENT SCIPIONI
Piling/Pier/Caisson 9/27/2017 Partial Approval VINCENT SCIPIONI
Deputy Reinf. Concrete 12/27/2017 Conditional Approval VINCENT SCIPIONI
Underground Mechanical 2/1/2018 No Access for Inspection VINCENT SCIPIONI
Underground Mechanical 2/2/2018 Partial Approval VINCENT SCIPIONI
Grounding or Bonding 6/15/2018 Partial Approval JOHN LUMB
Footing/Foundation/Slab 4/30/2020 Partial Inspection ANDREW NAVE
Piling/Pier/Caisson 5/6/2020 Approved ANDREW NAVE
Footing/Foundation/Slab 6/16/2020 Partial Inspection ANDREW NAVE
Footing/Foundation/Slab 6/17/2020 Partial Approval ANDREW NAVE
Special/Order Compliance 7/13/2020 Approved ANDREW NAVE
Footing/Foundation/Slab 7/27/2020 Partial Approval ANDREW NAVE
Deputy Steel/Welding 8/11/2020 Conditional Approval ANDREW NAVE
Deputy Steel/Welding 8/12/2020 Conditional Approval ANDREW NAVE
Footing/Foundation/Slab 8/12/2020 Partial Approval ANDREW NAVE
Deputy Steel/Welding 8/13/2020 Approved ROBERT SHELLY
Deputy Steel/Welding 8/14/2020 Conditional Approval ANDREW NAVE
Footing/Foundation/Slab 8/20/2020 Partial Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 10/5/2020 Partial Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 10/30/2020 Partial Approval ANDREW NAVE
BUILDING-Rough-Frame 11/13/2020 Not Ready for Inspection ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 11/13/2020 Partial Inspection ANDREW NAVE
PLUMBING-Rough 3/15/2021 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 3/24/2021 Partial Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 3/26/2021 Partial Inspection ANDREW NAVE
Insulation 5/6/2021 Partial Approval ANDREW NAVE
Drywall Nailing 6/7/2021 Partial Approval ANDREW NAVE
PLUMBING-Rough 8/13/2021 Partial Approval ANDREW NAVE
PLUMBING-Rough 8/30/2021 Partial Approval ANDREW NAVE
PLUMBING-Rough 8/31/2021 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 9/13/2021 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 9/21/2021 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 9/24/2021 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 9/29/2021 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 10/6/2021 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 10/28/2021 Partial Approval ANDREW NAVE
ELECTRICAL-Rough 11/10/2021 Partial Approval ANDREW NAVE
HVAC-Rough 11/10/2021 Partial Approval ANDREW NAVE
Insulation 11/15/2021 Partial Approval KENNETH NAGLE
Deputy Steel/Welding 11/17/2021 Approved ANDREW NAVE
Footing/Foundation/Slab 11/17/2021 Partial Approval ANDREW NAVE
Insulation 11/29/2021 Partial Approval STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 12/8/2021 Partial Approval ANDREW NAVE
PLUMBING-Rough 12/8/2021 Partial Approval ANDREW NAVE
BUILDING-Rough-Frame 1/5/2022 Partial Approval ANDREW NAVE
Drywall Nailing 1/5/2022 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 1/11/2022 Approved JOHN KIDWELL
Shower Pan 1/21/2022 Approved JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 1/26/2022 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 2/4/2022 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 2/11/2022 Partial Approval ANDREW NAVE
Excavation/Setback/Form/Re-Bar 2/24/2022 Approved ANDREW NAVE
Interior/Exterior Lathing 2/24/2022 Corrections Issued ANDREW NAVE
Interior/Exterior Lathing 3/16/2022 Partial Approval ANDREW NAVE
Excavation/Setback/Form/Re-Bar 3/29/2022 Approved ANDREW NAVE
Interior/Exterior Lathing 4/5/2022 Partial Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 5/2/2022 Approved ANDREW NAVE
HVAC-Rough 8/25/2022 Partial Approval BRENDAN LOONEY
PLUMBING-Rough 8/25/2022 Approved BRENDAN LOONEY
Interior/Exterior Lathing 9/6/2022 Partial Approval KENNETH NAGLE
ELECTRICAL-Rough 9/15/2022 Partial Approval BRENDAN LOONEY
BUILDING-Rough-Frame 10/7/2022 Approved BRENDAN LOONEY
Green Building Rough 10/7/2022 Approved BRENDAN LOONEY
Insulation 10/18/2022 Approved BRENDAN LOONEY
Interior/Exterior Lathing 10/18/2022 Partial Approval BRENDAN LOONEY
Shower Pan 10/18/2022 Corrections Issued BRENDAN LOONEY
Shower Pan 11/2/2022 Not Ready for Inspection BRENDAN LOONEY
Drywall Nailing 11/3/2022 Partial Approval KENNETH NAGLE
Interior/Exterior Lathing 11/10/2022 Approved BRENDAN LOONEY
Shower Pan 11/10/2022 Approved BRENDAN LOONEY
Drywall Nailing 12/6/2022 Approved BRENDAN LOONEY
Gas Test 12/7/2022 Approved BRENDAN LOONEY
Pre-Inspection 5/10/2023 Approved GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 5/11/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Masonry Wall/Backfill 5/24/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Final 9/5/2023 Approved EVAN COOPER
ELECTRICAL-Final 9/6/2023 Approved EVAN COOPER
HVAC-Final 9/15/2023 Conditional Approval KENNETH NAGLE
Final 12/19/2023 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 12/19/2023 Approved EVAN COOPER
Green Building Final 12/19/2023 Not Ready for Inspection EVAN COOPER
SGSOV-Seismic Gas S/O Valve 12/19/2023 SGSOV Approved EVAN COOPER
Smoke Detectors 12/19/2023 Approved EVAN COOPER
Final 1/9/2024 Corrections Issued EVAN COOPER
Green Building Final 1/9/2024 Approved EVAN COOPER
Final 1/11/2024 Not Ready for Inspection EVAN COOPER
Final 2/9/2024 Conditional Approval EVAN COOPER
Final 2/12/2024 Conditional Approval EVAN COOPER
Final 2/14/2024 OK to Issue CofO EVAN COOPER