|
Pre-Inspection
|
3/1/2021
|
Approved
|
NICK LAROCCA
|
|
Excavation/Setback/Form/Re-Bar
|
4/12/2021
|
Not Ready for Inspection
|
NICK LAROCCA
|
|
Pre-Inspection
|
9/28/2021
|
Partial Inspection
|
NICK LAROCCA
|
|
Pre-Inspection
|
3/25/2022
|
Approved
|
DERRICK SPENCER
|
|
Excavation/Setback/Form/Re-Bar
|
4/22/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Footing/Foundation/Slab
|
5/3/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Excavation/Setback/Form/Re-Bar
|
5/12/2022
|
Partial Approval
|
ALAN NOVAK
|
|
Footing/Foundation/Slab
|
5/12/2022
|
Partial Approval
|
ALAN NOVAK
|
|
Deputy Reinf. Concrete
|
5/13/2022
|
Approved
|
NICK LAROCCA
|
|
Deputy Reinf. Concrete
|
5/17/2022
|
Approved
|
NICK LAROCCA
|
|
Deputy Reinf. Concrete
|
5/18/2022
|
Approved
|
NICK LAROCCA
|
|
Excavation/Setback/Form/Re-Bar
|
5/18/2022
|
Partial Approval
|
NICK LAROCCA
|
|
Deputy Reinf. Concrete
|
5/19/2022
|
Approved
|
NICK LAROCCA
|
|
Excavation/Setback/Form/Re-Bar
|
5/20/2022
|
Not Ready for Inspection
|
JOEY BUCHANAN
|
|
Excavation/Setback/Form/Re-Bar
|
5/21/2022
|
Partial Approval
|
NICK LAROCCA
|
|
Footing/Foundation/Slab
|
5/21/2022
|
Off-Hour Fees Due
|
|
|
Footing/Foundation/Slab
|
5/21/2022
|
Partial Inspection
|
NICK LAROCCA
|
|
Deputy Shotcrete
|
5/24/2022
|
Approved
|
NICK LAROCCA
|
|
Footing/Foundation/Slab
|
5/24/2022
|
Partial Inspection
|
NICK LAROCCA
|
|
Deputy Reinf. Concrete
|
6/2/2022
|
Approved
|
NICK LAROCCA
|
|
Excavation/Setback/Form/Re-Bar
|
6/2/2022
|
Partial Approval
|
NICK LAROCCA
|
|
Deputy Reinf. Concrete
|
6/6/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Drilled-In Anchors
|
6/15/2022
|
Conditional Approval
|
DERRICK SPENCER
|
|
Deputy Reinf. Concrete
|
6/16/2022
|
Approved
|
DERRICK SPENCER
|
|
Excavation/Setback/Form/Re-Bar
|
6/16/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Deputy Reinf. Concrete
|
6/17/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Reinf. Concrete
|
7/5/2022
|
Approved
|
DERRICK SPENCER
|
|
Excavation/Setback/Form/Re-Bar
|
7/5/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Excavation/Setback/Form/Re-Bar
|
7/6/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Deputy Drilled-In Anchors
|
7/8/2022
|
Conditional Approval
|
DAVID TSAU
|
|
Deputy Reinf. Concrete
|
7/12/2022
|
Approved
|
DERRICK SPENCER
|
|
Excavation/Setback/Form/Re-Bar
|
7/12/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Deputy Reinf. Concrete
|
7/14/2022
|
Approved
|
DERRICK SPENCER
|
|
Excavation/Setback/Form/Re-Bar
|
7/14/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Footing/Foundation/Slab
|
7/14/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/25/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/27/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Deputy Wood Construction
|
7/28/2022
|
Approved
|
DERRICK SPENCER
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/28/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/29/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Deputy Wood Construction
|
8/4/2022
|
Approved
|
DERRICK SPENCER
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/4/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/5/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/11/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Deputy Wood Construction
|
8/12/2022
|
Approved
|
DERRICK SPENCER
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/12/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/15/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/23/2022
|
Not Ready for Inspection
|
DERRICK SPENCER
|
|
Deputy Wood Construction
|
9/7/2022
|
Conditional Approval
|
DERRICK SPENCER
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/7/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/12/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Deputy Drilled-In Anchors
|
9/14/2022
|
Approved
|
DERRICK SPENCER
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/29/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Green Building Rough
|
10/4/2022
|
Not Ready for Inspection
|
DERRICK SPENCER
|
|
Verify Sprinkler Sign Off
|
10/4/2022
|
Approved
|
DERRICK SPENCER
|
|
Wood Frame
|
10/4/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Insulation
|
10/7/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Deputy Drilled-In Anchors
|
10/17/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Wood Construction
|
10/17/2022
|
Conditional Approval
|
DERRICK SPENCER
|
|
Excavation/Setback/Form/Re-Bar
|
10/18/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Deputy Wood Construction
|
10/19/2022
|
Approved
|
DERRICK SPENCER
|
|
Excavation/Setback/Form/Re-Bar
|
10/19/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Pre-Inspection
|
10/24/2022
|
Approved
|
DERRICK SPENCER
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/28/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Insulation
|
11/3/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Drywall Nailing
|
11/14/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
SUSMP-Std. Urban Storm Water
|
11/29/2022
|
Not Ready for Inspection
|
DERRICK SPENCER
|
|
Pre-Inspection
|
12/1/2022
|
Approved
|
DERRICK SPENCER
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/5/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Insulation
|
12/8/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
SUSMP-Std. Urban Storm Water
|
12/13/2022
|
Approved
|
DERRICK SPENCER
|
|
SWPPP-Const. Storm Water
|
12/27/2022
|
Violation Observed
|
DERRICK SPENCER
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/28/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Pre-Inspection
|
12/29/2022
|
Approved
|
DERRICK SPENCER
|
|
Green Building Rough
|
1/3/2023
|
Approved
|
DERRICK SPENCER
|
|
Wood Frame
|
1/3/2023
|
Partial Approval
|
DERRICK SPENCER
|
|
Insulation
|
1/11/2023
|
Approved
|
DERRICK SPENCER
|
|
Deputy Wood Construction
|
1/13/2023
|
Approved
|
DERRICK SPENCER
|
|
Drywall Nailing
|
1/13/2023
|
Partial Approval
|
DERRICK SPENCER
|
|
Insulation
|
1/13/2023
|
Partial Approval
|
DERRICK SPENCER
|
|
Drywall Nailing
|
1/19/2023
|
Not Ready for Inspection
|
DERRICK SPENCER
|
|
Drywall Nailing
|
1/27/2023
|
Approved
|
DERRICK SPENCER
|
|
Pre-Inspection
|
1/27/2023
|
Approved
|
DERRICK SPENCER
|
|
Interior/Exterior Lathing
|
2/8/2023
|
Approved
|
DERRICK SPENCER
|
|
Drywall Nailing
|
2/9/2023
|
Approved
|
DERRICK SPENCER
|
|
Interior/Exterior Lathing
|
2/22/2023
|
Partial Approval
|
DERRICK SPENCER
|
|
SWPPP-Const. Storm Water
|
2/28/2023
|
Completed
|
DERRICK SPENCER
|
|
Pre-Inspection
|
3/13/2023
|
Approved
|
DERRICK SPENCER
|
|
Deputy Drilled-In Anchors
|
5/24/2023
|
Approved
|
DERRICK SPENCER
|
|
Deputy Drilled-In Anchors
|
5/30/2023
|
Conditional Approval
|
DERRICK SPENCER
|
|
Reinforced Concrete Frame
|
5/30/2023
|
Partial Approval
|
DERRICK SPENCER
|
|
Special/Order Compliance
|
6/14/2023
|
Approved
|
DERRICK SPENCER
|
|
Final
|
8/7/2023
|
Not Ready for Inspection
|
DERRICK SPENCER
|
|
Footing/Foundation/Slab
|
8/7/2023
|
Approved
|
DERRICK SPENCER
|
|
Green Building Final
|
8/7/2023
|
Not Ready for Inspection
|
DERRICK SPENCER
|
|
Reinforced Masonry Frame
|
8/7/2023
|
Approved
|
DERRICK SPENCER
|
|
SGSOV-Seismic Gas S/O Valve
|
8/7/2023
|
SGSOV Approved
|
DERRICK SPENCER
|
|
Smoke Detectors
|
8/7/2023
|
Approved
|
DERRICK SPENCER
|
|
Wood Frame
|
8/7/2023
|
Approved
|
DERRICK SPENCER
|
|
Final
|
8/21/2023
|
Not Ready for Inspection
|
DERRICK SPENCER
|
|
Green Building Final
|
8/21/2023
|
Approved
|
DERRICK SPENCER
|
|
Final
|
10/4/2023
|
Not Ready for Inspection
|
DERRICK SPENCER
|
|
Final
|
6/12/2024
|
Corrections Issued
|
DERRICK SPENCER
|
|
Final
|
9/18/2024
|
OK to Issue CofO
|
DERRICK SPENCER
|