5732 N STANSBURY AVE 91401
Certificate Information: 5732 N STANSBURY AVE 91401
- Application / Permit
- 13010-20000-01088
- Plan Check / Job No.
- B13VN04047
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 22' X 37' SECOND DWELLING UNIT PER WFPP. COMPLY WITH DEPARTMENT ORDER EFFECTIVE DATE 4/25/13. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE.
- Permit Issued
- Issued on 8/7/2013
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 3/3/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/15/2013 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2013 | JENNIFER LEE |
| Corrections Issued | 5/2/2013 | JENNIFER LEE |
| Quality Review Completed | 5/3/2013 | TAMERA SVETICH |
| Building Plans Picked Up | 5/7/2013 | APPLICANT |
| Green Plans Picked Up | 5/7/2013 | APPLICANT |
| Plan Check Approved | 5/29/2013 | JENNIFER LEE |
| Issued | 8/7/2013 | LADBS |
| Permit Closed | 6/27/2017 | EDMOND DECKERT |
| No Progress | 6/27/2017 | HAGOP BADOSSIAN |
| Permit Expired-Status Void | 4/10/2024 | HAGOP BADOSSIAN |
| Re-Activate Permit | 2/28/2025 | HAGOP BADOSSIAN |
| CofO in Progress | 3/3/2026 | JONATHAN FRANCHINI |
Permit Application Clearance Information
| Address approval | Cleared | 5/24/2013 | HOWARD COOPER |
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2013 | MARY MARCUS |
| Green Code | Cleared | 5/24/2013 | ROLLIN GETTLE III |
| Green Code | Cleared | 5/24/2013 | ROLLIN GETTLE III |
| Hydrant and Access approval | Cleared | 5/24/2013 | JOSEPH JACKSON |
| Permit | Cleared | 5/24/2013 | MARY MARCUS |
| Sewer availability | Cleared | 5/24/2013 | MARY MARCUS |
| Low Impact Development | Cleared | 5/29/2013 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 5/29/2013 | JAMES KHO |
Contact Information
| Contractor | Earl D'La Fer; Lic. No.: 858813-B | 1640 N HOBART BLVD #33 LOS ANGELES, CA 90027 |
| Contractor | Owner-Builder | , |
Inspector Information
| JOEL ORDAZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| PTOLEMY HILL, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVAKIAN, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDMOND DECKERT, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| TIMOTHY KEY, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT CHAVEZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/2/2013 | Approved | HECTOR RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2013 | Partial Approval | JOHN MATTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2014 | Approved | HECTOR RODRIGUEZ |
| ELECTRICAL-Final | 3/19/2014 | Not Ready for Inspection | HECTOR RODRIGUEZ |
| ELECTRICAL-Final | 6/2/2014 | Not Ready for Inspection | HECTOR RODRIGUEZ |
| BUILDING-Rough-Frame | 8/6/2014 | Partial Approval | HECTOR RODRIGUEZ |
| ELECTRICAL-Rough | 8/6/2014 | Approved | HECTOR RODRIGUEZ |
| Green Building Rough | 8/6/2014 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Rough | 8/6/2014 | Partial Approval | HECTOR RODRIGUEZ |
| Insulation | 8/20/2014 | No Access for Inspection | EDMOND DECKERT |
| Insulation | 8/21/2014 | Not Ready for Inspection | EDMOND DECKERT |
| Insulation | 8/25/2014 | No Access for Inspection | EDMOND DECKERT |
| Insulation | 8/26/2014 | Not Ready for Inspection | EDMOND DECKERT |
| Green Building Rough | 8/27/2014 | Corrections Issued | BRYAN MEYER |
| Green Building Rough | 9/2/2014 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 9/3/2014 | Not Ready for Inspection | FELIPE PENICHE |
| Insulation | 9/3/2014 | Not Ready for Inspection | FELIPE PENICHE |
| PLUMBING-Rough | 9/3/2014 | Corrections Issued | FELIPE PENICHE |
| BUILDING-Rough-Frame | 9/9/2014 | Corrections Issued | MATT KELLERMAN |
| Insulation | 9/9/2014 | Corrections Issued | MATT KELLERMAN |
| PLUMBING-Rough | 9/9/2014 | Corrections Issued | MATT KELLERMAN |
| BUILDING-Rough-Frame | 9/11/2014 | Corrections Issued | EDMOND DECKERT |
| Rough-Elec/Plmb/HVAC | 10/20/2014 | Corrections Issued | EDMOND DECKERT |
| BUILDING-Rough-Frame | 11/5/2014 | Not Ready for Inspection | EDMOND DECKERT |
| Drywall Nailing | 11/5/2014 | Not Ready for Inspection | EDMOND DECKERT |
| PLUMBING-Rough | 11/5/2014 | Not Ready for Inspection | EDMOND DECKERT |
| BUILDING-Rough-Frame | 2/27/2026 | Approved | JONATHAN FRANCHINI |
| Drywall Nailing | 2/27/2026 | Approved | JONATHAN FRANCHINI |
| Final | 2/27/2026 | OK to Issue CofO | JONATHAN FRANCHINI |
| Green Building Final | 2/27/2026 | Approved | JONATHAN FRANCHINI |
| SGSOV-Seismic Gas S/O Valve | 2/27/2026 | SGSOV Approved | JONATHAN FRANCHINI |
| Smoke Detectors | 2/27/2026 | Approved | JONATHAN FRANCHINI |