9259 W ROBIN DR 90069
Certificate Information: 9259 W ROBIN DR 90069
- Application / Permit
- 13010-10011-02998
- Plan Check / Job No.
- B22LA00045
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Supplemental to 13010-20000-02998: Recheck Building per current Zoning and Residential Code due to expired permit with 40% complete.
- Permit Issued
- Issued on 1/24/2022
- Issuing Office
- Current Status
- Permit Finaled on 5/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Plan Check Approved | 1/18/2022 | HERNAN ARREOLA |
| Issued | 1/24/2022 | APPLICANT |
| Permit Finaled | 5/13/2025 | RAUL BARAJAS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Dcw Signature Homes; Lic. No.: 1027406-B | 143 E CITY PLACE DRIVE SANTA ANA, CA 92705 |
| Engineer | Berkoz, Ertunga; Lic. No.: S2504 | 4665 ELLENITA AVE TARZANA, CA 91356 |
| Engineer | Zweigler, Robert Ingraham; Lic. No.: GE2120 | 1461 E. CHEVY CHASE DR. #200 GLENDALE, CA 91206 |
| Geologist | Cugno, Giuseppe; Lic. No.: EG1804 | J. BYER GROUP, THE 1461 E CHEVY CHASE DR, #200 GLENDALE, CA 91206 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Test | 1/28/2022 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 2/4/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2022 | Partial Approval | RAUL BARAJAS |
| Wood Frame | 2/4/2022 | Partial Inspection | RAUL BARAJAS |
| Green Building Rough | 4/7/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Insulation | 4/7/2022 | Partial Approval | RAUL BARAJAS |
| Rough-Elec/Plmb/HVAC | 4/7/2022 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 4/21/2022 | Approved | RAUL BARAJAS |
| HVAC-Rough | 5/4/2022 | Partial Approval | RAUL BARAJAS |
| Structural Steel Frame | 5/12/2022 | Approved | RAUL BARAJAS |
| Shower Pan | 6/13/2022 | Partial Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 6/22/2022 | Partial Approval | RAUL BARAJAS |
| HVAC-Rough | 6/29/2022 | Approved | RAUL BARAJAS |
| Grounding or Bonding | 8/30/2022 | Approved | RAUL BARAJAS |
| Shower Pan | 8/30/2022 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 9/21/2022 | Partial Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 9/21/2022 | Partial Approval | RAUL BARAJAS |
| BUILDING-Rough-Frame | 9/28/2022 | Partial Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 9/28/2022 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 10/19/2022 | Partial Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 10/19/2022 | Partial Approval | RAUL BARAJAS |
| BUILDING-Rough-Frame | 10/27/2022 | Partial Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 10/27/2022 | Approved | RAUL BARAJAS |
| Green Building Rough | 11/4/2022 | Partial Approval | RAUL BARAJAS |
| Insulation | 11/4/2022 | Partial Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 11/23/2022 | Partial Approval | RAUL BARAJAS |
| Insulation | 12/2/2022 | Partial Approval | RAUL BARAJAS |
| Drywall Nailing | 12/15/2022 | Partial Approval | RAUL BARAJAS |
| Insulation | 12/15/2022 | Partial Approval | RAUL BARAJAS |
| Interior/Exterior Lathing | 12/15/2022 | Not Ready for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 12/19/2022 | Conditional Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 12/19/2022 | Conditional Approval | RAUL BARAJAS |
| Green Building Rough | 12/19/2022 | Approved | RAUL BARAJAS |
| Insulation | 12/19/2022 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 12/21/2022 | Partial Approval | RAUL BARAJAS |
| Drywall Nailing | 1/3/2023 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 1/9/2023 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 2/27/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Interior/Exterior Lathing | 3/1/2023 | No Access for Inspection | RAUL BARAJAS |
| Interior/Exterior Lathing | 3/2/2023 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 3/13/2023 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 3/14/2023 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 3/14/2023 | Partial Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 3/20/2023 | Partial Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 6/26/2023 | Approved | RAUL BARAJAS |
| Service/Power Release | 6/26/2023 | Approved | RAUL BARAJAS |
| Drywall Nailing | 10/10/2023 | Partial Approval | RAUL BARAJAS |
| Pre-Inspection | 10/10/2023 | Partial Inspection | RAUL BARAJAS |
| Enclosure/Fence | 5/15/2024 | Partial Inspection | RAUL BARAJAS |
| ELECTRICAL-Final | 6/6/2024 | Partial Inspection | RAUL BARAJAS |
| ELECTRICAL-Final | 8/13/2024 | Partial Inspection | RAUL BARAJAS |
| Insulation | 10/9/2024 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 10/22/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Drywall Nailing | 11/14/2024 | Approved | RAUL BARAJAS |
| HVAC-Final | 11/14/2024 | Approved | RAUL BARAJAS |
| Green Building Final | 12/10/2024 | Approved | RAUL BARAJAS |
| PLUMBING-Final | 12/10/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Enclosure/Fence | 12/18/2024 | Not Ready for Inspection | ROY SPAULDING |
| PLUMBING-Final | 12/18/2024 | Not Ready for Inspection | ROY SPAULDING |
| Enclosure/Fence | 12/19/2024 | Approved | RAUL BARAJAS |
| PLUMBING-Final | 12/19/2024 | Partial Inspection | RAUL BARAJAS |
| PLUMBING-Final | 2/13/2025 | Not Ready for Inspection | ROY SPAULDING |
| Gas Test | 2/25/2025 | Approved | ROY SPAULDING |
| PLUMBING-Final | 2/25/2025 | Not Ready for Inspection | ROY SPAULDING |
| PLUMBING-Final | 4/15/2025 | Approved | ROY SPAULDING |
| ELECTRICAL-Final | 4/24/2025 | Corrections Issued | SCOTT FINNILA |
| Final | 4/24/2025 | Not Ready for Inspection | SCOTT FINNILA |
| Smoke Detectors | 4/24/2025 | Approved | SCOTT FINNILA |
| ELECTRICAL-Final | 4/29/2025 | Not Ready for Inspection | ROY SPAULDING |
| Final | 4/29/2025 | Not Ready for Inspection | ROY SPAULDING |
| ELECTRICAL-Final | 5/5/2025 | Approved | BRIAN SULLIVAN |
| Final | 5/5/2025 | Not Ready for Inspection | BRIAN SULLIVAN |
| Final | 5/13/2025 | Permit Finaled | RAUL BARAJAS |