3935 N HOPEVALE DR 91403
Certificate Information: 3935 N HOPEVALE DR 91403
- Application / Permit
- 13010-30000-02523
- Plan Check / Job No.
- B13WL03043
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (n) 2-story s.f.d. w/ basement & garage
- Permit Issued
- Issued on 2/2/2018
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 2/2/2018
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/21/2013 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2013 | MARJAN SHENASI |
| Corrections Issued | 9/12/2013 | MARJAN SHENASI |
| Quality Review Completed | 9/18/2013 | RUDOLF KINAR MELIKOFF |
| Building Plans Picked Up | 9/23/2013 | APPLICANT |
| Green Plans Picked Up | 9/23/2013 | APPLICANT |
| Applicant returned to address corrections | 4/17/2014 | MARJAN SHENASI |
| Applicant returned to address corrections | 4/23/2014 | MARJAN SHENASI |
| Applicant returned to address corrections | 4/29/2014 | MARJAN SHENASI |
| Applicant returned to address corrections | 5/2/2014 | MARJAN SHENASI |
| Applicant returned to address corrections | 5/14/2014 | MARJAN SHENASI |
| Applicant returned to address corrections | 5/30/2014 | MARJAN SHENASI |
| Applicant returned to address corrections | 6/26/2014 | MARJAN SHENASI |
| Applicant returned to address corrections | 7/31/2014 | MARJAN SHENASI |
| Applicant returned to address corrections | 8/27/2014 | MARJAN SHENASI |
| Applicant returned to address corrections | 9/5/2014 | MARJAN SHENASI |
| Applicant returned to address corrections | 9/12/2014 | MARJAN SHENASI |
| Applicant returned to address corrections | 10/6/2014 | MARJAN SHENASI |
| Applicant returned to address corrections | 10/21/2014 | MARJAN SHENASI |
| Applicant returned to address corrections | 10/24/2014 | MARJAN SHENASI |
| Applicant returned to address corrections | 11/18/2014 | MARJAN SHENASI |
| Applicant returned to address corrections | 4/15/2015 | MARJAN SHENASI |
| Applicant returned to address corrections | 4/22/2015 | MARJAN SHENASI |
| Applicant returned to address corrections | 7/28/2015 | MARJAN SHENASI |
| Applicant returned to address corrections | 12/23/2015 | MARJAN SHENASI |
| Plan Check Approved | 1/12/2018 | HERNAN ARREOLA |
| Issued | 2/2/2018 | LADBS |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 12/16/2013 | DAVID RILES |
| Address approval | Cleared | 12/17/2013 | HOWARD COOPER |
| BHO/Hillside ordinance | Cleared | 12/17/2013 | MIKE KOUYOUMDJIAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/17/2013 | MIKE KOUYOUMDJIAN |
| Miscellaneous | Cleared | 12/17/2013 | MIKE KOUYOUMDJIAN |
| Work Adjacent to Public Way | Cleared | 12/17/2013 | MIKE KOUYOUMDJIAN |
| BHO/Hillside ordinance | Cleared | 4/4/2014 | KATHLEEN HUGHEY |
| BHO/Hillside ordinance | Cleared | 4/4/2014 | KATHLEEN HUGHEY |
| BHO/Hillside ordinance | Cleared | 4/4/2014 | KATHLEEN HUGHEY |
| Miscellaneous | Cleared | 4/4/2014 | DENNIS CHEW |
| Miscellaneous | Cleared | 4/4/2014 | KATHLEEN HUGHEY |
| Permit | Cleared | 4/4/2014 | DENNIS BRAGIN |
| Miscellaneous | Cleared | 4/7/2014 | DENNIS CHEW |
| Stormwater Pollution Mitigatn | Cleared | 4/21/2014 | MARTIN FRAGOSO |
| Excavation more than 5-ft deep | Cleared | 4/23/2014 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 4/23/2014 | MARJAN SHENASI |
| Roof/Waste drainage to street | Cleared | 4/23/2014 | TAO YANG |
| BHO/Hillside ordinance | Cleared | 4/24/2014 | TAO YANG |
| Sewer availability | Cleared | 4/24/2014 | TAO YANG |
| Green Code | Cleared | 7/9/2015 | RICHARD GARCIA |
Contact Information
| Contractor | Melt Construction Inc; Lic. No.: 996599-B | 245 EAST OLIVE AVENUE 4TH FL BURBANK, CA 91502 |
| Engineer | Markarian, Mardiros; Lic. No.: C53434 | 3814 VANALDEN AVE TARZANA, CA 91356 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/12/2019 | Partial Approval | CHRISTOPHE COCHRAN |
| Deputy Reinf. Concrete | 7/19/2019 | Conditional Approval | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 7/24/2019 | Partial Approval | CHRISTOPHE COCHRAN |
| Deputy Reinf. Concrete | 7/25/2019 | Conditional Approval | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 9/5/2019 | Partial Approval | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 9/18/2019 | Partial Approval | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 10/4/2019 | Partial Approval | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 10/4/2019 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 10/28/2019 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 10/30/2019 | Partial Approval | JEFFREY PARD |
| Footing/Foundation/Slab | 11/12/2019 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2020 | Partial Approval | CHRISTOPHE COCHRAN |
| Green Building Rough | 2/20/2020 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 2/20/2020 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 9/14/2020 | Corrections Issued | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2020 | Partial Approval | CHARLES POWELL |
| PLUMBING-Rough | 9/14/2020 | Corrections Issued | CHARLES POWELL |
| PLUMBING-Rough | 9/16/2020 | Partial Approval | CHARLES POWELL |
| BUILDING-Rough-Frame | 10/16/2020 | Not Ready for Inspection | CHARLES POWELL |
| ELECTRICAL-Rough | 10/16/2020 | Corrections Issued | CHARLES POWELL |
| Green Building Rough | 10/16/2020 | Not Ready for Inspection | CHARLES POWELL |
| HVAC-Rough | 10/16/2020 | Approved | CHARLES POWELL |
| Verify Sprinkler Sign Off | 10/16/2020 | Not Ready for Inspection | CHARLES POWELL |
| BUILDING-Rough-Frame | 10/30/2020 | Approved | CHARLES POWELL |
| Green Building Rough | 10/30/2020 | Not Ready for Inspection | CHARLES POWELL |
| Verify Sprinkler Sign Off | 10/30/2020 | Approved | CHARLES POWELL |
| Insulation | 11/9/2020 | Approved | CHARLES POWELL |
| Interior/Exterior Lathing | 11/13/2020 | Not Ready for Inspection | CHARLES POWELL |
| Deck | 11/18/2020 | Approved | CHARLES POWELL |
| Drywall Nailing | 11/18/2020 | Approved | CHARLES POWELL |
| Green Building Rough | 11/18/2020 | Approved | CHARLES POWELL |
| Interior/Exterior Lathing | 11/18/2020 | Partial Approval | CHARLES POWELL |
| Interior/Exterior Lathing | 12/1/2020 | Approved | CHARLES POWELL |
| Service/Power Release | 1/23/2026 | Approved | JACK KARGODORIAN |
| Final | 2/23/2026 | Order to Comply Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 2/23/2026 | Approved | JACK KARGODORIAN |
| Green Building Final | 2/23/2026 | Approved | JACK KARGODORIAN |
| Reinforced Concrete Frame | 2/23/2026 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 2/23/2026 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 2/23/2026 | Approved | JACK KARGODORIAN |
| Final | 3/6/2026 | Not Ready for Inspection | MICHAEL CORTEZ |