6417 W SELMA AVE 90028

Certificate Information: 6417 W SELMA AVE 90028

Application / Permit
13010-10000-03647
Plan Check / Job No.
B13LA14815
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(11) Hotel
Work Description
10-STORY HOTEL BUILDING; PARKING, EQUIPMENT AND UTILITY ROOMS, TRASH AND RECYCLE ROOMS AT 1ST AND 2ND STORY LEVELS, GUEST ROOMS FROM 3 TO 9 STORY LEVELS, WITH ROOF TOP STAIRWAY AND ELEVATOR ROOMS; 10 STORY LEVEL CORE AND SHELL.
Permit Issued
Issued on 7/10/2014
Issuing Office
Metro
Current Status
CofO Issued on 6/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/25/2013 APPLICANT
Assigned to Plan Check Engineer 12/19/2013 BIDYUT RATH
Green Plans Picked Up 1/6/2014 APPLICANT
Disabled Access Plans Picked Up 1/10/2014 APPLICANT
Corrections Issued 1/27/2014 BIDYUT RATH
Quality Review Completed 1/31/2014 TIEN JEN WANG
Building Plans Picked Up 1/31/2014 APPLICANT
Applicant returned to address corrections 2/12/2014 BIDYUT RATH
Applicant returned to address corrections 2/18/2014 BIDYUT RATH
Applicant returned to address corrections 2/25/2014 BIDYUT RATH
Applicant returned to address corrections 3/6/2014 BIDYUT RATH
Applicant returned to address corrections 3/17/2014 BIDYUT RATH
Applicant returned to address corrections 3/24/2014 BIDYUT RATH
Applicant returned to address corrections 4/10/2014 BIDYUT RATH
Applicant returned to address corrections 4/24/2014 BIDYUT RATH
Applicant returned to address corrections 5/7/2014 BIDYUT RATH
Applicant returned to address corrections 5/14/2014 BIDYUT RATH
Applicant returned to address corrections 7/8/2014 BIDYUT RATH
Plan Check Approved 7/10/2014 BIDYUT RATH
Issued 7/10/2014 LADBS
TCO Issued (Expire Date: 12-27-2017) 6/30/2017 HENRY BAGHDASSARIAN
TCO Issued (Expire Date: 06-25-2018) 12/27/2017 HENRY BAGHDASSARIAN
TCO Issued (Expire Date: 01-05-2019) 7/9/2018 RICKEY JACKSON
TCO Issued (Expire Date: 03-11-2020) 9/13/2019 TERRY HERR
TCO Issued (Expire Date: 12-27-2020) 6/30/2020 DAVID TSAU
TCO Issued (Expire Date: 10-19-2021) 4/22/2021 ERNESTO CORRAL
TCO Issued (Expire Date: 05-04-2022) 11/5/2021 ERNESTO CORRAL
TCO Issued (Expire Date: 05-21-2023) 11/22/2022 ERNESTO CORRAL
CofO in Progress 6/14/2023 DAVID BURKHEAD
CofO Issued 6/15/2023 ERNESTO CORRAL
Permit Finaled 6/15/2023 ERNESTO CORRAL

Permit Application Clearance Information

Encroachment in public way Cleared 1/16/2014 ARMENIA HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 1/16/2014 ARMENIA HERNANDEZ
Address approval Cleared 2/4/2014 AVALYN KAMACHI
Permit Cleared 2/4/2014 AVALYN KAMACHI
Internal circulation Cleared 3/12/2014 COLLINS ALLAN
ZA Case Cleared 4/9/2014 MINDY NGUYEN
ZA Case Cleared 4/9/2014 MINDY NGUYEN
ZA Case Cleared 4/9/2014 MINDY NGUYEN
Building over 3-story or 36-ft Cleared 4/10/2014 CALOSHA APPROVED
Food Service Establishment Cleared 4/16/2014 RAMESHBHAIR PATEL
Sewer availability Cleared 4/21/2014 ARMENIA HERNANDEZ
Excavation more than 5-ft deep Cleared 4/24/2014 CALOSHA APPROVED
Work Adjacent to Public Way Cleared 4/24/2014 TERRY PHAN
ZA Case Cleared 4/25/2014 MINDY NGUYEN
ZI Cleared 4/25/2014 MINDY NGUYEN
Hydrant and Access approval Cleared 4/28/2014 ROBERT DUFF
Project located in CRA area Cleared 4/30/2014 JIM URQUHART
Green Code Cleared 5/15/2014 MARCUS LEVIAS
Low Impact Development Cleared 5/29/2014 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 5/29/2014 JULIA MOYE
Stormwater Pollution Mitigatn Cleared 5/29/2014 MARTIN FRAGOSO
DAS Clearance Cleared 6/12/2014 EDDIE GARIN
Title 19 building approval Cleared 6/12/2014 ANDREW KO
"D" conditions Cleared 7/7/2014 BRIDGETTE WOOTEN
"Q" conditions Cleared 7/7/2014 BRIDGETTE WOOTEN
"T" removal Cleared 7/7/2014 BRIDGETTE WOOTEN
CPC Cleared 7/7/2014 BRIDGETTE WOOTEN
Frnt yard landscape/Water mgmt Cleared 7/7/2014 BRIDGETTE WOOTEN
Prkng lot landscape/Water mgmt Cleared 7/7/2014 BRIDGETTE WOOTEN
ZA Case Cleared 7/7/2014 BRIDGETTE WOOTEN
ZI Cleared 7/7/2014 BRIDGETTE WOOTEN

Contact Information

Architect Flammang, Barbara Hansen; Lic. No.: C13422 1625 OLYMPIC BLVD      SANTA MONICA, CA 90404
Contractor Five Chairs Construction; Lic. No.: 488672-B 1605 CAHUENGA BLVD      LOS ANGELES, CA 90028
Engineer Bains, Gagan Prit Singh; Lic. No.: S4482 307 N SANTA ANITA AVE STE B      ARCADIA, CA 91006
Engineer Bernal, Andres; Lic. No.: GE2715 4373 VIEWRIDGE AVE STE B      SAN DIEGO, CA 92123
Engineer Nasrollahi, Tahmoores; Lic. No.: M22301 6652 VICKIVIEW DR      WEST HILLS, CA 91307

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/15/2014 Partial Inspection SAKO AGHAZARIAN
Excavation/Setback/Form/Re-Bar 7/22/2014 Partial Approval BARRY SILLS
Deputy Reinf. Concrete 7/23/2014 Conditional Approval BARRY SILLS
Deputy Reinf. Concrete 7/24/2014 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/25/2014 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/28/2014 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/29/2014 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/30/2014 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/31/2014 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/1/2014 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/4/2014 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/5/2014 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/6/2014 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/7/2014 Approved SAKO AGHAZARIAN
Excavation/Setback/Form/Re-Bar 8/7/2014 Partial Approval SAKO AGHAZARIAN
Footing/Foundation/Slab 8/7/2014 Partial Inspection SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/11/2014 Approved SAKO AGHAZARIAN
Excavation/Setback/Form/Re-Bar 8/11/2014 Partial Inspection SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/12/2014 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/13/2014 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/14/2014 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/15/2014 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/19/2014 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 9/3/2014 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/4/2014 Conditional Approval BARRY SILLS
Deputy Reinf. Concrete 9/5/2014 Conditional Approval BARRY SILLS
Deputy Reinf. Concrete 10/7/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 10/7/2014 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 10/8/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 10/8/2014 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 10/9/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 10/9/2014 Approved SAKO AGHAZARIAN
Footing/Foundation/Slab 10/9/2014 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 10/10/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 10/10/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 10/16/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 10/17/2014 Approved SAKO AGHAZARIAN
Deputy Shotcrete 10/21/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 10/21/2014 Approved SAKO AGHAZARIAN
Deputy Shotcrete 10/22/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 10/22/2014 Approved SAKO AGHAZARIAN
Deputy Shotcrete 10/23/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 10/23/2014 Approved SAKO AGHAZARIAN
Deputy Shotcrete 10/24/2014 Conditional Approval BARRY SILLS
Deputy Steel/Welding 10/24/2014 Conditional Approval BARRY SILLS
Deputy Shotcrete 10/27/2014 Approved SAKO AGHAZARIAN
Reinforced Concrete Frame 10/27/2014 Partial Inspection SAKO AGHAZARIAN
Verify Sprinkler Sign Off 10/27/2014 Approved SAKO AGHAZARIAN
Deputy Shotcrete 10/28/2014 Approved SAKO AGHAZARIAN
Deputy Shotcrete 10/29/2014 Approved SAKO AGHAZARIAN
Deputy Shotcrete 10/30/2014 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 10/30/2014 Partial Approval SAKO AGHAZARIAN
Deputy Shotcrete 10/31/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 11/5/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 11/6/2014 Conditional Approval BARRY SILLS
Deputy Steel/Welding 11/7/2014 Conditional Approval BARRY SILLS
Deputy Shotcrete 11/12/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 11/12/2014 Approved SAKO AGHAZARIAN
Deputy Shotcrete 11/13/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 11/13/2014 Approved SAKO AGHAZARIAN
Deputy Shotcrete 11/14/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 11/14/2014 Approved SAKO AGHAZARIAN
Deputy Shotcrete 11/19/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 11/19/2014 Approved SAKO AGHAZARIAN
Deputy Shotcrete 11/20/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 11/20/2014 Approved SAKO AGHAZARIAN
Reinforced Concrete Frame 11/20/2014 Partial Approval SAKO AGHAZARIAN
Deputy Shotcrete 11/21/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 11/21/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 11/25/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 11/26/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 12/2/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 12/8/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 12/9/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 12/10/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 12/11/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 12/12/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 12/16/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 12/17/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 12/18/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 12/19/2014 Conditional Approval BARRY SILLS
Floor/Roof Diaphrgm/Shear Wall 12/19/2014 Partial Approval BARRY SILLS
Deputy Steel/Welding 12/23/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 12/24/2014 Approved SAKO AGHAZARIAN
Excavation/Setback/Form/Re-Bar 12/24/2014 Partial Approval SAKO AGHAZARIAN
Deputy Steel/Welding 12/26/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 12/31/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 1/2/2015 Conditional Approval BARRY SILLS
Deputy Shotcrete 1/6/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 1/6/2015 Approved SAKO AGHAZARIAN
Reinforced Concrete Frame 1/6/2015 Partial Approval SAKO AGHAZARIAN
Deputy Shotcrete 1/7/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 1/7/2015 Approved SAKO AGHAZARIAN
Deputy Shotcrete 1/8/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 1/8/2015 Approved SAKO AGHAZARIAN
Deputy Shotcrete 1/9/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 1/9/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 1/12/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 1/13/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 1/14/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 1/15/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 1/16/2015 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 1/26/2015 Approved SAKO AGHAZARIAN
Green Building Rough 1/26/2015 Not Ready for Inspection DEROLD HAUFF
Reinforced Concrete Frame 1/26/2015 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 1/27/2015 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 2/10/2015 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 2/10/2015 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 2/11/2015 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 2/12/2015 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 2/13/2015 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 2/18/2015 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 2/19/2015 Approved SAKO AGHAZARIAN
Green Building Rough 2/26/2015 Not Ready for Inspection ROLLIN GETTLE III
Reinforced Concrete Frame 2/26/2015 Partial Approval SAKO AGHAZARIAN
Deputy Steel/Welding 3/2/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 3/3/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 3/4/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 3/5/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 3/6/2015 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 3/6/2015 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 3/9/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 3/10/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 3/11/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 3/12/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 3/13/2015 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 3/13/2015 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 3/16/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 3/16/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 3/17/2015 Approved SAKO AGHAZARIAN
Deputy Fireproofing 3/18/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 3/18/2015 Approved SAKO AGHAZARIAN
Deputy Fireproofing 3/19/2015 Approved SAKO AGHAZARIAN
Deputy Shotcrete 3/19/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 3/19/2015 Approved SAKO AGHAZARIAN
Deputy Fireproofing 3/20/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 3/20/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 3/24/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 3/25/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 3/26/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 3/27/2015 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 3/31/2015 Partial Approval SAKO AGHAZARIAN
Deputy Steel/Welding 4/6/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 4/7/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 4/8/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 4/9/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 4/10/2015 Conditional Approval BARRY SILLS
Floor/Roof Diaphrgm/Shear Wall 4/10/2015 Partial Approval BARRY SILLS
Structural Steel Frame 4/10/2015 Partial Approval BARRY SILLS
Deputy Reinf. Concrete 4/13/2015 Conditional Approval BARRY SILLS
Deputy Steel/Welding 4/13/2015 Conditional Approval BARRY SILLS
Deputy Fireproofing 4/14/2015 Conditional Approval BARRY SILLS
Deputy Steel/Welding 4/14/2015 Conditional Approval BARRY SILLS
Deputy Fireproofing 4/15/2015 Conditional Approval BARRY SILLS
Deputy Steel/Welding 4/15/2015 Conditional Approval BARRY SILLS
Deputy Fireproofing 4/16/2015 Conditional Approval BARRY SILLS
Deputy Steel/Welding 4/16/2015 Conditional Approval BARRY SILLS
Floor/Roof Diaphrgm/Shear Wall 4/16/2015 Partial Approval BARRY SILLS
Deputy Fireproofing 4/17/2015 Conditional Approval BARRY SILLS
Deputy Reinf. Concrete 4/17/2015 Conditional Approval BARRY SILLS
Deputy Steel/Welding 4/17/2015 Conditional Approval BARRY SILLS
Floor/Roof Diaphrgm/Shear Wall 4/22/2015 Partial Approval SAKO AGHAZARIAN
Deputy Steel/Welding 4/27/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 4/28/2015 Approved SAKO AGHAZARIAN
Light Gage Steel Frame 4/28/2015 Partial Inspection SAKO AGHAZARIAN
Deputy Steel/Welding 4/29/2015 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 4/29/2015 Partial Approval SAKO AGHAZARIAN
Deputy Steel/Welding 4/30/2015 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 5/1/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/1/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/5/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/12/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/13/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/14/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/15/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/18/2015 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 5/18/2015 Partial Approval SAKO AGHAZARIAN
Deputy Steel/Welding 5/19/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/20/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/21/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/22/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/27/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/28/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/29/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 6/1/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 6/2/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 6/3/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 6/4/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 6/5/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 6/9/2015 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 6/9/2015 Partial Approval SAKO AGHAZARIAN
Deputy Steel/Welding 6/10/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 6/11/2015 Approved SAKO AGHAZARIAN
Light Gage Steel Frame 6/11/2015 Partial Inspection SAKO AGHAZARIAN
Deputy Steel/Welding 6/12/2015 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 6/19/2015 Partial Inspection WILLIAM GARCIA
Deputy Steel/Welding 6/22/2015 Partial Approval SAKO AGHAZARIAN
Deputy Steel/Welding 6/23/2015 Conditional Approval BARRY SILLS
Deputy Steel/Welding 6/24/2015 Conditional Approval BARRY SILLS
Deputy Steel/Welding 6/25/2015 Conditional Approval BARRY SILLS
Deputy Reinf. Concrete 6/26/2015 Conditional Approval BARRY SILLS
Deputy Steel/Welding 6/26/2015 Conditional Approval BARRY SILLS
Deputy Steel/Welding 6/29/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 6/30/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/1/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/2/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/7/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/8/2015 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 7/8/2015 Partial Approval SAKO AGHAZARIAN
Deputy Steel/Welding 7/9/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/10/2015 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/14/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/14/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/15/2015 Conditional Approval SAKO AGHAZARIAN
Deputy Steel/Welding 7/16/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/17/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/20/2015 Approved SAKO AGHAZARIAN
Footing/Foundation/Slab 7/21/2015 Partial Approval SAKO AGHAZARIAN
Deputy Steel/Welding 7/27/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/28/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/29/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/30/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/31/2015 Approved SAKO AGHAZARIAN
Green Building Rough 7/31/2015 Partial Inspection ROLLIN GETTLE III
Reinforced Concrete Frame 7/31/2015 Partial Approval SAKO AGHAZARIAN
Deputy Steel/Welding 8/3/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 8/4/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 8/5/2015 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 8/5/2015 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/6/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 8/6/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 8/7/2015 Approved SAKO AGHAZARIAN
Green Building Rough 8/31/2015 Not Ready for Inspection ROLLIN GETTLE III
Structural Steel Frame 8/31/2015 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 9/1/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 9/14/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 9/15/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 9/17/2015 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 9/18/2015 Conditional Approval BARRY SILLS
Light Gage Steel Frame 11/12/2015 Partial Inspection SAKO AGHAZARIAN
Light Gage Steel Frame 12/10/2015 Partial Approval BARRY SILLS
Drywall Nailing 1/5/2016 Partial Approval SAKO AGHAZARIAN
Green Building Rough 1/5/2016 No Access for Inspection ROLLIN GETTLE III
Drywall Nailing 1/22/2016 Partial Approval BARRY SILLS
Green Building Rough 1/22/2016 Not Ready for Inspection ROLLIN GETTLE III
Light Gage Steel Frame 1/22/2016 Partial Approval BARRY SILLS
Green Building Rough 1/26/2016 Partial Inspection ROLLIN GETTLE III
Light Gage Steel Frame 1/26/2016 Partial Approval SAKO AGHAZARIAN
Insulation 2/17/2016 Partial Approval SAKO AGHAZARIAN
Light Gage Steel Frame 2/17/2016 Partial Approval SAKO AGHAZARIAN
Drywall Nailing 3/9/2016 Partial Approval SAKO AGHAZARIAN
Green Building Rough 3/9/2016 Corrections Issued MICKEY YAMASHITA
Insulation 3/9/2016 Partial Approval SAKO AGHAZARIAN
Light Gage Steel Frame 3/9/2016 Partial Approval SAKO AGHAZARIAN
Insulation 4/7/2016 Partial Approval SAKO AGHAZARIAN
Light Gage Steel Frame 4/7/2016 Partial Approval SAKO AGHAZARIAN
Deputy Steel/Welding 4/14/2016 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 4/15/2016 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 4/18/2016 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 4/19/2016 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 4/20/2016 Approved SAKO AGHAZARIAN
Light Gage Steel Frame 5/16/2016 Partial Approval SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 5/24/2016 Partial Approval SAKO AGHAZARIAN
Green Building Rough 6/16/2016 Not Ready for Inspection MICKEY YAMASHITA
Light Gage Steel Frame 6/16/2016 Partial Inspection SAKO AGHAZARIAN
Green Building Rough 6/22/2016 Not Ready for Inspection JOHN KLARIN
Reinforced Concrete Frame 6/22/2016 Partial Approval BARRY SILLS
Interior/Exterior Lathing 7/20/2016 Partial Approval BARRY SILLS
Insulation 7/25/2016 Partial Approval BARRY SILLS
Light Gage Steel Frame 7/25/2016 Partial Inspection BARRY SILLS
Light Gage Steel Frame 7/27/2016 Not Ready for Inspection BARRY SILLS
Light Gage Steel Frame 7/28/2016 Not Ready for Inspection BARRY SILLS
Drywall Nailing 8/12/2016 Partial Approval SAKO AGHAZARIAN
Drywall Nailing 10/11/2016 Partial Inspection SAKO AGHAZARIAN
Green Building Rough 10/11/2016 Not Ready for Inspection DONALD CRICHLOW
Light Gage Steel Frame 10/11/2016 Partial Inspection SAKO AGHAZARIAN
Drywall Nailing 10/28/2016 Partial Inspection SAKO AGHAZARIAN
Green Building Rough 10/28/2016 Partial Inspection MICKEY YAMASHITA
Light Gage Steel Frame 10/28/2016 Approved SAKO AGHAZARIAN
Pre-Inspection 11/1/2016 Approved SAKO AGHAZARIAN
Green Building Rough 1/18/2017 Not Ready for Inspection MICKEY YAMASHITA
Light Gage Steel Frame 1/19/2017 Partial Inspection SAKO AGHAZARIAN
Drywall Nailing 2/15/2017 Partial Approval SAKO AGHAZARIAN
Green Building Rough 2/15/2017 Not Ready for Inspection MICKEY YAMASHITA
Light Gage Steel Frame 2/15/2017 Partial Approval SAKO AGHAZARIAN
Deputy Steel/Welding 3/24/2017 Approved SAKO AGHAZARIAN
Green Building Rough 4/4/2017 Approved JOHN KLARIN
T-Bar Ceiling 5/4/2017 Partial Inspection SAKO AGHAZARIAN
T-Bar Ceiling 5/11/2017 Partial Inspection SAKO AGHAZARIAN
Green Building Final 6/7/2017 Not Ready for Inspection WILLIAM ROSE
Posting Pre-Inspection 6/7/2017 Approved SAKO AGHAZARIAN
Special/Order Compliance 6/7/2017 Approved SAKO AGHAZARIAN
Smoke Detectors 6/20/2017 Approved SAKO AGHAZARIAN
Drywall Nailing 6/23/2017 Approved SAKO AGHAZARIAN
Final 6/23/2017 Partial Inspection SAKO AGHAZARIAN
Footing/Foundation/Slab 6/23/2017 Approved SAKO AGHAZARIAN
Green Building Final 6/23/2017 Partial Approval WILLIAM ROSE
Reinforced Concrete Frame 6/23/2017 Approved SAKO AGHAZARIAN
Reinforced Masonry Frame 6/23/2017 Approved SAKO AGHAZARIAN
SGSOV-Seismic Gas S/O Valve 6/23/2017 SGSOV Approved SAKO AGHAZARIAN
Special/Order Compliance 6/23/2017 Partial Approval DONALD CRICHLOW
Structural Steel Frame 6/23/2017 Approved SAKO AGHAZARIAN
Final 6/28/2017 Partial Inspection SAKO AGHAZARIAN
Green Building Final 6/28/2017 Partial Approval WILLIAM ROSE
Special/Order Compliance 12/5/2017 Approved SAKO AGHAZARIAN
Special/Order Compliance 12/11/2017 Approved JEFF BYTHEWAY
Special/Order Compliance 6/4/2018 Approved TED RIES
Special/Order Compliance 12/14/2018 Approved JEFF BYTHEWAY
Special/Order Compliance 12/21/2018 Approved TED RIES
Special/Order Compliance 12/21/2018 Order to Comply Issued JEFF BYTHEWAY
Special/Order Compliance 2/18/2020 Approved DAVID BURKHEAD
Special/Order Compliance 12/4/2020 Partial Inspection DAVID BURKHEAD
Final 12/9/2020 Partial Inspection DAVID BURKHEAD
Green Building Final 12/9/2020 Approved DAVID BURKHEAD
Final 12/23/2020 Partial Inspection DAVID BURKHEAD
Final 4/1/2021 Not Ready for Inspection DAVID BURKHEAD
Special/Order Compliance 9/22/2021 Approved DAVID BURKHEAD
Special/Order Compliance 4/6/2022 Approved DAVID BURKHEAD
Special/Order Compliance 4/25/2023 Approved DAVID BURKHEAD
Final 6/14/2023 OK to Issue CofO DAVID BURKHEAD