9211 W NIGHTINGALE DR 90069

Certificate Information: 9211 W NIGHTINGALE DR 90069

Application / Permit
13010-20000-04329
Plan Check / Job No.
B13VN14908
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 80' X 111' 1 STORY SFD W/ BASEMENT.
Permit Issued
Issued on 8/18/2015
Issuing Office
Valley
Current Status
CofO Issued on 6/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2013 APPLICANT
Assigned to Plan Check Engineer 1/2/2014 HERNAN ARREOLA
Corrections Issued 1/7/2014 HERNAN ARREOLA
Quality Review Completed 1/9/2014 TAMERA SVETICH
Building Plans Picked Up 1/9/2014 APPLICANT
Green Plans Picked Up 1/9/2014 APPLICANT
Plan Check Approved 8/14/2015 HERNAN ARREOLA
Issued 8/18/2015 LADBS
CofO in Progress 6/12/2023 RAUL BARAJAS
CofO Issued 6/25/2023 DEROLD HAUFF
Permit Finaled 6/25/2023 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 2/24/2014 JOHN LIN
BHO/Hillside ordinance Cleared 2/24/2014 JOHN LIN
BHO/Hillside ordinance Cleared 2/24/2014 JOHN LIN
BHO/Hillside ordinance Cleared 2/24/2014 JOHN LIN
BHO/Hillside ordinance Cleared 2/24/2014 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 2/24/2014 JOHN LIN
Permit Cleared 2/24/2014 JOHN LIN
Sewer availability Cleared 2/24/2014 JOHN LIN
Hydrant and Access approval Cleared 2/25/2014 ROBERT DUFF
Low Impact Development Cleared 3/4/2014 MICHAEL SCADUTO
Grading Pre-Inspection Cleared 9/15/2014 HERNAN ARREOLA
Mailing Labels Cleared 9/15/2014 HERNAN ARREOLA
Roof/Waste drainage to street Cleared 12/4/2014 MIKE KOUYOUMDJIAN
ZI Cleared 12/4/2014 ANNA VIDAL
Green Code Cleared 12/5/2014 PETER FOLLING
Excavation more than 5-ft deep Cleared 6/19/2015 CALOSHA APPROVED

Contact Information

Engineer Nazari, Arthur; Lic. No.: C53497 PO BOX 7112      NORTHRIDGE, CA 91327
Engineer Tsao, Tze-Tzong; Lic. No.: C46886 9428 ETON AVE STE M      CHATSWORTH, CA 91311
Geologist Schick, John Wayne; Lic. No.: EG1300 7650 HASKELL AVENUE STE D      VAN NUYS, CA 91406

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/29/2016 Partial Approval BRAD BESCOS
Footing/Foundation/Slab 5/13/2016 Conditional Approval BRAD BESCOS
Special/Order Compliance 10/19/2017 Partial Inspection DANIEL GONZALEZ
Special/Order Compliance 10/26/2017 Approved ROBERT MINASSIANS
Footing/Foundation/Slab 3/27/2018 Partial Approval DANIEL GONZALEZ
Reinforced Concrete Frame 3/27/2018 Partial Approval DANIEL GONZALEZ
Footing/Foundation/Slab 12/24/2018 Partial Approval RONALD COWAN
Masonry Wall/Backfill 1/25/2019 Partial Approval DANNY TOLENTINO
Footing/Foundation/Slab 2/25/2019 Partial Approval DANNY TOLENTINO
Masonry Wall/Backfill 3/14/2019 Partial Approval DANNY TOLENTINO
Footing/Foundation/Slab 3/27/2019 Partial Approval DANNY TOLENTINO
Masonry Wall/Backfill 3/27/2019 Partial Approval DANNY TOLENTINO
Deputy Reinf. Masonry 4/2/2019 Conditional Approval DANNY TOLENTINO
Footing/Foundation/Slab 4/9/2019 Not Ready for Inspection DANNY TOLENTINO
Masonry Wall/Backfill 4/9/2019 Partial Approval DANNY TOLENTINO
Footing/Foundation/Slab 5/14/2019 Partial Inspection DANNY TOLENTINO
Special/Order Compliance 6/26/2019 Partial Inspection DANNY TOLENTINO
Wood Frame 8/16/2019 Conditional Approval RICHARD STEINBACH
Deputy Wood Construction 8/20/2019 Conditional Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 3/5/2020 Conditional Approval RICHARD STEINBACH
Special/Order Compliance 3/5/2020 Corrections Issued RICHARD STEINBACH
Deputy Wood Construction 3/9/2020 Conditional Approval RICHARD STEINBACH
Footing/Foundation/Slab 4/10/2020 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 4/14/2020 Not Ready for Inspection RAUL BARAJAS
Footing/Foundation/Slab 4/20/2020 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 6/26/2020 Partial Approval RAUL BARAJAS
Drywall Nailing 11/20/2020 Not Ready for Inspection RAUL BARAJAS
Wood Frame 11/20/2020 Partial Inspection RAUL BARAJAS
Wood Frame 12/22/2020 Not Ready for Inspection RAUL BARAJAS
HVAC-Rough 3/3/2021 Corrections Issued RAUL BARAJAS
PLUMBING-Rough 3/4/2021 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 3/31/2021 Corrections Issued RAUL BARAJAS
ELECTRICAL-Rough 5/7/2021 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 4/7/2022 Partial Approval RAUL BARAJAS
BUILDING-Rough-Frame 5/31/2022 Approved RAUL BARAJAS
Drywall Nailing 5/31/2022 Approved RAUL BARAJAS
Final 5/31/2022 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 5/31/2022 Approved RAUL BARAJAS
Gas Test 5/31/2022 Approved RAUL BARAJAS
Green Building Final 5/31/2022 Not Ready for Inspection RAUL BARAJAS
Green Building Rough 5/31/2022 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 5/31/2022 SGSOV Not Ready RAUL BARAJAS
Smoke Detectors 5/31/2022 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 5/31/2022 Approved RAUL BARAJAS
HVAC-Final 6/6/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Interior/Exterior Lathing 6/6/2022 Approved ALIZAH MAYAGOITIA
Smoke Detectors 12/21/2022 Approved RAUL BARAJAS
Special/Order Compliance 12/21/2022 Corrections Issued RAUL BARAJAS
ELECTRICAL-Rough 12/28/2022 Approved RAUL BARAJAS
Final 12/28/2022 Not Ready for Inspection RAUL BARAJAS
Green Building Final 12/28/2022 Not Ready for Inspection RAUL BARAJAS
HVAC-Rough 12/28/2022 Approved RAUL BARAJAS
PLUMBING-Rough 12/28/2022 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 12/28/2022 SGSOV Not Ready RAUL BARAJAS
ELECTRICAL-Final 12/30/2022 Partial Inspection RAUL BARAJAS
Green Building Final 12/30/2022 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Final 12/30/2022 Not Ready for Inspection RAUL BARAJAS
Final 1/3/2023 Partial Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 1/3/2023 SGSOV Not Ready RAUL BARAJAS
ELECTRICAL-Final 1/5/2023 Approved RAUL BARAJAS
Final 1/5/2023 Corrections Issued RAUL BARAJAS
HVAC-Final 1/5/2023 Corrections Issued RAUL BARAJAS
PLUMBING-Final 1/5/2023 Partial Inspection RAUL BARAJAS
Green Building Final 1/6/2023 Approved RAUL BARAJAS
Final 1/12/2023 Corrections Issued RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 1/12/2023 SGSOV Not Ready RAUL BARAJAS
Final 2/7/2023 No Access for Inspection RAUL BARAJAS
HVAC-Final 2/7/2023 No Access for Inspection RAUL BARAJAS
PLUMBING-Final 2/7/2023 No Access for Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 2/7/2023 SGSOV Not Ready RAUL BARAJAS
HVAC-Final 2/8/2023 Conditional Approval RAUL BARAJAS
PLUMBING-Final 2/9/2023 Approved RAUL BARAJAS
HVAC-Final 3/2/2023 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Final 3/2/2023 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Final 3/3/2023 Approved RAUL BARAJAS
Final 3/22/2023 Partial Inspection STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 3/22/2023 SGSOV Not Ready STUART CHAPMAN
HVAC-Final 4/3/2023 Approved RAUL BARAJAS
Final 4/25/2023 Not Ready for Inspection STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 4/25/2023 SGSOV Not Ready STUART CHAPMAN
Final 5/8/2023 Corrections Issued RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 5/8/2023 SGSOV Approved RAUL BARAJAS
Final 5/31/2023 Not Ready for Inspection RAUL BARAJAS
Final 6/6/2023 Not Ready for Inspection RAUL BARAJAS
Final 6/9/2023 OK to Issue CofO RAUL BARAJAS