9211 W NIGHTINGALE DR 90069
Certificate Information: 9211 W NIGHTINGALE DR 90069
- Application / Permit
- 13010-20000-04329
- Plan Check / Job No.
- B13VN14908
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 80' X 111' 1 STORY SFD W/ BASEMENT.
- Permit Issued
- Issued on 8/18/2015
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2013 | APPLICANT |
| Assigned to Plan Check Engineer | 1/2/2014 | HERNAN ARREOLA |
| Corrections Issued | 1/7/2014 | HERNAN ARREOLA |
| Quality Review Completed | 1/9/2014 | TAMERA SVETICH |
| Building Plans Picked Up | 1/9/2014 | APPLICANT |
| Green Plans Picked Up | 1/9/2014 | APPLICANT |
| Plan Check Approved | 8/14/2015 | HERNAN ARREOLA |
| Issued | 8/18/2015 | LADBS |
| CofO in Progress | 6/12/2023 | RAUL BARAJAS |
| CofO Issued | 6/25/2023 | DEROLD HAUFF |
| Permit Finaled | 6/25/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 2/24/2014 | JOHN LIN |
| BHO/Hillside ordinance | Cleared | 2/24/2014 | JOHN LIN |
| BHO/Hillside ordinance | Cleared | 2/24/2014 | JOHN LIN |
| BHO/Hillside ordinance | Cleared | 2/24/2014 | JOHN LIN |
| BHO/Hillside ordinance | Cleared | 2/24/2014 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2014 | JOHN LIN |
| Permit | Cleared | 2/24/2014 | JOHN LIN |
| Sewer availability | Cleared | 2/24/2014 | JOHN LIN |
| Hydrant and Access approval | Cleared | 2/25/2014 | ROBERT DUFF |
| Low Impact Development | Cleared | 3/4/2014 | MICHAEL SCADUTO |
| Grading Pre-Inspection | Cleared | 9/15/2014 | HERNAN ARREOLA |
| Mailing Labels | Cleared | 9/15/2014 | HERNAN ARREOLA |
| Roof/Waste drainage to street | Cleared | 12/4/2014 | MIKE KOUYOUMDJIAN |
| ZI | Cleared | 12/4/2014 | ANNA VIDAL |
| Green Code | Cleared | 12/5/2014 | PETER FOLLING |
| Excavation more than 5-ft deep | Cleared | 6/19/2015 | CALOSHA APPROVED |
Contact Information
| Engineer | Nazari, Arthur; Lic. No.: C53497 | PO BOX 7112 NORTHRIDGE, CA 91327 |
| Engineer | Tsao, Tze-Tzong; Lic. No.: C46886 | 9428 ETON AVE STE M CHATSWORTH, CA 91311 |
| Geologist | Schick, John Wayne; Lic. No.: EG1300 | 7650 HASKELL AVENUE STE D VAN NUYS, CA 91406 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/29/2016 | Partial Approval | BRAD BESCOS |
| Footing/Foundation/Slab | 5/13/2016 | Conditional Approval | BRAD BESCOS |
| Special/Order Compliance | 10/19/2017 | Partial Inspection | DANIEL GONZALEZ |
| Special/Order Compliance | 10/26/2017 | Approved | ROBERT MINASSIANS |
| Footing/Foundation/Slab | 3/27/2018 | Partial Approval | DANIEL GONZALEZ |
| Reinforced Concrete Frame | 3/27/2018 | Partial Approval | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 12/24/2018 | Partial Approval | RONALD COWAN |
| Masonry Wall/Backfill | 1/25/2019 | Partial Approval | DANNY TOLENTINO |
| Footing/Foundation/Slab | 2/25/2019 | Partial Approval | DANNY TOLENTINO |
| Masonry Wall/Backfill | 3/14/2019 | Partial Approval | DANNY TOLENTINO |
| Footing/Foundation/Slab | 3/27/2019 | Partial Approval | DANNY TOLENTINO |
| Masonry Wall/Backfill | 3/27/2019 | Partial Approval | DANNY TOLENTINO |
| Deputy Reinf. Masonry | 4/2/2019 | Conditional Approval | DANNY TOLENTINO |
| Footing/Foundation/Slab | 4/9/2019 | Not Ready for Inspection | DANNY TOLENTINO |
| Masonry Wall/Backfill | 4/9/2019 | Partial Approval | DANNY TOLENTINO |
| Footing/Foundation/Slab | 5/14/2019 | Partial Inspection | DANNY TOLENTINO |
| Special/Order Compliance | 6/26/2019 | Partial Inspection | DANNY TOLENTINO |
| Wood Frame | 8/16/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Wood Construction | 8/20/2019 | Conditional Approval | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2020 | Conditional Approval | RICHARD STEINBACH |
| Special/Order Compliance | 3/5/2020 | Corrections Issued | RICHARD STEINBACH |
| Deputy Wood Construction | 3/9/2020 | Conditional Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 4/10/2020 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 4/14/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 4/20/2020 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 6/26/2020 | Partial Approval | RAUL BARAJAS |
| Drywall Nailing | 11/20/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Wood Frame | 11/20/2020 | Partial Inspection | RAUL BARAJAS |
| Wood Frame | 12/22/2020 | Not Ready for Inspection | RAUL BARAJAS |
| HVAC-Rough | 3/3/2021 | Corrections Issued | RAUL BARAJAS |
| PLUMBING-Rough | 3/4/2021 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 3/31/2021 | Corrections Issued | RAUL BARAJAS |
| ELECTRICAL-Rough | 5/7/2021 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 4/7/2022 | Partial Approval | RAUL BARAJAS |
| BUILDING-Rough-Frame | 5/31/2022 | Approved | RAUL BARAJAS |
| Drywall Nailing | 5/31/2022 | Approved | RAUL BARAJAS |
| Final | 5/31/2022 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 5/31/2022 | Approved | RAUL BARAJAS |
| Gas Test | 5/31/2022 | Approved | RAUL BARAJAS |
| Green Building Final | 5/31/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Rough | 5/31/2022 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 5/31/2022 | SGSOV Not Ready | RAUL BARAJAS |
| Smoke Detectors | 5/31/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 5/31/2022 | Approved | RAUL BARAJAS |
| HVAC-Final | 6/6/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 6/6/2022 | Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 12/21/2022 | Approved | RAUL BARAJAS |
| Special/Order Compliance | 12/21/2022 | Corrections Issued | RAUL BARAJAS |
| ELECTRICAL-Rough | 12/28/2022 | Approved | RAUL BARAJAS |
| Final | 12/28/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Final | 12/28/2022 | Not Ready for Inspection | RAUL BARAJAS |
| HVAC-Rough | 12/28/2022 | Approved | RAUL BARAJAS |
| PLUMBING-Rough | 12/28/2022 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 12/28/2022 | SGSOV Not Ready | RAUL BARAJAS |
| ELECTRICAL-Final | 12/30/2022 | Partial Inspection | RAUL BARAJAS |
| Green Building Final | 12/30/2022 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Final | 12/30/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 1/3/2023 | Partial Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 1/3/2023 | SGSOV Not Ready | RAUL BARAJAS |
| ELECTRICAL-Final | 1/5/2023 | Approved | RAUL BARAJAS |
| Final | 1/5/2023 | Corrections Issued | RAUL BARAJAS |
| HVAC-Final | 1/5/2023 | Corrections Issued | RAUL BARAJAS |
| PLUMBING-Final | 1/5/2023 | Partial Inspection | RAUL BARAJAS |
| Green Building Final | 1/6/2023 | Approved | RAUL BARAJAS |
| Final | 1/12/2023 | Corrections Issued | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 1/12/2023 | SGSOV Not Ready | RAUL BARAJAS |
| Final | 2/7/2023 | No Access for Inspection | RAUL BARAJAS |
| HVAC-Final | 2/7/2023 | No Access for Inspection | RAUL BARAJAS |
| PLUMBING-Final | 2/7/2023 | No Access for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 2/7/2023 | SGSOV Not Ready | RAUL BARAJAS |
| HVAC-Final | 2/8/2023 | Conditional Approval | RAUL BARAJAS |
| PLUMBING-Final | 2/9/2023 | Approved | RAUL BARAJAS |
| HVAC-Final | 3/2/2023 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Final | 3/2/2023 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Final | 3/3/2023 | Approved | RAUL BARAJAS |
| Final | 3/22/2023 | Partial Inspection | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 3/22/2023 | SGSOV Not Ready | STUART CHAPMAN |
| HVAC-Final | 4/3/2023 | Approved | RAUL BARAJAS |
| Final | 4/25/2023 | Not Ready for Inspection | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 4/25/2023 | SGSOV Not Ready | STUART CHAPMAN |
| Final | 5/8/2023 | Corrections Issued | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 5/8/2023 | SGSOV Approved | RAUL BARAJAS |
| Final | 5/31/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 6/6/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 6/9/2023 | OK to Issue CofO | RAUL BARAJAS |