8730 S FIGUEROA ST 90003
Certificate Information: 8730 S FIGUEROA ST 90003
- Application / Permit
- 13010-10000-04084
- Plan Check / Job No.
- B13LA15721
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- New apartment with attached garage.
- Permit Issued
- Issued on 8/18/2014
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/16/2013 | APPLICANT |
| Assigned to Plan Check Engineer | 12/26/2013 | JESSE CARDOZA |
| Disabled Access Plans Picked Up | 1/2/2014 | APPLICANT |
| Green Plans Picked Up | 1/2/2014 | APPLICANT |
| Corrections Issued | 1/6/2014 | JESSE CARDOZA |
| Quality Review Completed | 1/17/2014 | BILL STUTSMAN |
| Building Plans Picked Up | 1/27/2014 | APPLICANT |
| Applicant returned to address corrections | 4/22/2014 | JESSE CARDOZA |
| Applicant returned to address corrections | 4/23/2014 | JESSE CARDOZA |
| Applicant returned to address corrections | 5/12/2014 | JESSE CARDOZA |
| Plan Check Approved | 8/18/2014 | JESSE CARDOZA |
| Issued | 8/18/2014 | LADBS |
| CofO in Progress | 10/25/2021 | JAMES POWERS |
| Permit Finaled | 10/25/2021 | WINSTON DUNNING |
| CofO Issued | 10/25/2021 | WINSTON DUNNING |
| Permit Finaled | 10/25/2021 | WINSTON DUNNING |
Permit Application Clearance Information
| Address approval | Cleared | 5/15/2014 | AVALYN KAMACHI |
| Eng Process Fee Ord 176,300 | Cleared | 5/16/2014 | AVALYN KAMACHI |
| Hydrant and Access approval | Cleared | 5/16/2014 | JOSEPH JACKSON |
| Sewer availability | Cleared | 5/19/2014 | AVALYN KAMACHI |
| Construction within easement | Cleared | 5/28/2014 | LUCIO FERRER |
| Green Code | Cleared | 6/2/2014 | RUSSELL KELLY |
| Green Code | Cleared | 6/2/2014 | RUSSELL KELLY |
| Highway dedication | Cleared | 7/8/2014 | JAMES MORALEZ |
| DAS Clearance | Cleared | 7/29/2014 | JESSE CARDOZA |
| Low Impact Development | Cleared | 8/4/2014 | AMMAR ELTAWIL |
| Permit | Cleared | 8/5/2014 | JULIA MOYE |
| Roof/Waste drainage to street | Cleared | 8/5/2014 | JULIA MOYE |
| Work Adjacent to Public Way | Cleared | 8/5/2014 | JULIA MOYE |
| Miscellaneous | Cleared | 8/18/2014 | JESSE CARDOZA |
Contact Information
| Contractor | Harvey Ralph Donell; Lic. No.: 652651-B | 11715 SOUTH WILTON PLACE HAWTHORNE, CA 90250 |
| Engineer | Nieto, Jose M; Lic. No.: C36968 | PO BOX 1434 CULVER CITY, CA 90232 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/4/2014 | Corrections Issued | BYRON FUENTES |
| Footing/Foundation/Slab | 11/6/2014 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 2/5/2015 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 2/17/2015 | Not Ready for Inspection | BYRON FUENTES |
| Footing/Foundation/Slab | 2/24/2015 | Approved | BYRON FUENTES |
| Deputy Reinf. Concrete | 3/5/2015 | No Access for Inspection | BYRON FUENTES |
| Piling/Pier/Caisson | 3/5/2015 | Corrections Issued | BYRON FUENTES |
| Deputy Reinf. Concrete | 3/6/2015 | Approved | BYRON FUENTES |
| Deputy Steel/Welding | 1/8/2016 | Approved | BYRON FUENTES |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2016 | Conditional Approval | BYRON FUENTES |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2016 | Partial Approval | BYRON FUENTES |
| Green Building Rough | 3/31/2016 | Not Ready for Inspection | JOHN KLARIN |
| Structural Steel Frame | 3/31/2016 | Conditional Approval | BYRON FUENTES |
| Verify Sprinkler Sign Off | 3/31/2016 | Not Ready for Inspection | BYRON FUENTES |
| Green Building Rough | 8/5/2016 | Not Ready for Inspection | JOHN KLARIN |
| Verify Sprinkler Sign Off | 8/5/2016 | Not Ready for Inspection | JEFFREY FULTON |
| Wood Frame | 8/5/2016 | Partial Inspection | JEFFREY FULTON |
| Final | 10/24/2016 | Not Ready for Inspection | BYRON FUENTES |
| Green Building Rough | 11/4/2016 | Not Ready for Inspection | JOHN KLARIN |
| Verify Sprinkler Sign Off | 11/4/2016 | Not Ready for Inspection | JAMES POWERS |
| Wood Frame | 11/4/2016 | Not Ready for Inspection | JAMES POWERS |
| Green Building Rough | 1/23/2018 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 1/23/2018 | Not Ready for Inspection | JAMES POWERS |
| Wood Frame | 1/23/2018 | Not Ready for Inspection | JAMES POWERS |
| Green Building Rough | 2/26/2018 | Partial Approval | JAMES POWERS |
| Verify Sprinkler Sign Off | 2/26/2018 | No Access for Inspection | JAMES POWERS |
| Wood Frame | 2/26/2018 | Not Ready for Inspection | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2018 | Partial Approval | JAMES POWERS |
| Interior/Exterior Lathing | 5/1/2018 | Partial Approval | JAMES POWERS |
| Interior/Exterior Lathing | 5/17/2018 | Approved | JAMES POWERS |
| Green Building Rough | 7/2/2018 | Approved | JAMES POWERS |
| Verify Sprinkler Sign Off | 7/2/2018 | Approved | JAMES POWERS |
| Wood Frame | 7/2/2018 | Approved | JAMES POWERS |
| Drywall Nailing | 3/4/2019 | Not Ready for Inspection | JAMES POWERS |
| Insulation | 3/8/2019 | Approved | JAMES POWERS |
| Drywall Nailing | 3/19/2019 | Approved | JAMES POWERS |
| Interior/Exterior Lathing | 4/10/2019 | Approved | JAMES POWERS |
| Final | 2/24/2021 | Not Ready for Inspection | JAMES POWERS |
| Green Building Final | 2/24/2021 | Approved | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 2/24/2021 | SGSOV Approved | JAMES POWERS |
| Smoke Detectors | 2/24/2021 | Approved | JAMES POWERS |
| Structural Steel Frame | 2/24/2021 | Approved | JAMES POWERS |
| Final | 3/24/2021 | Not Ready for Inspection | JAMES POWERS |
| Final | 10/4/2021 | OK for TCO | JAMES POWERS |
| Final | 10/14/2021 | Not Ready for Inspection | JAMES POWERS |
| Final | 10/25/2021 | OK to Issue CofO | JAMES POWERS |