- New Two Story (28'-5"x 37'-0") SFD with Attached Garage
- Permit Issued
- Issued on 12/15/2016
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/23/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/17/2013 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2014 | DANNY TANG |
| Corrections Issued | 2/3/2014 | DANNY TANG |
| Quality Review Completed | 2/10/2014 | GARO TELMI |
| Building Plans Picked Up | 2/12/2014 | APPLICANT |
| Green Plans Picked Up | 2/12/2014 | APPLICANT |
| Applicant returned to address corrections | 9/30/2015 | CHIU TAM |
| Applicant returned to address corrections | 1/8/2016 | CHIU TAM |
| Applicant returned to address corrections | 11/10/2016 | YOUNG KIM |
| Applicant returned to address corrections | 12/6/2016 | YOUNG KIM |
| Plan Check Approved | 12/15/2016 | YOUNG KIM |
| Issued | 12/15/2016 | LADBS |
| CofO in Progress | 9/21/2020 | ELMER BLAND |
| Permit Finaled | 9/23/2020 | DEROLD HAUFF |
| CofO Issued | 9/23/2020 | DEROLD HAUFF |
| Permit Finaled | 9/23/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/14/2014 | RICHARD SOUTHERLAND |
| Distance to fire station | Cleared | 5/28/2015 | ROBERT DUFF |
| Hydrant and Access approval | Cleared | 5/28/2015 | ROBERT DUFF |
| CPC | Cleared | 6/22/2015 | RALPH AVILA |
| Low Impact Development | Cleared | 6/24/2015 | MARTIN FRAGOSO |
| Green Code | Cleared | 6/30/2015 | MARCUS LEVIAS |
| BHO/Hillside ordinance | Cleared | 9/28/2015 | AVALYN KAMACHI |
| BHO/Hillside ordinance | Cleared | 9/28/2015 | AVALYN KAMACHI |
| BHO/Hillside ordinance | Cleared | 9/28/2015 | AVALYN KAMACHI |
| BHO/Hillside ordinance | Cleared | 9/28/2015 | AVALYN KAMACHI |
| Drainage to Storm Drain | Cleared | 9/28/2015 | AVALYN KAMACHI |
| Eng Process Fee Ord 176,300 | Cleared | 9/28/2015 | AVALYN KAMACHI |
| Permit | Cleared | 9/28/2015 | AVALYN KAMACHI |
| Roof/Waste drainage to street | Cleared | 9/28/2015 | AVALYN KAMACHI |
| Sewer availability | Cleared | 9/28/2015 | AVALYN KAMACHI |
| "D" conditions | Cleared | 11/3/2015 | MARY RICHARDSON |
| "Q" conditions | Cleared | 11/3/2015 | MARY RICHARDSON |
| ZI | Cleared | 11/3/2015 | MARY RICHARDSON |
| Mailing Labels | Cleared | 12/14/2016 | DANNY TANG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Carrizosa, Richard Garcia; Lic. No.: C25828 | 1505 LYNDHURST AVE HACIENDA HEIGHTS, CA 917452932 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/15/2017 | No Access for Inspection | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 8/8/2017 | Not Ready for Inspection | DOMINIC DANERI |
| Footing/Foundation/Slab | 8/8/2017 | Not Ready for Inspection | DOMINIC DANERI |
| ELECTRICAL-Rough | 8/10/2017 | Not Ready for Inspection | RUBEN SALAS |
| Footing/Foundation/Slab | 8/10/2017 | Partial Inspection | RUBEN SALAS |
| Footing/Foundation/Slab | 8/14/2017 | Partial Approval | ENRIQUE MIRELES |
| Service/Power Release | 8/14/2017 | Partial Inspection | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 9/12/2017 | Partial Approval | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 9/19/2017 | Partial Approval | ENRIQUE MIRELES |
| Underground Mechanical | 11/21/2017 | Partial Approval | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/1/2017 | Partial Approval | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 7/9/2018 | Not Ready for Inspection | ENRIQUE MIRELES |
| Deputy Drilled-In Anchors | 9/14/2018 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 9/18/2018 | Approved | ENRIQUE MIRELES |
| Deputy Reinf. Concrete | 9/20/2018 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 11/26/2018 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Rough | 11/26/2018 | Not Ready for Inspection | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 11/26/2018 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 12/18/2018 | Partial Approval | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 12/18/2018 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 12/18/2018 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 12/18/2018 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/18/2018 | Not Ready for Inspection | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 12/18/2018 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 1/3/2019 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 1/3/2019 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 1/3/2019 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 1/3/2019 | Approved | ENRIQUE MIRELES |
| Special/Order Compliance | 1/3/2019 | Approved | RUBEN SALAS |
| ELECTRICAL-Rough | 1/11/2019 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 1/23/2019 | Approved | ENRIQUE MIRELES |
| Special/Order Compliance | 5/16/2019 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 4/23/2020 | Approved | ENRIQUE MIRELES |
| Final | 4/23/2020 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 4/23/2020 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 4/23/2020 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 4/23/2020 | Approved | ENRIQUE MIRELES |
| Reinforced Masonry Frame | 4/23/2020 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 4/23/2020 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 4/23/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Smoke Detectors | 4/23/2020 | Approved | ENRIQUE MIRELES |
| Structural Steel Frame | 4/23/2020 | Approved | ENRIQUE MIRELES |
| Final | 4/30/2020 | Corrections Issued | ENRIQUE MIRELES |
| Service/Power Release | 4/30/2020 | Approved | ENRIQUE MIRELES |
| Final | 8/7/2020 | Partial Approval | ENRIQUE MIRELES |
| Final | 9/21/2020 | OK to Issue CofO | ELMER BLAND |