9330 W HILLROSE ST 91040

Certificate Information: 9330 W HILLROSE ST 91040

Application / Permit
13010-20000-00128
Plan Check / Job No.
B13VN00672
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SFD W/BASEMENT AND ATT. GARAGE FULLY SPRINKLER.
Permit Issued
Issued on 4/3/2015
Issuing Office
Valley
Current Status
CofO Issued on 1/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/23/2013 APPLICANT
Green Plans Picked Up 3/1/2013 APPLICANT
Assigned to Plan Check Engineer 3/7/2013 CHON CHIO KUO
Corrections Issued 3/20/2013 CHON CHIO KUO
Quality Review Completed 3/29/2013 TAMERA SVETICH
Building Plans Picked Up 3/29/2013 APPLICANT
Applicant returned to address corrections 3/5/2014 CHON CHIO KUO
Applicant returned to address corrections 4/9/2014 CHON CHIO KUO
Applicant returned to address corrections 4/15/2014 CHON CHIO KUO
Applicant returned to address corrections 5/8/2014 CHON CHIO KUO
Applicant returned to address corrections 9/22/2014 CHON CHIO KUO
Applicant returned to address corrections 9/29/2014 CHON CHIO KUO
Applicant returned to address corrections 10/7/2014 CHON CHIO KUO
Applicant returned to address corrections 10/20/2014 CHON CHIO KUO
Applicant returned to address corrections 12/17/2014 CHON CHIO KUO
Applicant returned to address corrections 1/8/2015 CHON CHIO KUO
Applicant returned to address corrections 3/25/2015 CHON CHIO KUO
Plan Check Approved 3/27/2015 CHON CHIO KUO
Issued 4/3/2015 LADBS
CofO in Progress 9/30/2021 WILLIAM KUEHN
Permit Finaled 1/8/2022 MICHAEL SMITH
CofO Issued 1/8/2022 MICHAEL SMITH
Permit Finaled 1/8/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/18/2013 CHRISTINE KEUSHGUERIAN
Work Adjacent to Public Way Cleared 12/19/2013 MIKE KOUYOUMDJIAN
Disturb/Remove Protected Trees Cleared 4/15/2014 CHON-CHIO KUO
BHO/Hillside ordinance Cleared 9/18/2014 JOHN LIN
Permit Cleared 9/18/2014 JOHN LIN
Specific Plan Cleared 9/22/2014 TOM GLICK
ZA Case Cleared 9/22/2014 TOM GLICK
ZA Case Cleared 9/22/2014 TOM GLICK
Hydrant and Access approval Cleared 9/23/2014 MARTIN GUTIERREZ
VHFHSZ Cleared 9/23/2014 MARTIN GUTIERREZ
Low Impact Development Cleared 9/25/2014 AYMAN JABBOURI
Roof/Waste drainage to street Cleared 9/25/2014 MIKE KOUYOUMDJIAN
Stormwater Pollution Mitigatn Cleared 9/26/2014 MARTIN FRAGOSO
Supplemental Onsite WTS Cleared 9/26/2014 MARTIN FRAGOSO
Landscape for retaining wall Cleared 9/29/2014 HERMINIGILDO AGUSTIN
ZA Case Cleared 9/29/2014 HERMINIGILDO AGUSTIN
Excavation more than 5-ft deep Cleared 10/20/2014 CALOSHA APPROVED
Miscellaneous Cleared 10/20/2014 CHON-CHIO KUO
Green Code Cleared 12/11/2014 MICHAEL AYERS
Private sewage disp. approval Cleared 3/25/2015 CHON-CHIO KUO

Contact Information

Contractor Highrise Inc; Lic. No.: 971653-B 10118 FERNGLEN AVE #3      TUJUNGA, CA 91042
Engineer Abkarian, Raffi; Lic. No.: C36027 18763 VINTAGE STREET      NORTHRIDGE, CA 91324
Engineer Minassian, Andre Melik; Lic. No.: C33813 P O BOX 29216      LOS ANGELES, CA 90029

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/2/2016 Not Ready for Inspection KEVIN BEAULIEU
METHANE-Barrier 6/2/2016 Approved KEVIN BEAULIEU
METHANE-Subgrade 6/2/2016 Approved KEVIN BEAULIEU
Excavation/Setback/Form/Re-Bar 6/3/2016 Partial Approval KEVIN BEAULIEU
Masonry Wall/Backfill 1/18/2017 Partial Inspection BEAU COLLINS
SUSMP-Std. Urban Storm Water 9/29/2017 No Access for Inspection BEAU COLLINS
Footing/Foundation/Slab 3/22/2018 Not Ready for Inspection KEVIN BEAULIEU
Underground Mechanical 8/3/2018 Partial Inspection BEAU COLLINS
Excavation/Setback/Form/Re-Bar 8/22/2018 Not Ready for Inspection BEAU COLLINS
Underground Mechanical 8/22/2018 Not Ready for Inspection BEAU COLLINS
Excavation/Setback/Form/Re-Bar 8/23/2018 Partial Approval BEAU COLLINS
Underground Mechanical 8/23/2018 Not Ready for Inspection BEAU COLLINS
Masonry Wall/Backfill 10/19/2018 Partial Approval BEAU COLLINS
BUILDING-Rough-Frame 11/20/2018 Partial Approval BEAU COLLINS
Footing/Foundation/Slab 12/3/2018 Corrections Issued BEAU COLLINS
Floor/Roof Diaphrgm/Shear Wall 12/4/2018 Partial Approval BEAU COLLINS
Masonry Wall/Backfill 12/11/2018 Partial Approval BEAU COLLINS
PLUMBING-Rough 1/10/2019 Partial Approval BEAU COLLINS
Floor/Roof Diaphrgm/Shear Wall 1/25/2019 Partial Approval BEAU COLLINS
Floor/Roof Diaphrgm/Shear Wall 2/27/2019 Conditional Approval BEAU COLLINS
Insulation 5/23/2019 Partial Approval BEAU COLLINS
BUILDING-Rough-Frame 6/3/2019 Corrections Issued BEAU COLLINS
Deputy Wood Construction 6/3/2019 Approved BEAU COLLINS
Floor/Roof Diaphrgm/Shear Wall 6/3/2019 Approved BEAU COLLINS
HVAC-Rough 6/3/2019 Approved BEAU COLLINS
PLUMBING-Rough 6/3/2019 Approved BEAU COLLINS
Rough-Elec/Plmb/HVAC 6/13/2019 Approved BEAU COLLINS
Shower Pan 6/13/2019 Not Ready for Inspection BEAU COLLINS
ELECTRICAL-Rough 7/2/2019 Not Ready for Inspection BEAU COLLINS
BUILDING-Rough-Frame 7/22/2019 Partial Approval BEAU COLLINS
ELECTRICAL-Rough 7/22/2019 Approved BEAU COLLINS
Green Building Rough 7/22/2019 Approved BEAU COLLINS
HVAC-Rough 7/22/2019 Approved BEAU COLLINS
METHANE-Rough 7/22/2019 Approved BEAU COLLINS
PLUMBING-Rough 7/22/2019 Approved BEAU COLLINS
Verify Sprinkler Sign Off 7/22/2019 Approved BEAU COLLINS
Insulation 7/30/2019 Not Ready for Inspection BEAU COLLINS
Insulation 8/1/2019 Approved BEAU COLLINS
Sewer 8/8/2019 Approved BEAU COLLINS
BUILDING-Rough-Frame 8/26/2019 Conditional Approval BEAU COLLINS
Drywall Nailing 8/26/2019 Approved BEAU COLLINS
Footing/Foundation/Slab 8/26/2019 Approved BEAU COLLINS
Interior/Exterior Lathing 8/26/2019 Partial Approval BEAU COLLINS
Reinforced Masonry Frame 8/26/2019 Approved BEAU COLLINS
Structural Steel Frame 8/26/2019 Approved BEAU COLLINS
Gas Test 11/14/2019 Approved BEAU COLLINS
BUILDING-Rough-Frame 12/16/2019 Partial Inspection BEAU COLLINS
Excavation/Setback/Form/Re-Bar 1/8/2020 Not Ready for Inspection BEAU COLLINS
Special/Order Compliance 7/22/2020 Corrections Issued BEAU COLLINS
Special/Order Compliance 7/22/2020 Partial Inspection PIERRE VEGA
BUILDING-Rough-Frame 12/15/2020 Approved BEAU COLLINS
ELECTRICAL-Final 12/15/2020 Approved BEAU COLLINS
Final 12/15/2020 Corrections Issued BEAU COLLINS
Green Building Final 12/15/2020 Not Ready for Inspection BEAU COLLINS
HVAC-Final 12/15/2020 Not Ready for Inspection BEAU COLLINS
PLUMBING-Final 12/15/2020 Approved BEAU COLLINS
SGSOV-Seismic Gas S/O Valve 12/15/2020 SGSOV Approved BEAU COLLINS
Smoke Detectors 12/15/2020 Approved BEAU COLLINS
Final 1/19/2021 Not Ready for Inspection BEAU COLLINS
Green Building Final 1/19/2021 Not Ready for Inspection BEAU COLLINS
Final 6/18/2021 Not Ready for Inspection DAVID SANDOVAL
Green Building Final 6/18/2021 Not Ready for Inspection DAVID SANDOVAL
Final 7/13/2021 Corrections Issued MATTHEW NELSON
Green Building Final 7/13/2021 Corrections Issued MATTHEW NELSON
Final 9/21/2021 Corrections Issued WILLIAM KUEHN
Green Building Final 9/21/2021 Approved WILLIAM KUEHN
Service/Power Release 9/21/2021 Approved WILLIAM KUEHN
Final 9/29/2021 OK to Issue CofO WILLIAM KUEHN