1133 S HOPE ST 90015
Certificate Information: 1133 S HOPE ST 90015
- Application / Permit
- 13010-10005-02854
- Plan Check / Job No.
- B17LA02053
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- PLAN REVISION; 1) REMOVE ONE LEVEL (P3) OF PARKING 2) CHANGE UNIT MIX ON LEVEL 5, 25,26,27 3) REMOVAL OF STRUCTURAL WALLS WITHIN CORE SHEARWALLS 4) UPPER PENHOUSE AND ROOF GARDEN REVISIONS 5) PT SLABS. (***THIS PERMIT COVER REVISIONS FROM GRADE LEVEL AND BELOW ONLY***)
- Permit Issued
- Issued on 7/18/2017
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 8/3/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2017 | SUEN LIEU |
| Corrections Issued | 2/24/2017 | SUEN LIEU |
| Disabled Access Plans Picked Up | 2/24/2017 | APPLICANT |
| Quality Review Completed | 2/27/2017 | DAVID CHANG |
| Building Plans Picked Up | 2/27/2017 | APPLICANT |
| Green Plans Picked Up | 3/2/2017 | APPLICANT |
| Applicant returned to address corrections | 3/13/2017 | SUEN LIEU |
| Applicant returned to address corrections | 4/18/2017 | SUEN LIEU |
| Applicant returned to address corrections | 4/21/2017 | SUEN LIEU |
| Applicant returned to address corrections | 4/24/2017 | SUEN LIEU |
| Applicant returned to address corrections | 4/25/2017 | SUEN LIEU |
| Applicant returned to address corrections | 5/3/2017 | SUEN LIEU |
| Applicant returned to address corrections | 5/4/2017 | SUEN LIEU |
| Plan Check Approved | 5/11/2017 | SUEN LIEU |
| Issued | 7/18/2017 | LADBS |
| Permit Finaled | 8/3/2020 | NICK DANERI |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/19/2017 | PAMELA TENEZA |
| Project located in CRA area | Cleared | 4/19/2017 | CRAIG BULLOCK |
| "D" conditions | Cleared | 5/3/2017 | SARAH GOLDMAN |
| Green Code | Cleared | 5/3/2017 | JOHN KLARIN |
| DAS Clearance | Cleared | 5/4/2017 | CHOI YAN |
| "Q" conditions | Cleared | 5/8/2017 | SARAH GOLDMAN |
| Opn space landscape/Water mgmt | Cleared | 5/8/2017 | SARAH GOLDMAN |
| Site Plan review | Cleared | 5/8/2017 | SARAH GOLDMAN |
| Tract Map conditions | Cleared | 5/8/2017 | SARAH GOLDMAN |
| Tract Map conditions | Cleared | 5/8/2017 | SARAH GOLDMAN |
| ZA Case | Cleared | 5/8/2017 | SARAH GOLDMAN |
| ZA Case | Cleared | 5/8/2017 | SARAH GOLDMAN |
| ZA Case | Cleared | 5/8/2017 | SARAH GOLDMAN |
| ZI | Cleared | 5/8/2017 | SARAH GOLDMAN |
| Methane Ordinance | Cleared | 5/9/2017 | DAVE MYERS |
| Sewer availability | Cleared | 5/9/2017 | ARMENIA AGUILAR |
| Title 19 building approval | Cleared | 5/9/2017 | ANDREW KO |
| Work Adjacent to Public Way | Cleared | 5/9/2017 | ARMENIA AGUILAR |
Contact Information
| Contractor | Lend Lease (Us) Construction Inc; Lic. No.: 483550-B | 200 PARK AVENUE 9TH FLOOR ATTN GENERAL COUNSEL NEW YORK, NY 10166 |
| Engineer | Arriola, Kirby Norman; Lic. No.: C31416 | PO BOX 5566 OXNARD, CA 93031 |
| Engineer | Berliner, Neal David; Lic. No.: GE2576 | 4913 MONUMENT ST SIMI VALLEY, CA 93063 |
| Engineer | Cummins, Charles Stephen; Lic. No.: C34526 | 17625 CRENSHAW BLVD SUITE 300 TORRANCE, CA 90504 |
| Engineer | Derkalousdian, Hrair Harry; Lic. No.: C79694 | 441 PALM DR 3 GLENDALE, CA 91202 |
| Engineer | Gerlick, Bradley J; Lic. No.: C83388 | 9401 MEADOW LEAF CT BAKERSFIELD, CA 93311 |
| Engineer | O'Keeffe, Michael John; Lic. No.: S4879 | 1661 W 5TH AVE VANCOUVER, BC, V6J1N5 |
| Geologist | Kasman, Gerald Alan; Lic. No.: EG2251 | 29072 GLADIOLUS DR CANYON COUNTRY, CA 91387 |
| Landscape Architect | Stoyko, David Lawrence; Lic. No.: LA5341 | 2686 EAST 6TH AVENUE BRITISH COLUMBIA VANCOUVER, V5M 1R3 |
Inspector Information
| RONALD JIMENEZ, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| LARRY ARNICK, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEY BUCHANAN, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| ERNESTO CORRAL, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL ESPINOZA, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Reinforced Concrete Frame | 8/10/2017 | Partial Inspection | ERNESTO CORRAL |
| Reinforced Concrete Frame | 8/17/2017 | Partial Inspection | ERNESTO CORRAL |
| Footing/Foundation/Slab | 8/29/2017 | Partial Inspection | ERNESTO CORRAL |
| Reinforced Concrete Frame | 9/8/2017 | Partial Inspection | ERNESTO CORRAL |
| Footing/Foundation/Slab | 9/13/2017 | Corrections Issued | ERNESTO CORRAL |
| Reinforced Concrete Frame | 9/15/2017 | Partial Approval | LESLIE TRUJILLO |
| Footing/Foundation/Slab | 9/21/2017 | Partial Inspection | ERNESTO CORRAL |
| Footing/Foundation/Slab | 9/25/2017 | Partial Inspection | ERNESTO CORRAL |
| Footing/Foundation/Slab | 10/3/2017 | Partial Inspection | ERNESTO CORRAL |
| Reinforced Concrete Frame | 10/3/2017 | Partial Inspection | ERNESTO CORRAL |
| Final | 10/5/2017 | Partial Inspection | ERNESTO CORRAL |
| METHANE-Final | 10/5/2017 | Approved | ERNESTO CORRAL |
| Reinforced Concrete Frame | 2/14/2018 | Not Ready for Inspection | ERNESTO CORRAL |
| Final | 8/3/2020 | Permit Finaled | NICK DANERI |
| Green Building Final | 8/3/2020 | Approved | NICK DANERI |