527 W ELBERON AVE 90731
Certificate Information: 527 W ELBERON AVE 90731
- Application / Permit
- 13010-70000-04588
- Plan Check / Job No.
- B13SL01703
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SFD W/ATT GARAGE (3 BEDROOMS, 3 BATHROOMS). FULLY SPRINKLERED WITH NFPA-13D.
- Permit Issued
- Issued on 12/29/2017
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/7/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2013 | APPLICANT |
| Assigned to Plan Check Engineer | 1/22/2014 | VERONICA LOPEZ |
| Corrections Issued | 1/22/2014 | VERONICA LOPEZ |
| Quality Review Completed | 1/23/2014 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 3/14/2014 | VERONICA LOPEZ |
| Applicant returned to address corrections | 6/8/2016 | VERONICA LOPEZ |
| Plan Check Approved | 12/29/2017 | VERONICA LOPEZ |
| Issued | 12/29/2017 | LADBS |
| Permit Expired-Status Void | 8/6/2019 | DEROLD HAUFF |
| Re-Activate Permit | 11/4/2019 | RONALD MYRICK |
| CofO in Progress | 4/11/2021 | JOHN KLARIN |
| Permit Finaled | 6/7/2021 | DEROLD HAUFF |
| CofO Issued | 6/7/2021 | DEROLD HAUFF |
| Permit Finaled | 6/7/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 1/23/2014 | JOHN DALLAS |
| Address approval | Cleared | 2/3/2014 | ARMENIA HERNANDEZ |
| BHO/Hillside ordinance | Cleared | 2/3/2014 | ARMENIA HERNANDEZ |
| BHO/Hillside ordinance | Cleared | 2/3/2014 | ARMENIA HERNANDEZ |
| BHO/Hillside ordinance | Cleared | 2/3/2014 | ARMENIA HERNANDEZ |
| BHO/Hillside ordinance | Cleared | 2/3/2014 | ARMENIA HERNANDEZ |
| BHO/Hillside ordinance | Cleared | 2/3/2014 | ARMENIA HERNANDEZ |
| CPC | Cleared | 2/3/2014 | ALFREDO PEREZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2014 | ARMENIA HERNANDEZ |
| Permit | Cleared | 2/3/2014 | ARMENIA HERNANDEZ |
| Roof/Waste drainage to street | Cleared | 2/3/2014 | ARMENIA HERNANDEZ |
| Sewer availability | Cleared | 2/3/2014 | ARMENIA HERNANDEZ |
| Work Adjacent to Public Way | Cleared | 2/3/2014 | ARMENIA HERNANDEZ |
| Project located in CRA area | Cleared | 3/2/2016 | JIM URQUHART |
| Miscellaneous | Cleared | 3/29/2016 | PHILLIP WILSON |
| Grading Pre-Inspection | Cleared | 4/22/2016 | TIMOTHY POWELL |
| Mailing Labels | Cleared | 4/22/2016 | GEORGE KUC |
| Green Code | Cleared | 5/16/2016 | MARCUS LEVIAS |
| Low Impact Development | Cleared | 6/7/2016 | RYAN HUDSON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Madero, Fidencio Jr; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/21/2019 | Not Ready for Inspection | PAUL BECKER |
| Special/Order Compliance | 6/21/2019 | Approved | PAUL BECKER |
| Excavation/Setback/Form/Re-Bar | 7/26/2019 | Corrections Issued | ANSON MAGLASANG |
| Footing/Foundation/Slab | 7/26/2019 | Corrections Issued | ANSON MAGLASANG |
| Special/Order Compliance | 7/26/2019 | Corrections Issued | ANSON MAGLASANG |
| Footing/Foundation/Slab | 3/20/2020 | Corrections Issued | ANSON MAGLASANG |
| Special/Order Compliance | 3/20/2020 | Corrections Issued | WILLIAM ROSE |
| Footing/Foundation/Slab | 3/26/2020 | Partial Approval | JOHN KLARIN |
| Insulation | 7/8/2020 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 7/8/2020 | Not Ready for Inspection | JOHN KLARIN |
| Wood Frame | 7/8/2020 | Corrections Issued | JOHN KLARIN |
| Insulation | 8/3/2020 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 8/3/2020 | Approved | JOHN KLARIN |
| Wood Frame | 8/3/2020 | Partial Inspection | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2020 | Partial Inspection | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2020 | Partial Approval | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2020 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 11/2/2020 | Not Ready for Inspection | JOHN KLARIN |
| MERV13>=Rough | 11/2/2020 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Rough | 11/6/2020 | Approved | JOHN KLARIN |
| Green Building Rough | 11/6/2020 | Approved | JOHN KLARIN |
| HVAC-Rough | 11/6/2020 | Approved | JOHN KLARIN |
| Insulation | 11/6/2020 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 11/6/2020 | Approved | JOHN KLARIN |
| Rough-Elec/Plmb/HVAC | 11/6/2020 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 11/6/2020 | Approved | JOHN KLARIN |
| Drywall Nailing | 11/17/2020 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 11/17/2020 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 3/22/2021 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 3/22/2021 | Approved | JOHN KLARIN |
| Final | 3/22/2021 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 3/22/2021 | Approved | JOHN KLARIN |
| Green Building Final | 3/22/2021 | Approved | JOHN KLARIN |
| HVAC-Final | 3/22/2021 | Approved | JOHN KLARIN |
| MERV13>=Final | 3/22/2021 | Approved | JOHN KLARIN |
| MERV13>=Rough | 3/22/2021 | Approved | JOHN KLARIN |
| PLUMBING-Final | 3/22/2021 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 3/22/2021 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 3/22/2021 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 3/22/2021 | Approved | JOHN KLARIN |
| Final | 4/7/2021 | OK to Issue CofO | JOHN KLARIN |
| Service/Power Release | 4/7/2021 | Approved | JOHN KLARIN |
| Special/Order Compliance | 5/18/2021 | Partial Approval | JOHN KLARIN |
| Masonry Wall/Backfill | 5/25/2021 | Approved | JOHN KLARIN |