4418 S SLAUSON AVE #1-8 90230

Certificate Information: 4418 S SLAUSON AVE #1-8 90230

Application / Permit
13010-10000-04283
Plan Check / Job No.
B13LA16113
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONSTRUCT A 4-STORY,, 8-UNIT APARTMENT BLDG. OVER A SUBTERRANEAN GARAGE
Permit Issued
Issued on 6/24/2020
Issuing Office
West Los Angeles
Current Status
CofO Corrected on 12/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2013 APPLICANT
Assigned to Plan Check Engineer 1/30/2014 MOHAMMAD FIROUZBAKHT
Corrections Issued 2/6/2014 MOHAMMAD FIROUZBAKHT
Disabled Access Plans Picked Up 2/7/2014 APPLICANT
Green Plans Picked Up 2/13/2014 APPLICANT
Quality Review Completed 2/14/2014 GARO TELMI
Building Plans Picked Up 2/18/2014 APPLICANT
Applicant returned to address corrections 4/11/2019 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 3/4/2020 TEODORO DIAZ RODRIGUEZ
Issued 6/24/2020 LADBS
TCO Issued (Expire Date: 04-13-2025) 10/15/2024 HENRY BAGHDASSARIAN
CofO in Progress 10/17/2024 DERRICK SPENCER
CofO Issued-Status Void 10/17/2024 HENRY BAGHDASSARIAN
Permit Finaled-Status Void 10/17/2024 HENRY BAGHDASSARIAN
Re-Activate Permit 12/12/2024 DAVID TSAU
Permit Finaled 12/13/2024 HENRY BAGHDASSARIAN
CofO Corrected 12/13/2024 HENRY BAGHDASSARIAN
Permit Finaled 12/13/2024 HENRY BAGHDASSARIAN

Permit Application Clearance Information

Address approval Cleared 2/19/2014 JAMES KHO
Highway dedication Cleared 2/18/2015 JAMES KHO
DAS Clearance Cleared 5/26/2015 WAI LAU
Eng Process Fee Ord 176,300 Cleared 5/28/2015 PAMELA TENEZA
Hydrant and Access approval Cleared 5/28/2015 ROBERT DUFF
Specific Plan Cleared 11/17/2016 EDER ROMERO
Green Code Cleared 10/26/2017 DONALD CRICHLOW
Sewer availability Cleared 3/21/2019 ELAINE LEI
Fire Marshall Fire Life Safety Cleared 5/9/2019 MENOA AGHAJANI
Low Impact Development Cleared 1/29/2020 SARAH YOUSSEF
Opn space landscape/Water mgmt Cleared 1/29/2020 SARAHI ORTEGA
Permit Cleared 1/29/2020 THOMAS LANG
Roof/Waste drainage to street Cleared 1/29/2020 THOMAS LANG
Stormwater Pollution Mitigatn Cleared 2/27/2020 SARAH YOUSSEF
Building over 3-story or 36-ft Cleared 3/4/2020 CALOSHA APPROVED

Contact Information

Contractor A T Construction & Consultant; Lic. No.: 671011-B 73 PORTUGUESE BEND ROAD      ROLLING HILLS, CA 90274

Inspector Information

VASIL MIHALEV, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/1/2021 Approved NICK LAROCCA
Excavation/Setback/Form/Re-Bar 4/12/2021 Not Ready for Inspection NICK LAROCCA
Pre-Inspection 9/28/2021 Partial Inspection NICK LAROCCA
Pre-Inspection 3/25/2022 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 4/22/2022 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 5/3/2022 Partial Approval DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 5/12/2022 Partial Approval ALAN NOVAK
Footing/Foundation/Slab 5/12/2022 Partial Approval ALAN NOVAK
Deputy Reinf. Concrete 5/13/2022 Approved NICK LAROCCA
Deputy Reinf. Concrete 5/17/2022 Approved NICK LAROCCA
Deputy Reinf. Concrete 5/18/2022 Approved NICK LAROCCA
Excavation/Setback/Form/Re-Bar 5/18/2022 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 5/19/2022 Approved NICK LAROCCA
Excavation/Setback/Form/Re-Bar 5/20/2022 Not Ready for Inspection JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 5/21/2022 Partial Approval NICK LAROCCA
Footing/Foundation/Slab 5/21/2022 Off-Hour Fees Due
Footing/Foundation/Slab 5/21/2022 Partial Inspection NICK LAROCCA
Deputy Shotcrete 5/24/2022 Approved NICK LAROCCA
Footing/Foundation/Slab 5/24/2022 Partial Inspection NICK LAROCCA
Deputy Reinf. Concrete 6/2/2022 Approved NICK LAROCCA
Excavation/Setback/Form/Re-Bar 6/2/2022 Partial Approval NICK LAROCCA
Deputy Reinf. Concrete 6/6/2022 Approved DERRICK SPENCER
Deputy Drilled-In Anchors 6/15/2022 Conditional Approval DERRICK SPENCER
Deputy Reinf. Concrete 6/16/2022 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 6/16/2022 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 6/17/2022 Approved DERRICK SPENCER
Deputy Reinf. Concrete 7/5/2022 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 7/5/2022 Partial Approval DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 7/6/2022 Partial Approval DERRICK SPENCER
Deputy Drilled-In Anchors 7/8/2022 Conditional Approval DAVID TSAU
Deputy Reinf. Concrete 7/12/2022 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 7/12/2022 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 7/14/2022 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 7/14/2022 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 7/14/2022 Partial Approval DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 7/25/2022 Partial Approval DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 7/27/2022 Partial Approval DERRICK SPENCER
Deputy Wood Construction 7/28/2022 Approved DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 7/28/2022 Partial Approval DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 7/29/2022 Partial Approval DERRICK SPENCER
Deputy Wood Construction 8/4/2022 Approved DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 8/4/2022 Partial Approval DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 8/5/2022 Partial Approval DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 8/11/2022 Partial Approval DERRICK SPENCER
Deputy Wood Construction 8/12/2022 Approved DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 8/12/2022 Partial Approval DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 8/15/2022 Partial Approval DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 8/23/2022 Not Ready for Inspection DERRICK SPENCER
Deputy Wood Construction 9/7/2022 Conditional Approval DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 9/7/2022 Partial Approval DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 9/12/2022 Partial Approval DERRICK SPENCER
Deputy Drilled-In Anchors 9/14/2022 Approved DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 9/29/2022 Partial Approval DERRICK SPENCER
Green Building Rough 10/4/2022 Not Ready for Inspection DERRICK SPENCER
Verify Sprinkler Sign Off 10/4/2022 Approved DERRICK SPENCER
Wood Frame 10/4/2022 Partial Approval DERRICK SPENCER
Insulation 10/7/2022 Partial Approval DERRICK SPENCER
Deputy Drilled-In Anchors 10/17/2022 Approved DERRICK SPENCER
Deputy Wood Construction 10/17/2022 Conditional Approval DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 10/18/2022 Partial Approval DERRICK SPENCER
Deputy Wood Construction 10/19/2022 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 10/19/2022 Partial Approval DERRICK SPENCER
Pre-Inspection 10/24/2022 Approved DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 10/28/2022 Partial Approval DERRICK SPENCER
Insulation 11/3/2022 Partial Approval DERRICK SPENCER
Drywall Nailing 11/14/2022 Partial Approval DERRICK SPENCER
SUSMP-Std. Urban Storm Water 11/29/2022 Not Ready for Inspection DERRICK SPENCER
Pre-Inspection 12/1/2022 Approved DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 12/5/2022 Partial Approval DERRICK SPENCER
Insulation 12/8/2022 Partial Approval DERRICK SPENCER
SUSMP-Std. Urban Storm Water 12/13/2022 Approved DERRICK SPENCER
SWPPP-Const. Storm Water 12/27/2022 Violation Observed DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 12/28/2022 Partial Approval DERRICK SPENCER
Pre-Inspection 12/29/2022 Approved DERRICK SPENCER
Green Building Rough 1/3/2023 Approved DERRICK SPENCER
Wood Frame 1/3/2023 Partial Approval DERRICK SPENCER
Insulation 1/11/2023 Approved DERRICK SPENCER
Deputy Wood Construction 1/13/2023 Approved DERRICK SPENCER
Drywall Nailing 1/13/2023 Partial Approval DERRICK SPENCER
Insulation 1/13/2023 Partial Approval DERRICK SPENCER
Drywall Nailing 1/19/2023 Not Ready for Inspection DERRICK SPENCER
Drywall Nailing 1/27/2023 Approved DERRICK SPENCER
Pre-Inspection 1/27/2023 Approved DERRICK SPENCER
Interior/Exterior Lathing 2/8/2023 Approved DERRICK SPENCER
Drywall Nailing 2/9/2023 Approved DERRICK SPENCER
Interior/Exterior Lathing 2/22/2023 Partial Approval DERRICK SPENCER
SWPPP-Const. Storm Water 2/28/2023 Completed DERRICK SPENCER
Pre-Inspection 3/13/2023 Approved DERRICK SPENCER
Deputy Drilled-In Anchors 5/24/2023 Approved DERRICK SPENCER
Deputy Drilled-In Anchors 5/30/2023 Conditional Approval DERRICK SPENCER
Reinforced Concrete Frame 5/30/2023 Partial Approval DERRICK SPENCER
Special/Order Compliance 6/14/2023 Approved DERRICK SPENCER
Final 8/7/2023 Not Ready for Inspection DERRICK SPENCER
Footing/Foundation/Slab 8/7/2023 Approved DERRICK SPENCER
Green Building Final 8/7/2023 Not Ready for Inspection DERRICK SPENCER
Reinforced Masonry Frame 8/7/2023 Approved DERRICK SPENCER
SGSOV-Seismic Gas S/O Valve 8/7/2023 SGSOV Approved DERRICK SPENCER
Smoke Detectors 8/7/2023 Approved DERRICK SPENCER
Wood Frame 8/7/2023 Approved DERRICK SPENCER
Final 8/21/2023 Not Ready for Inspection DERRICK SPENCER
Green Building Final 8/21/2023 Approved DERRICK SPENCER
Final 10/4/2023 Not Ready for Inspection DERRICK SPENCER
Final 6/12/2024 Corrections Issued DERRICK SPENCER
Final 9/18/2024 OK to Issue CofO DERRICK SPENCER