5110 S CRENSHAW BLVD 1-32 90043

Certificate Information: 5110 S CRENSHAW BLVD 1-32 90043

Application / Permit
13010-10000-03633
Plan Check / Job No.
B13LA14732
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONSTRUCT NEW 4-STORY MULTI-FAMILY APARTMENT BUILDING, 135'x140'. 1ST STORY TYPE 1-A GARAGE AND 2ND TO 4TH STORIES, TYPE V-A, TOTAL 32-UNIT RESIDENTIAL DWELLING UNITS
Permit Issued
Issued on 4/4/2014
Issuing Office
Metro
Current Status
CofO Issued on 1/27/2016
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/25/2013 APPLICANT
Assigned to Plan Check Engineer 11/27/2013 BOK GOH
Corrections Issued 12/11/2013 BOK GOH
Quality Review Completed 12/12/2013 LAWRENCE QUIRANTE
Building Plans Picked Up 12/17/2013 APPLICANT
Disabled Access Plans Picked Up 12/17/2013 APPLICANT
Applicant returned to address corrections 2/19/2014 BOK GOH
Applicant returned to address corrections 2/25/2014 BOK GOH
Applicant returned to address corrections 3/5/2014 BOK GOH
Applicant returned to address corrections 3/14/2014 BOK GOH
Applicant returned to address corrections 3/19/2014 BOK GOH
Plan Check Approved 3/26/2014 TIEN JEN WANG
Issued 4/4/2014 LADBS
TCO Corrected (Expire Date: 06-28-2016) 12/31/2015 WINSTON DUNNING
CofO in Progress 1/27/2016 RICKEY JACKSON
CofO Issued 1/27/2016 RICKEY JACKSON
Permit Finaled 1/27/2016 RICKEY JACKSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/22/2014 JAMES KHO
Work Adjacent to Public Way Cleared 1/22/2014 JAMES KHO
Housing rent stabilization Cleared 1/28/2014 CARLOS PELAEZ
Driveway location Cleared 2/11/2014 COLLINS ALLAN
Specific Plan Cleared 2/11/2014 COLLINS ALLAN
DAS Clearance Cleared 2/24/2014 EDDIE GARIN
Green Code Cleared 2/24/2014 MARCUS LEVIAS
Building over 3-story or 36-ft Cleared 2/28/2014 CALOSHA APPROVED
Metro Rail approval Cleared 2/28/2014 MTA APPROVED
"Q" conditions Cleared 3/6/2014 MAY SIRINOPWONGSAGO
Frnt yard landscape/Water mgmt Cleared 3/6/2014 MAY SIRINOPWONGSAGO
Miscellaneous Cleared 3/6/2014 MAY SIRINOPWONGSAGO
Opn space landscape/Water mgmt Cleared 3/6/2014 MAY SIRINOPWONGSAGO
Prkng lot landscape/Water mgmt Cleared 3/6/2014 MAY SIRINOPWONGSAGO
Specific Plan Cleared 3/6/2014 MAY SIRINOPWONGSAGO
Low Impact Development Cleared 3/11/2014 AMMAR ELTAWIL
Hydrant and Access approval Cleared 3/12/2014 ROBERT DUFF
Project located in CRA area Cleared 3/12/2014 JIM URQUHART
Address approval Cleared 3/18/2014 LINDA MARGARET
Highway dedication Cleared 3/18/2014 LINDA MARGARET
Miscellaneous Cleared 3/18/2014 LINDA MARGARET
Permit Cleared 3/18/2014 LINDA MARGARET
Roof/Waste drainage to street Cleared 3/18/2014 LINDA MARGARET
Sewer availability Cleared 3/18/2014 ARMENIA HERNANDEZ
Title 19 building approval Cleared 3/18/2014 ANDREW KO
Miscellaneous Cleared 3/19/2014 MAY SIRINOPWONGSAGO
Housing density bonus Cleared 3/25/2014 MARITES CUNANAN

Contact Information

Architect Maffris, Kevin M; Lic. No.: C33104 3816 MAIN STREET      CULVER CITY, CA 90232
Contractor B L H Construction Company; Lic. No.: 801617-B 5951 VARIEL AVE      WOODLAND HILLS, CA 91367
Engineer Salem, Rifaat Sammy; Lic. No.: GE2549 4195 W SAMPLE AVE      FRESNO, CA 93722
Engineer Waggoner, Michael Alan; Lic. No.: S3738 10641 BENT TREE RD      SANTA ANA, CA 92705
Engineer Walsh, Matthew Ryan; Lic. No.: C79026 5951 VARIEL AVENUE      WOODLAND HILLS, CA 91367

Inspector Information

JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/5/2014 Not Ready for Inspection BYRON FUENTES
Footing/Foundation/Slab 9/24/2014 Corrections Issued BYRON FUENTES
Footing/Foundation/Slab 9/25/2014 No Access for Inspection BYRON FUENTES
Excavation/Setback/Form/Re-Bar 9/26/2014 Not Ready for Inspection BYRON FUENTES
Excavation/Setback/Form/Re-Bar 10/1/2014 Partial Approval BYRON FUENTES
Footing/Foundation/Slab 10/1/2014 Partial Approval BYRON FUENTES
Deputy Reinf. Concrete 10/6/2014 Approved BYRON FUENTES
Excavation/Setback/Form/Re-Bar 10/23/2014 Partial Approval BYRON FUENTES
Excavation/Setback/Form/Re-Bar 10/27/2014 Approved BYRON FUENTES
Excavation/Setback/Form/Re-Bar 11/3/2014 Not Ready for Inspection BYRON FUENTES
Excavation/Setback/Form/Re-Bar 11/7/2014 Partial Approval JAMES POWERS
Masonry Wall/Backfill 11/7/2014 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 12/10/2014 Partial Approval BYRON FUENTES
Footing/Foundation/Slab 12/30/2014 Partial Approval JOHN JONES
Deputy Pre-Stress Concrete 1/6/2015 Approved JOHN JONES
Masonry Wall/Backfill 1/14/2015 Not Ready for Inspection JOHN JONES
Masonry Wall/Backfill 1/15/2015 Partial Approval BYRON FUENTES
Deputy Reinf. Masonry 1/16/2015 Approved JOHN JONES
Masonry Wall/Backfill 1/27/2015 Partial Approval JOHN JONES
Deputy Reinf. Masonry 1/28/2015 Approved JOHN JONES
Deputy Reinf. Masonry 2/4/2015 Partial Approval JAMES POWERS
Masonry Wall/Backfill 2/5/2015 Not Ready for Inspection BYRON FUENTES
Deputy Reinf. Masonry 2/6/2015 Approved BYRON FUENTES
Masonry Wall/Backfill 2/6/2015 Partial Approval BYRON FUENTES
Deputy Reinf. Masonry 2/10/2015 Approved BYRON FUENTES
Deputy Reinf. Masonry 2/11/2015 Approved BYRON FUENTES
Deputy Reinf. Masonry 2/12/2015 Approved BYRON FUENTES
Deputy Reinf. Masonry 2/12/2015 Approved JOHN JONES
Deputy Reinf. Masonry 2/13/2015 Approved BYRON FUENTES
Masonry Wall/Backfill 2/18/2015 Partial Approval BYRON FUENTES
Masonry Wall/Backfill 2/26/2015 Partial Approval BYRON FUENTES
Deputy Reinf. Masonry 3/4/2015 Approved BYRON FUENTES
Deputy Reinf. Masonry 3/5/2015 Approved BYRON FUENTES
Deputy Reinf. Masonry 3/6/2015 Approved BYRON FUENTES
Deputy Reinf. Masonry 3/6/2015 Partial Approval JAMES POWERS
Masonry Wall/Backfill 3/6/2015 Approved BYRON FUENTES
Deputy Reinf. Masonry 3/9/2015 Conditional Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 4/20/2015 Not Ready for Inspection BYRON FUENTES
Deputy Reinf. Concrete 4/27/2015 Conditional Approval BYRON FUENTES
Deputy Reinf. Concrete 4/28/2015 Conditional Approval BYRON FUENTES
Deputy Reinf. Concrete 4/29/2015 Approved BYRON FUENTES
Excavation/Setback/Form/Re-Bar 4/29/2015 Conditional Approval BYRON FUENTES
Deputy Reinf. Concrete 4/30/2015 Conditional Approval BYRON FUENTES
Deputy Reinf. Concrete 5/1/2015 Approved BYRON FUENTES
Drywall Nailing 5/27/2015 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/27/2015 Partial Approval JAMES POWERS
Green Building Rough 5/27/2015 Not Ready for Inspection JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 6/12/2015 Partial Approval BYRON FUENTES
Green Building Rough 6/12/2015 Not Ready for Inspection JOHN KLARIN
Verify Sprinkler Sign Off 6/12/2015 Not Ready for Inspection BYRON FUENTES
Wood Frame 6/12/2015 Partial Approval BYRON FUENTES
Floor/Roof Diaphrgm/Shear Wall 6/16/2015 Partial Approval BYRON FUENTES
Green Building Rough 6/18/2015 Not Ready for Inspection JOHN KLARIN
Verify Sprinkler Sign Off 6/18/2015 Approved BYRON FUENTES
Wood Frame 6/18/2015 Conditional Approval BYRON FUENTES
Insulation 6/22/2015 Partial Approval BYRON FUENTES
Deputy Wood Construction 6/23/2015 Approved BYRON FUENTES
Floor/Roof Diaphrgm/Shear Wall 6/26/2015 Partial Approval BYRON FUENTES
Drywall Nailing 6/30/2015 Partial Inspection JEFFREY FULTON
Green Building Rough 6/30/2015 Not Ready for Inspection JOHN KLARIN
Insulation 6/30/2015 Partial Inspection JEFFREY FULTON
Green Building Rough 7/9/2015 Not Ready for Inspection JOHN KLARIN
Wood Frame 7/9/2015 Partial Approval BYRON FUENTES
Insulation 7/17/2015 Partial Approval BYRON FUENTES
Drywall Nailing 7/22/2015 Partial Approval BYRON FUENTES
Green Building Rough 7/22/2015 Not Ready for Inspection JOHN KLARIN
Excavation/Setback/Form/Re-Bar 8/6/2015 Partial Inspection ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 8/6/2015 Partial Inspection ERNESTO CORRAL
Insulation 8/6/2015 Partial Inspection ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 8/18/2015 Partial Inspection ARTHUR BELIS
Insulation 8/18/2015 Partial Inspection ARTHUR BELIS
Green Building Rough 8/26/2015 Not Ready for Inspection JOHN KLARIN
Wood Frame 8/26/2015 Partial Approval BYRON FUENTES
Green Building Rough 9/11/2015 Not Ready for Inspection JOHN KLARIN
Wood Frame 9/11/2015 Partial Approval BYRON FUENTES
Green Building Rough 9/14/2015 Not Ready for Inspection JOHN KLARIN
Green Building Rough 9/18/2015 Not Ready for Inspection JOHN KLARIN
Light Gage Steel Frame 9/18/2015 Partial Approval BYRON FUENTES
Wood Frame 9/18/2015 Partial Approval BYRON FUENTES
Insulation 9/22/2015 Partial Approval BYRON FUENTES
Drywall Nailing 9/24/2015 Partial Approval BYRON FUENTES
Green Building Rough 9/24/2015 Not Ready for Inspection JOHN KLARIN
Light Gage Steel Frame 9/24/2015 Partial Approval BYRON FUENTES
Insulation 9/28/2015 Partial Approval BYRON FUENTES
Wood Frame 9/28/2015 Conditional Approval BYRON FUENTES
Drywall Nailing 9/30/2015 Partial Approval BYRON FUENTES
Green Building Rough 9/30/2015 Not Ready for Inspection JOHN KLARIN
Drywall Nailing 10/5/2015 Partial Approval BYRON FUENTES
Light Gage Steel Frame 10/5/2015 Partial Approval BYRON FUENTES
Insulation 10/16/2015 Partial Approval BYRON FUENTES
Drywall Nailing 10/23/2015 Partial Approval BYRON FUENTES
Green Building Rough 10/23/2015 Not Ready for Inspection JOHN KLARIN
Drywall Nailing 10/28/2015 Partial Approval BYRON FUENTES
Green Building Rough 10/28/2015 Not Ready for Inspection JOHN KLARIN
Interior/Exterior Lathing 10/30/2015 Approved BYRON FUENTES
Drywall Nailing 11/3/2015 Partial Approval BYRON FUENTES
Light Gage Steel Frame 11/3/2015 Partial Approval BYRON FUENTES
Green Building Rough 12/2/2015 Partial Approval JOHN KLARIN
Structural Steel Frame 12/2/2015 Partial Approval BYRON FUENTES
T-Bar Ceiling 12/11/2015 Partial Approval BYRON FUENTES
Drywall Nailing 12/15/2015 Partial Approval BYRON FUENTES
Green Building Rough 12/15/2015 Not Ready for Inspection JOHN KLARIN
T-Bar Ceiling 12/18/2015 Partial Approval JAMES POWERS
Green Building Final 12/24/2015 Not Ready for Inspection DAVID MATSON
T-Bar Ceiling 12/24/2015 Partial Approval BYRON FUENTES
Special/Order Compliance 12/28/2015 Partial Inspection BYRON FUENTES
Drywall Nailing 12/30/2015 Conditional Approval BYRON FUENTES
Final 12/30/2015 Not Ready for Inspection BYRON FUENTES
Footing/Foundation/Slab 12/30/2015 Approved BYRON FUENTES
Green Building Final 12/30/2015 Approved JOHN KLARIN
Green Building Rough 12/30/2015 Approved JOHN KLARIN
Reinforced Concrete Frame 12/30/2015 Conditional Approval BYRON FUENTES
Reinforced Masonry Frame 12/30/2015 Conditional Approval BYRON FUENTES
SGSOV-Seismic Gas S/O Valve 12/30/2015 SGSOV Approved BYRON FUENTES
Smoke Detectors 12/30/2015 Approved BYRON FUENTES
Structural Steel Frame 12/30/2015 Conditional Approval BYRON FUENTES
Wood Frame 12/30/2015 Conditional Approval BYRON FUENTES
Drywall Nailing 1/13/2016 Approved BYRON FUENTES
Final 1/13/2016 Conditional Approval BYRON FUENTES
Reinforced Concrete Frame 1/13/2016 Approved BYRON FUENTES
Reinforced Masonry Frame 1/13/2016 Approved BYRON FUENTES
Structural Steel Frame 1/13/2016 Approved BYRON FUENTES
Wood Frame 1/13/2016 Approved BYRON FUENTES