4140 S GLENCOE AVE 90292
Certificate Information: 4140 S GLENCOE AVE 90292
- Application / Permit
- 13010-20002-00027
- Plan Check / Job No.
- B14VN12459
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Supplemental to #13010-10000-00027: Revisions to the foundation plan
- Permit Issued
- Issued on 2/6/2015
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 1/10/2017
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 10/7/2014 | APPLICANT |
Disabled Access Plans Picked Up | 10/22/2014 | APPLICANT |
Assigned to Plan Check Engineer | 10/23/2014 | BINH PHAN |
Corrections Issued | 10/28/2014 | BINH PHAN |
Quality Review Completed | 10/29/2014 | SHAHEN AKELYAN |
Building Plans Picked Up | 10/31/2014 | APPLICANT |
Plan Check Approved | 2/6/2015 | BINH PHAN |
Issued | 2/6/2015 | LADBS |
Permit Finaled | 1/10/2017 | NICK LAROCCA |
Permit Application Clearance Information
Miscellaneous | Cleared | 1/30/2015 | RICK TORRES |
Specific Plan | Cleared | 1/30/2015 | RICK TORRES |
Tract Map conditions | Cleared | 1/30/2015 | RICK TORRES |
Miscellaneous | Cleared | 2/4/2015 | DENNIS CHEW |
DAS Clearance | Cleared | 2/5/2015 | WAI LAU |
Contact Information
Architect | Kudelka, Phillip Roman; Lic. No.: C19548 | 22663 COLLINS STREET PK ARCHITECTURE WOODLAND HILLS, CA 91367 |
Contractor | Owner-Builder | , |
Engineer | Babayan, Raffi Samuel; Lic. No.: C72168 | 1140 N COLUMBUS AVE 112 GLENDALE, CA 91202 |
Engineer | Dejban, Masoud; Lic. No.: S2521 | 17200 VENTURA BLVD STE 213A ENCINO, CA 91316 |
Engineer | Zweigler, Robert Ingraham; Lic. No.: GE2120 | 1461 E. CHEVY CHASE DR. #200 GLENDALE, CA 91206 |
Inspector Information
VASIL MIHALEV, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Footing/Foundation/Slab | 2/9/2015 | Partial Approval | NICK LAROCCA |
Masonry Wall/Backfill | 2/19/2015 | Corrections Issued | JASON MARKOWSKI |
Masonry Wall/Backfill | 2/19/2015 | Not Ready for Inspection | MAURICE MARTINEZ |
Masonry Wall/Backfill | 2/20/2015 | Not Ready for Inspection | MAURICE MARTINEZ |
Footing/Foundation/Slab | 2/23/2015 | Not Ready for Inspection | JASON MARKOWSKI |
Reinforced Concrete Frame | 2/23/2015 | Not Ready for Inspection | JASON MARKOWSKI |
Footing/Foundation/Slab | 2/24/2015 | Partial Approval | JASON MARKOWSKI |
Deputy Reinf. Concrete | 2/25/2015 | No Access for Inspection | TERRY DRIBIN |
Footing/Foundation/Slab | 2/27/2015 | Conditional Approval | MAURICE MARTINEZ |
Footing/Foundation/Slab | 2/27/2015 | Partial Approval | JASON MARKOWSKI |
Deputy Reinf. Concrete | 3/2/2015 | Conditional Approval | MAURICE MARTINEZ |
Masonry Wall/Backfill | 3/2/2015 | Conditional Approval | MAURICE MARTINEZ |
Masonry Wall/Backfill | 3/3/2015 | Conditional Approval | MAURICE MARTINEZ |
Masonry Wall/Backfill | 3/4/2015 | Conditional Approval | MAURICE MARTINEZ |
Masonry Wall/Backfill | 3/6/2015 | Partial Approval | MAURICE MARTINEZ |
Masonry Wall/Backfill | 3/9/2015 | Conditional Approval | MAURICE MARTINEZ |
Deputy Reinf. Concrete | 4/6/2015 | Conditional Approval | MAURICE MARTINEZ |
Footing/Foundation/Slab | 4/6/2015 | Conditional Approval | MAURICE MARTINEZ |
Deputy Reinf. Concrete | 4/7/2015 | Conditional Approval | MAURICE MARTINEZ |
Footing/Foundation/Slab | 4/7/2015 | Conditional Approval | MAURICE MARTINEZ |
Deputy Reinf. Concrete | 4/8/2015 | Conditional Approval | MAURICE MARTINEZ |
Deputy Reinf. Concrete | 4/15/2015 | Conditional Approval | MAURICE MARTINEZ |
Reinforced Concrete Frame | 4/15/2015 | Partial Approval | MAURICE MARTINEZ |
Reinforced Concrete Frame | 4/16/2015 | Corrections Issued | MAURICE MARTINEZ |
Deputy Reinf. Concrete | 4/17/2015 | Conditional Approval | MAURICE MARTINEZ |
Deputy Reinf. Concrete | 4/21/2015 | Conditional Approval | DAVID TSAU |
Footing/Foundation/Slab | 4/21/2015 | Partial Approval | DAVID TSAU |
Deputy Reinf. Concrete | 4/24/2015 | Conditional Approval | DAVID TSAU |
Deputy Reinf. Concrete | 5/11/2015 | Conditional Approval | DAVID TSAU |
Deputy Reinf. Concrete | 5/12/2015 | Conditional Approval | DAVID TSAU |
Deputy Reinf. Concrete | 5/13/2015 | Approved | DAVID TSAU |
Footing/Foundation/Slab | 5/13/2015 | Partial Approval | DAVID TSAU |
Deputy Reinf. Concrete | 5/14/2015 | Approved | DAVID TSAU |
Footing/Foundation/Slab | 5/14/2015 | Partial Approval | DAVID TSAU |
Deputy Reinf. Masonry | 5/19/2015 | Conditional Approval | DAVID TSAU |
Deputy Reinf. Masonry | 5/20/2015 | Conditional Approval | MAURICE MARTINEZ |
Footing/Foundation/Slab | 5/20/2015 | Partial Approval | MAURICE MARTINEZ |
Reinforced Concrete Frame | 5/20/2015 | Partial Approval | MAURICE MARTINEZ |
Reinforced Masonry Frame | 5/20/2015 | Partial Approval | MAURICE MARTINEZ |
Deputy Reinf. Masonry | 5/21/2015 | Conditional Approval | DAVID TSAU |
Deputy Reinf. Concrete | 5/22/2015 | Conditional Approval | DAVID TSAU |
Deputy Reinf. Concrete | 6/4/2015 | Conditional Approval | DAVID TSAU |
Deputy Reinf. Concrete | 6/5/2015 | Conditional Approval | DAVID TSAU |
Deputy Reinf. Concrete | 6/8/2015 | Conditional Approval | DAVID TSAU |
Deputy Reinf. Concrete | 6/9/2015 | Approved | DAVID TSAU |
Footing/Foundation/Slab | 6/9/2015 | Partial Inspection | DAVID TSAU |
Reinforced Concrete Frame | 6/9/2015 | Partial Inspection | DAVID TSAU |
Deputy Reinf. Concrete | 6/10/2015 | Approved | DAVID TSAU |
Reinforced Concrete Frame | 6/10/2015 | Partial Approval | DAVID TSAU |
Deputy Reinf. Concrete | 6/11/2015 | Approved | DAVID TSAU |
Reinforced Concrete Frame | 6/11/2015 | Partial Inspection | DAVID TSAU |
Reinforced Masonry Frame | 6/11/2015 | Partial Approval | DAVID TSAU |
Deputy Reinf. Concrete | 6/12/2015 | Approved | DAVID TSAU |
Deputy Reinf. Concrete | 6/25/2015 | Conditional Approval | DAVID TSAU |
Deputy Reinf. Concrete | 6/26/2015 | Approved | DAVID TSAU |
Footing/Foundation/Slab | 6/26/2015 | Partial Approval | DAVID TSAU |
Reinforced Concrete Frame | 6/26/2015 | Not Ready for Inspection | DAVID TSAU |
Reinforced Masonry Frame | 6/29/2015 | Not Ready for Inspection | DAVID TSAU |
Reinforced Concrete Frame | 7/14/2015 | Partial Approval | DAVID TSAU |
Deputy Reinf. Concrete | 7/30/2015 | Conditional Approval | DAVID TSAU |
Reinforced Concrete Frame | 7/30/2015 | Partial Approval | DAVID TSAU |
Floor/Roof Diaphrgm/Shear Wall | 8/13/2015 | Partial Approval | DAVID TSAU |
Light Gage Steel Frame | 8/13/2015 | Partial Approval | DAVID TSAU |
Wood Frame | 8/13/2015 | Partial Inspection | DAVID TSAU |
Wood Frame | 8/28/2015 | Partial Approval | DAVID TSAU |
Floor/Roof Diaphrgm/Shear Wall | 10/7/2015 | Not Ready for Inspection | DAVID TSAU |
Deputy Reinf. Concrete | 11/3/2015 | Conditional Approval | DAVID TSAU |
Deputy Reinf. Concrete | 12/30/2015 | Conditional Approval | DAVID TSAU |
Deputy Reinf. Concrete | 3/18/2016 | Conditional Approval | DAVID TSAU |
Deputy Reinf. Concrete | 9/13/2016 | Approved | NICK LAROCCA |