Pre-Inspection
|
4/20/2017
|
Partial Inspection
|
GREGORY POMISH
|
|
Footing/Foundation/Slab
|
8/30/2017
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
METHANE-Barrier
|
8/30/2017
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
METHANE-Subgrade
|
8/30/2017
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
10/18/2017
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
10/20/2017
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Methane Barrier
|
12/4/2017
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Methane Barrier
|
12/5/2017
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Methane Barrier
|
12/6/2017
|
Conditional Approval
|
GREGORY POMISH
|
|
Footing/Foundation/Slab
|
12/7/2017
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
METHANE-Barrier
|
12/7/2017
|
Partial Inspection
|
GREGORY POMISH
|
|
METHANE-Subgrade
|
12/7/2017
|
Partial Inspection
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
12/13/2017
|
Conditional Approval
|
GREGORY POMISH
|
|
Footing/Foundation/Slab
|
12/13/2017
|
Partial Approval
|
GREGORY POMISH
|
|
METHANE-Barrier
|
12/13/2017
|
Partial Approval
|
GREGORY POMISH
|
|
METHANE-Subgrade
|
12/13/2017
|
Partial Approval
|
GREGORY POMISH
|
|
Deputy Methane Barrier
|
1/25/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Methane Barrier
|
1/26/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
METHANE-Barrier
|
1/29/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
2/2/2018
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
2/2/2018
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
2/2/2018
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
2/2/2018
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
2/9/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
2/12/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Footing/Foundation/Slab
|
2/12/2018
|
Partial Approval
|
GREGORY POMISH
|
|
METHANE-Barrier
|
2/12/2018
|
Partial Approval
|
GREGORY POMISH
|
|
METHANE-Subgrade
|
2/12/2018
|
Partial Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
2/13/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
3/6/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Footing/Foundation/Slab
|
3/6/2018
|
Partial Approval
|
GREGORY POMISH
|
|
METHANE-Barrier
|
3/6/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
METHANE-Subgrade
|
3/6/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
3/7/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Shotcrete
|
3/8/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Shotcrete
|
3/12/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Shotcrete
|
3/13/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Shotcrete
|
3/15/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Green Building Rough
|
3/15/2018
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
METHANE-Rough
|
3/15/2018
|
Partial Approval
|
GREGORY POMISH
|
|
Reinforced Masonry Frame
|
3/15/2018
|
Partial Approval
|
GREGORY POMISH
|
|
Verify Sprinkler Sign Off
|
3/15/2018
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Deputy Shotcrete
|
3/16/2018
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
3/16/2018
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Barrier
|
3/16/2018
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
METHANE-Subgrade
|
3/16/2018
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Deputy Shotcrete
|
3/20/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Shotcrete
|
3/21/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Footing/Foundation/Slab
|
3/21/2018
|
Partial Approval
|
GREGORY POMISH
|
|
METHANE-Barrier
|
3/21/2018
|
Approved
|
GREGORY POMISH
|
|
METHANE-Subgrade
|
3/21/2018
|
Approved
|
GREGORY POMISH
|
|
Deputy Reinf. Masonry
|
4/2/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Masonry
|
4/3/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Masonry
|
4/4/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Masonry
|
4/5/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Masonry
|
4/6/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Masonry
|
4/9/2018
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Reinforced Concrete Frame
|
4/9/2018
|
Not Ready for Inspection
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Masonry
|
4/10/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Footing/Foundation/Slab
|
4/10/2018
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Deputy Reinf. Masonry
|
4/11/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Green Building Rough
|
4/11/2018
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
METHANE-Rough
|
4/11/2018
|
Approved
|
GREGORY POMISH
|
|
Reinforced Masonry Frame
|
4/11/2018
|
Partial Approval
|
GREGORY POMISH
|
|
Verify Sprinkler Sign Off
|
4/11/2018
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Deputy Reinf. Masonry
|
4/12/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
5/1/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Footing/Foundation/Slab
|
5/1/2018
|
Partial Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
5/2/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Masonry
|
5/8/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Footing/Foundation/Slab
|
5/8/2018
|
Partial Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Masonry
|
5/9/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Masonry
|
5/11/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Masonry
|
5/15/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Masonry
|
5/16/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Masonry Wall/Backfill
|
5/16/2018
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Deputy Reinf. Masonry
|
5/17/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Masonry
|
5/18/2018
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Masonry Wall/Backfill
|
5/18/2018
|
Partial Approval
|
DAVID BURKHEAD
|
|
Masonry Wall/Backfill
|
5/21/2018
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Masonry
|
5/22/2018
|
Conditional Approval
|
LARRY ARNICK
|
|
Footing/Foundation/Slab
|
5/25/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Deputy Reinf. Masonry
|
5/29/2018
|
Conditional Approval
|
LARRY ARNICK
|
|
Masonry Wall/Backfill
|
5/29/2018
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Masonry
|
5/30/2018
|
Conditional Approval
|
LARRY ARNICK
|
|
Footing/Foundation/Slab
|
5/30/2018
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
6/1/2018
|
Conditional Approval
|
LARRY ARNICK
|
|
Masonry Wall/Backfill
|
6/5/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Deputy Reinf. Masonry
|
6/7/2018
|
Conditional Approval
|
LARRY ARNICK
|
|
Masonry Wall/Backfill
|
6/14/2018
|
Approved
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
6/19/2018
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
6/21/2018
|
Conditional Approval
|
LARRY ARNICK
|
|
Footing/Foundation/Slab
|
6/21/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Masonry Wall/Backfill
|
6/22/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Footing/Foundation/Slab
|
6/23/2018
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
6/25/2018
|
Conditional Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
7/11/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
7/11/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
7/11/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Green Building Rough
|
7/23/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
7/23/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
7/23/2018
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
7/27/2018
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Wood Construction
|
8/8/2018
|
Conditional Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
8/8/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
8/8/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
8/8/2018
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/27/2018
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
8/27/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
8/27/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
8/27/2018
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Wood Construction
|
8/28/2018
|
Conditional Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/28/2018
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/20/2018
|
Partial Approval
|
LARRY ARNICK
|
|
Footing/Foundation/Slab
|
9/20/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Footing/Foundation/Slab
|
9/26/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Footing/Foundation/Slab
|
10/1/2018
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Masonry Wall/Backfill
|
10/3/2018
|
Approved
|
LARRY ARNICK
|
|
Drywall Nailing
|
10/10/2018
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Green Building Rough
|
10/10/2018
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/12/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Deputy Drilled-In Anchors
|
10/16/2018
|
Conditional Approval
|
LARRY ARNICK
|
|
Masonry Wall/Backfill
|
10/23/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/24/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Deputy Wood Construction
|
11/1/2018
|
Conditional Approval
|
GREGORY POMISH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/1/2018
|
Partial Approval
|
JEFF BYTHEWAY
|
|
Deputy Wood Construction
|
11/16/2018
|
Conditional Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
11/16/2018
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/16/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Green Building Rough
|
11/16/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/20/2018
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
12/5/2018
|
Partial Approval
|
TED RIES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/5/2018
|
Not Ready for Inspection
|
TED RIES
|
|
Green Building Rough
|
12/5/2018
|
Not Ready for Inspection
|
TED RIES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/14/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/18/2018
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/19/2018
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Drilled-In Anchors
|
12/26/2018
|
Conditional Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/26/2018
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Drywall Nailing
|
1/2/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/2/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Green Building Rough
|
1/2/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Insulation
|
1/3/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/24/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/25/2019
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Deputy Wood Construction
|
1/28/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
1/29/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Wood Construction
|
2/12/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/12/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
2/19/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
2/22/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
2/22/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/11/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
3/11/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
3/15/2019
|
Approved
|
LARRY ARNICK
|
|
Deputy Wood Construction
|
3/19/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/19/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
3/19/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/20/2019
|
Approved
|
LARRY ARNICK
|
|
Drywall Nailing
|
3/21/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
3/21/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Drywall Nailing
|
3/22/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
3/22/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
4/10/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
4/11/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
4/18/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
4/22/2019
|
Approved
|
LARRY ARNICK
|
|
Insulation
|
4/22/2019
|
Approved
|
LARRY ARNICK
|
|
Wood Frame
|
4/23/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Final
|
4/25/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Insulation
|
4/25/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Insulation
|
4/26/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
4/30/2019
|
Not Ready for Inspection
|
HAMID PISHEHVAR
|
|
Green Building Final
|
4/30/2019
|
Approved
|
HAMID PISHEHVAR
|
|
Insulation
|
4/30/2019
|
Partial Approval
|
HAMID PISHEHVAR
|
|
Insulation
|
5/2/2019
|
Partial Approval
|
DERRICK SPENCER
|
|
Drywall Nailing
|
5/8/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
5/15/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
5/17/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
5/22/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
5/23/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
5/28/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
5/28/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
5/29/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Drywall Nailing
|
5/30/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
5/30/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Drywall Nailing
|
6/3/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
6/3/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
6/7/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Drywall Nailing
|
6/11/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
6/11/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Drywall Nailing
|
6/12/2019
|
Approved
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
6/12/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
6/20/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
6/21/2019
|
Partial Inspection
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Masonry
|
7/26/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
8/7/2019
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Insulation
|
8/7/2019
|
Partial Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
8/8/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
8/9/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
8/13/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/13/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Footing/Foundation/Slab
|
8/13/2019
|
Approved
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/16/2019
|
Approved
|
LARRY ARNICK
|
|
Deputy Wood Construction
|
8/19/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/20/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
8/30/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
9/4/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
9/6/2019
|
Approved
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
9/10/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Reinforced Concrete Frame
|
9/20/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Reinforced Masonry Frame
|
9/20/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
9/20/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Final
|
1/9/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Reinforced Concrete Frame
|
1/9/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Reinforced Masonry Frame
|
1/9/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
SGSOV-Seismic Gas S/O Valve
|
1/9/2020
|
SGSOV Approved
|
LARRY ARNICK
|
|
Smoke Detectors
|
1/9/2020
|
Approved
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
1/9/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
1/9/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
T-Bar Ceiling
|
1/12/2020
|
Approved
|
LARRY ARNICK
|
|
Green Building Final
|
1/13/2020
|
Approved
|
LARRY ARNICK
|
|
Masonry Wall/Backfill
|
1/13/2020
|
Approved
|
LARRY ARNICK
|
|
Reinforced Concrete Frame
|
1/13/2020
|
Approved
|
LARRY ARNICK
|
|
Smoke Detectors
|
1/13/2020
|
Approved
|
LARRY ARNICK
|
|
T-Bar Ceiling
|
1/13/2020
|
Approved
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
1/13/2020
|
Approved
|
LARRY ARNICK
|
|
Wall Anchors
|
1/13/2020
|
Approved
|
LARRY ARNICK
|
|
Wood Frame
|
1/13/2020
|
Approved
|
LARRY ARNICK
|
|
Final
|
1/16/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Reinforced Concrete Frame
|
1/16/2020
|
Approved
|
LARRY ARNICK
|
|
Reinforced Masonry Frame
|
1/16/2020
|
Approved
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
1/16/2020
|
Approved
|
LARRY ARNICK
|
|
Wood Frame
|
1/16/2020
|
Approved
|
LARRY ARNICK
|
|
Final
|
2/5/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|