5327 N HERMITAGE AVE #1-#42 91607

Certificate Information: 5327 N HERMITAGE AVE #1-#42 91607

Application / Permit
13010-20000-03079
Plan Check / Job No.
B13VN11672
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Fully sprinklered 164'-9" x 104'-5 1/2" irreg. shaped 4 story 42 unit apartment with basement garage
Permit Issued
Issued on 3/30/2016
Issuing Office
Valley
Current Status
CofO Issued on 1/16/2019
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/4/2013 APPLICANT
Assigned to Plan Check Engineer 10/31/2013 STEVEN KIM
Disabled Access Plans Picked Up 11/5/2013 APPLICANT
Green Plans Picked Up 11/5/2013 APPLICANT
Corrections Issued 11/14/2013 STEVEN KIM
Quality Review Completed 11/18/2013 TAMERA SVETICH
Building Plans Picked Up 11/19/2013 APPLICANT
Applicant returned to address corrections 2/7/2014 STEVEN KIM
Applicant returned to address corrections 2/21/2014 STEVEN KIM
Applicant returned to address corrections 3/28/2014 STEVEN KIM
Applicant returned to address corrections 8/27/2014 STEVEN KIM
Applicant returned to address corrections 4/7/2015 STEVEN KIM
Applicant returned to address corrections 1/6/2016 STEVEN KIM
Applicant returned to address corrections 3/2/2016 STEVEN KIM
Applicant returned to address corrections 3/15/2016 STEVEN KIM
Plan Check Approved 3/25/2016 STEVEN KIM
Issued 3/30/2016 LADBS
TCO Issued (Expire Date: 02-12-2019) 8/16/2018 ANDREW CROMER
CofO in Progress 12/4/2018 CAMERON CHABAN
CofO Issued 1/16/2019 ANDREW CROMER
Permit Finaled 1/16/2019 ANDREW CROMER

Permit Application Clearance Information

Address approval Cleared 1/9/2014 HOWARD COOPER
Eng Process Fee Ord 176,300 Cleared 1/9/2014 JOHN LIN
Sewer availability Cleared 1/9/2014 JOHN LIN
Highway dedication Cleared 3/5/2015 HELEN FRANCISCO
Hydrant and Access approval Cleared 4/13/2015 ROBERT DUFF
Low Impact Development Cleared 8/27/2015 IDA MEISAMI-FARD
Green Code Cleared 9/29/2015 MICHAEL AYERS
Green Code Cleared 9/29/2015 MICHAEL AYERS
DAS Clearance Cleared 10/5/2015 NORLITO MEDRANO
Roof/Waste drainage to street Cleared 10/16/2015 JOHN LIN
Frnt yard landscape/Water mgmt Cleared 11/2/2015 SARAH HOUNSELL
Miscellaneous Cleared 11/2/2015 SARAH HOUNSELL
Opn space landscape/Water mgmt Cleared 11/2/2015 SARAH HOUNSELL
Building over 3-story or 36-ft Cleared 1/6/2016 CALOSHA APPROVED
Title 19 building approval Cleared 1/6/2016 ANDREW KO
Housing density bonus Cleared 2/25/2016 REX LEE
Specific Plan Cleared 3/10/2016 SARAH HOUNSELL
Specific Plan Cleared 3/14/2016 SARAH HOUNSELL
Specific Plan Cleared 3/14/2016 SARAH HOUNSELL
Permit Cleared 3/29/2016 ERIK MUNOZ

Contact Information

Architect Stockton, Kenneth; Lic. No.: C19870 26500 W AGOURA RD. PMB # 844      CALABASAS, CA 91302
Contractor Owner-Builder       ,
Engineer Freitas, Richard Gomes; Lic. No.: C49072 240 COPA DE ORO DR      BREA, CA 92823
Engineer Haddad, Raymond Mounir; Lic. No.: GE2985 17106 CEREDO PL      GRANADA HILLS, CA 91344

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/24/2016 Partial Inspection CAMERON CHABAN
Deputy Grading 9/30/2016 Conditional Approval CAMERON CHABAN
Deputy Grading 10/4/2016 Conditional Approval CAMERON CHABAN
Deputy Grading 10/5/2016 Conditional Approval CAMERON CHABAN
Deputy Grading 10/6/2016 Conditional Approval CAMERON CHABAN
Deputy Grading 10/7/2016 Conditional Approval CAMERON CHABAN
Deputy Grading 10/18/2016 Conditional Approval CAMERON CHABAN
Deputy Grading 10/19/2016 Conditional Approval CAMERON CHABAN
Deputy Grading 10/20/2016 Conditional Approval CAMERON CHABAN
Deputy Grading 10/21/2016 Conditional Approval CAMERON CHABAN
Deputy Grading 10/24/2016 Conditional Approval CAMERON CHABAN
Deputy Grading 10/25/2016 Conditional Approval CAMERON CHABAN
Deputy Grading 10/26/2016 Conditional Approval CAMERON CHABAN
Deputy Grading 11/1/2016 Conditional Approval CAMERON CHABAN
Pre-Inspection 11/7/2016 Partial Inspection JOHN KITCKO
Deputy Reinf. Concrete 11/18/2016 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 11/18/2016 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 11/22/2016 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 11/22/2016 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 11/28/2016 Conditional Approval TROY CHRISTIAN
Deputy Reinf. Concrete 11/29/2016 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 11/29/2016 Conditional Approval ROBERT COLE
Excavation/Setback/Form/Re-Bar 11/29/2016 Partial Approval ROBERT COLE
Deputy Reinf. Concrete 12/1/2016 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/1/2016 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 12/1/2016 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 12/2/2016 Approved JOHN KITCKO
Deputy Reinf. Masonry 12/2/2016 Approved JOHN KITCKO
Deputy Shotcrete 12/2/2016 Approved JOHN KITCKO
Masonry Wall/Backfill 12/2/2016 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 12/6/2016 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 12/6/2016 Conditional Approval CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 12/6/2016 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 12/7/2016 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 12/7/2016 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 12/8/2016 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 12/8/2016 Conditional Approval CAMERON CHABAN
Deputy Shotcrete 12/8/2016 Conditional Approval CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 12/8/2016 Conditional Approval CAMERON CHABAN
Masonry Wall/Backfill 12/8/2016 Conditional Approval CAMERON CHABAN
Verify Sprinkler Sign Off 12/8/2016 Not Ready for Inspection CAMERON CHABAN
Deputy Reinf. Concrete 12/9/2016 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 12/9/2016 Conditional Approval CAMERON CHABAN
Deputy Shotcrete 12/9/2016 Conditional Approval CAMERON CHABAN
Deputy Shotcrete 12/12/2016 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 12/14/2016 Conditional Approval CAMERON CHABAN
Masonry Wall/Backfill 12/14/2016 Conditional Approval CAMERON CHABAN
Verify Sprinkler Sign Off 12/14/2016 Not Ready for Inspection CAMERON CHABAN
Deputy Reinf. Concrete 1/25/2017 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 1/26/2017 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 1/27/2017 Approved JEFFREY DURAN
Deputy Reinf. Concrete 1/30/2017 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 1/31/2017 Partial Approval DANIEL VARNUM
Deputy Reinf. Concrete 2/1/2017 Approved JOHN KITCKO
Deputy Reinf. Concrete 2/2/2017 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 2/3/2017 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 2/7/2017 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 2/8/2017 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 2/9/2017 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 2/10/2017 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 2/13/2017 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 2/13/2017 Not Ready for Inspection JOHN KITCKO
Deputy Reinf. Concrete 2/14/2017 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 2/14/2017 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 2/16/2017 Conditional Approval CAMERON CHABAN
Deputy Drilled-In Anchors 2/23/2017 Approved JOHN KITCKO
Deputy Drilled-In Anchors 2/24/2017 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 2/28/2017 Partial Approval DANIEL VARNUM
Deputy Steel/Welding 3/1/2017 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 3/2/2017 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 3/6/2017 Conditional Approval CAMERON CHABAN
Masonry Wall/Backfill 3/6/2017 Conditional Approval CAMERON CHABAN
Masonry Wall/Backfill 3/7/2017 Partial Approval CAMERON CHABAN
Deputy Reinf. Masonry 3/9/2017 Conditional Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 3/15/2017 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 3/16/2017 Partial Approval CAMERON CHABAN
Masonry Wall/Backfill 3/16/2017 Partial Approval CAMERON CHABAN
Deputy Wood Construction 3/20/2017 Conditional Approval CAMERON CHABAN
Deputy Wood Construction 3/23/2017 Approved JOHN KITCKO
Masonry Wall/Backfill 3/28/2017 Conditional Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 4/5/2017 Conditional Approval CAMERON CHABAN
Masonry Wall/Backfill 4/10/2017 Partial Approval CAMERON CHABAN
Deputy Wood Construction 4/12/2017 Approved CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 4/20/2017 Conditional Approval CAMERON CHABAN
Green Building Rough 4/20/2017 Not Ready for Inspection ROLLIN GETTLE III
Insulation 4/20/2017 Partial Approval CAMERON CHABAN
Verify Sprinkler Sign Off 4/20/2017 Not Ready for Inspection CAMERON CHABAN
Wood Frame 4/20/2017 Partial Approval CAMERON CHABAN
Deputy Wood Construction 5/2/2017 Conditional Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 5/24/2017 Conditional Approval CAMERON CHABAN
Deputy Wood Construction 5/25/2017 Conditional Approval CAMERON CHABAN
Insulation 6/9/2017 Partial Approval JOHN KITCKO
Green Building Rough 6/12/2017 Not Ready for Inspection MICKEY YAMASHITA
Verify Sprinkler Sign Off 6/12/2017 Not Ready for Inspection JOHN KITCKO
Wood Frame 6/12/2017 Conditional Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 6/13/2017 Partial Inspection JOHN KITCKO
Deputy Wood Construction 6/14/2017 Approved JOHN KITCKO
Insulation 6/14/2017 Partial Inspection JOHN KITCKO
Insulation 6/15/2017 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 6/16/2017 Partial Approval JOHN KITCKO
Insulation 6/21/2017 Conditional Approval CAMERON CHABAN
Drywall Nailing 7/12/2017 Not Ready for Inspection ROBERT COLE
Green Building Rough 7/12/2017 Not Ready for Inspection MICKEY YAMASHITA
Insulation 7/12/2017 Partial Approval ROBERT COLE
Insulation 7/13/2017 Conditional Approval CAMERON CHABAN
Masonry Wall/Backfill 7/19/2017 Conditional Approval CAMERON CHABAN
Drywall Nailing 8/3/2017 Partial Approval CAMERON CHABAN
Green Building Rough 8/3/2017 Not Ready for Inspection MICKEY YAMASHITA
Deputy Wood Construction 8/16/2017 Conditional Approval TROY CHRISTIAN
Insulation 8/28/2017 Partial Approval CAMERON CHABAN
Green Building Rough 8/30/2017 Partial Approval MICKEY YAMASHITA
Green Building Rough 9/22/2017 Partial Approval MICKEY YAMASHITA
Insulation 9/22/2017 Conditional Approval CAMERON CHABAN
Verify Sprinkler Sign Off 9/22/2017 Partial Approval CAMERON CHABAN
Wood Frame 9/22/2017 Conditional Approval CAMERON CHABAN
Interior/Exterior Lathing 9/25/2017 Approved CAMERON CHABAN
Drywall Nailing 10/2/2017 Partial Approval CAMERON CHABAN
Green Building Rough 10/2/2017 Not Ready for Inspection DAVID MATSON
Drywall Nailing 10/13/2017 Conditional Approval CAMERON CHABAN
Green Building Rough 10/13/2017 Partial Approval MICKEY YAMASHITA
Drywall Nailing 10/31/2017 Partial Approval ROBERT DAVIS
Green Building Rough 10/31/2017 Not Ready for Inspection MICKEY YAMASHITA
Drywall Nailing 11/8/2017 Partial Approval CAMERON CHABAN
Green Building Rough 11/8/2017 Approved CAMERON CHABAN
Drywall Nailing 11/9/2017 Partial Approval CAMERON CHABAN
Footing/Foundation/Slab 1/18/2018 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 1/23/2018 Approved JOHN KITCKO
Deputy Reinf. Concrete 1/25/2018 Approved ROBERT DAVIS
Green Building Final 6/25/2018 Approved CAMERON CHABAN
Drywall Nailing 7/12/2018 Approved CAMERON CHABAN
Final 7/12/2018 Partial Inspection CAMERON CHABAN
Footing/Foundation/Slab 7/12/2018 Approved CAMERON CHABAN
Reinforced Concrete Frame 7/12/2018 Approved CAMERON CHABAN
Reinforced Masonry Frame 7/12/2018 Approved CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 7/12/2018 SGSOV Approved CAMERON CHABAN
Smoke Detectors 7/12/2018 Approved CAMERON CHABAN
Structural Steel Frame 7/12/2018 Approved CAMERON CHABAN
Verify Sprinkler Sign Off 7/12/2018 Approved CAMERON CHABAN
Wood Frame 7/12/2018 Approved CAMERON CHABAN
Final 7/17/2018 Partial Inspection CAMERON CHABAN
Final 8/9/2018 Partial Inspection CAMERON CHABAN
Final 9/12/2018 Partial Inspection CAMERON CHABAN
Final 12/4/2018 OK to Issue CofO CAMERON CHABAN