5912 N CALVIN AVE 91356

Certificate Information: 5912 N CALVIN AVE 91356

Application / Permit
13010-20000-00958
Plan Check / Job No.
B13VN03497
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Carport
Work Description
20' X 22'10" CARPORT
Permit Issued
Issued on 9/16/2013
Issuing Office
Valley
Current Status
CofO Issued on 11/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/2/2013 APPLICANT
Green Plans Picked Up 4/8/2013 APPLICANT
Assigned to Plan Check Engineer 4/11/2013 CHON CHIO KUO
Corrections Issued 4/15/2013 CHON CHIO KUO
Quality Review Completed 4/19/2013 TAMERA SVETICH
Building Plans Picked Up 4/22/2013 APPLICANT
Applicant returned to address corrections 4/30/2013 CHON CHIO KUO
Applicant returned to address corrections 7/24/2013 CHON CHIO KUO
Applicant returned to address corrections 7/29/2013 CHON CHIO KUO
Plan Check Approved 9/3/2013 CHON-CHIO KUO
Issued 9/16/2013 LADBS
Re-Activate Permit 8/27/2024 JON MCHUGH
Re-Activate Permit 8/27/2024 SEAN WIRCH
Permit Expired-Status Void 8/27/2024 JON MCHUGH
Permit Expired-Status Void 8/27/2024 SEAN WIRCH
CofO in Progress 9/4/2024 JON MCHUGH
CofO Issued 11/12/2024 JOHN JANSON
Permit Finaled 11/12/2024 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/20/2013 CHRISTINE KEUSHGUERIAN
Green Code Cleared 7/5/2013 ROLLIN GETTLE III
Roof/Waste drainage to street Cleared 7/24/2013 CHRISTINE KEUSHGUERIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/1/2014 Not Ready for Inspection MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 7/22/2014 Partial Approval MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 9/5/2014 Approved MICHAEL TEMPLE
BUILDING-Rough-Frame 6/29/2017 Approved SEAN WIRCH
Final 6/29/2017 Not Ready for Inspection SEAN WIRCH
Footing/Foundation/Slab 6/29/2017 Approved SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 6/29/2017 SGSOV Not Ready SEAN WIRCH
Smoke Detectors 6/29/2017 Approved SEAN WIRCH
Final 8/26/2024 Corrections Issued JON MCHUGH
SGSOV-Seismic Gas S/O Valve 8/26/2024 SGSOV Not Ready JON MCHUGH
Pre-Inspection 8/27/2024 Not Ready for Inspection SEAN WIRCH
Final 8/29/2024 Off-Hour Fees Due
SGSOV-Seismic Gas S/O Valve 8/29/2024 Off-Hour Fees Due
Final 9/3/2024 OK to Issue CofO JON MCHUGH
SGSOV-Seismic Gas S/O Valve 9/3/2024 SGSOV Approved JON MCHUGH