1133 S HOPE ST 90015

Certificate Information: 1133 S HOPE ST 90015

Application / Permit
13010-10000-02854
Plan Check / Job No.
B13LA11401
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 28 story residential tower, 24 levels of residential, 1 level of amenity space, and 5 level of parking above grade and 3 level below grade with ground level commerical space (core and shell).
Permit Issued
Issued on 10/6/2016
Issuing Office
Metro
Current Status
CofO Issued on 4/11/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/7/2013 APPLICANT
Assigned to Plan Check Engineer 10/10/2013 SUEN LIEU
Plans on Hold 11/27/2013 SUEN LIEU
Hold Released 3/5/2014 SUEN LIEU
Corrections Issued 3/7/2014 SUEN LIEU
Building Plans Picked Up 3/13/2014 APPLICANT
Quality Review Completed 3/19/2014 CHARLES CHANG
Applicant returned to address corrections 6/11/2014 SUEN LIEU
Applicant returned to address corrections 10/24/2014 SUEN LIEU
Applicant returned to address corrections 12/4/2014 SUEN LIEU
Applicant returned to address corrections 1/20/2015 SUEN LIEU
Applicant returned to address corrections 2/6/2015 SUEN LIEU
Applicant returned to address corrections 2/13/2015 SUEN LIEU
Applicant returned to address corrections 2/20/2015 SUEN LIEU
Applicant returned to address corrections 2/27/2015 SUEN LIEU
Applicant returned to address corrections 3/12/2015 SUEN LIEU
Applicant returned to address corrections 3/13/2015 SUEN LIEU
Applicant returned to address corrections 3/19/2015 SUEN LIEU
Applicant returned to address corrections 9/29/2015 SUEN LIEU
Applicant returned to address corrections 10/1/2015 SUEN LIEU
Applicant returned to address corrections 8/23/2016 SUEN LIEU
Applicant returned to address corrections 8/26/2016 SUEN LIEU
Applicant returned to address corrections 9/9/2016 SUEN LIEU
Applicant returned to address corrections 9/15/2016 SUEN LIEU
Applicant returned to address corrections 9/22/2016 SUEN LIEU
Applicant returned to address corrections 9/29/2016 SUEN LIEU
Plan Check Approved 10/4/2016 SUEN LIEU
Issued 10/6/2016 LADBS
TCO Issued (Expire Date: 02-24-2021) 8/28/2020 ERNESTO CORRAL
TCO Issued (Expire Date: 08-23-2021) 2/24/2021 ERNESTO CORRAL
TCO Issued (Expire Date: 02-26-2022) 8/30/2021 ERNESTO CORRAL
TCO Issued (Expire Date: 09-13-2022) 3/17/2022 TED RIES
TCO Issued (Expire Date: 03-27-2023) 9/28/2022 ERNESTO CORRAL
TCO Issued (Expire Date: 09-27-2023) 3/31/2023 TED RIES
TCO Issued (Expire Date: 08-17-2024) 2/19/2024 ERNESTO CORRAL
CofO in Progress 3/15/2024 RAFAEL ESPINOZA
Permit Finaled 4/11/2024 ADAM BURGESS
CofO Issued 4/11/2024 ADAM BURGESS
Permit Finaled 4/11/2024 ADAM BURGESS

Permit Application Clearance Information

Project located in CRA area Cleared 2/11/2015 JIM URQUHART
Address approval Cleared 9/27/2016 JAMES KHO
Eng Process Fee Ord 176,300 Cleared 9/27/2016 JAMES KHO
Highway dedication Cleared 9/27/2016 JAMES KHO
Permit Cleared 9/27/2016 JAMES KHO
Sewer availability Cleared 9/27/2016 JAMES KHO
DAS Clearance Cleared 9/29/2016 SUEN LIEU
Driveway location Cleared 9/30/2016 TAIMOUR TANAVOLI
Green Code Cleared 9/30/2016 RUSSELL KELLY
Hydrant and Access approval Cleared 9/30/2016 ROBERT DUFF
Internal circulation Cleared 9/30/2016 TAIMOUR TANAVOLI
Methane Ordinance Cleared 9/30/2016 DAVE MYERS
Title 19 building approval Cleared 9/30/2016 DAVE MYERS
"D" conditions Cleared 10/3/2016 MARITZA PRZEKOP
"Q" conditions Cleared 10/3/2016 MARITZA PRZEKOP
Abandoned oil well approval Cleared 10/3/2016 JOHN CONNEALLY
Encroachment in public way Cleared 10/3/2016 JAMES KHO
Opn space landscape/Water mgmt Cleared 10/3/2016 MARITZA PRZEKOP
Roof/Waste drainage to street Cleared 10/3/2016 JAMES KHO
Site Plan review Cleared 10/3/2016 MARITZA PRZEKOP
Stormwater Pollution Mitigatn Cleared 10/3/2016 MARTIN FRAGOSO
Tract Map conditions Cleared 10/3/2016 MARITZA PRZEKOP
Tract Map conditions Cleared 10/3/2016 MARITZA PRZEKOP
Work Adjacent to Public Way Cleared 10/3/2016 JAMES KHO
ZA Case Cleared 10/3/2016 MARITZA PRZEKOP
ZA Case Cleared 10/3/2016 MARITZA PRZEKOP
ZA Case Cleared 10/3/2016 MARITZA PRZEKOP
ZI Cleared 10/3/2016 MARITZA PRZEKOP
Building over 3-story or 36-ft Cleared 10/4/2016 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 10/4/2016 CALOSHA APPROVED

Contact Information

Contractor Owner-Builder       ,
Engineer Arriola, Kirby Norman; Lic. No.: C31416 PO BOX 5566      OXNARD, CA 93031
Engineer Berliner, Neal David; Lic. No.: GE2576 4913 MONUMENT ST      SIMI VALLEY, CA 93063
Engineer Cummins, Charles Stephen; Lic. No.: C34526 17625 CRENSHAW BLVD SUITE 300      TORRANCE, CA 90504
Engineer Derkalousdian, Hrair Harry; Lic. No.: C79694 441 PALM DR 3      GLENDALE, CA 91202
Engineer Gerlick, Bradley J; Lic. No.: C83388 9401 MEADOW LEAF CT      BAKERSFIELD, CA 93311
Engineer O'Keeffe, Michael John; Lic. No.: S4879 1661 W 5TH AVE      VANCOUVER, BC, V6J1N5
Geologist Kasman, Gerald Alan; Lic. No.: EG2251 29072 GLADIOLUS DR      CANYON COUNTRY, CA 91387
Landscape Architect Stoyko, David Lawrence; Lic. No.: LA5341 2686 EAST 6TH AVENUE   BRITISH COLUMBIA    VANCOUVER, V5M 1R3

Inspector Information

RONALD JIMENEZ, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
LARRY ARNICK, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
JOEY BUCHANAN, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
ERNESTO CORRAL, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL ESPINOZA, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 6/29/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/3/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/5/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/6/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/7/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/10/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/11/2017 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 7/12/2017 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 7/13/2017 Conditional Approval ERNESTO CORRAL
Pre-Inspection 7/13/2017 Approved ERNESTO CORRAL
Deputy Reinf. Concrete 7/14/2017 Conditional Approval ERNESTO CORRAL
Pre-Inspection 7/14/2017 Approved ERNESTO CORRAL
Deputy Reinf. Concrete 7/17/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/18/2017 No Access for Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 7/19/2017 No Access for Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 7/20/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/21/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/9/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/10/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/15/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/16/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/17/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/18/2017 Conditional Approval ERNESTO CORRAL
METHANE-Rough 8/18/2017 Partial Inspection ERNESTO CORRAL
Reinforced Concrete Frame 8/18/2017 Partial Inspection ERNESTO CORRAL
Verify Sprinkler Sign Off 8/18/2017 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 8/21/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/22/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/23/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/24/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/25/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/29/2017 Conditional Approval ERNESTO CORRAL
Grading Pre-Inspection 8/29/2017 Approved ERNESTO CORRAL
Deputy Reinf. Concrete 8/30/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/31/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 9/1/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 9/5/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 9/6/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 9/7/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 9/8/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 9/11/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 9/12/2017 Conditional Approval ERNESTO CORRAL
METHANE-Rough 9/12/2017 Partial Inspection ERNESTO CORRAL
Reinforced Concrete Frame 9/12/2017 Partial Inspection ERNESTO CORRAL
Verify Sprinkler Sign Off 9/12/2017 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 9/13/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 9/14/2017 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/15/2017 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/18/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 9/20/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 9/21/2017 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 9/21/2017 Partial Inspection ERNESTO CORRAL
METHANE-Barrier 9/21/2017 Partial Inspection ERNESTO CORRAL
METHANE-Subgrade 9/21/2017 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 9/22/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 9/25/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 9/26/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 9/27/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 9/28/2017 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 9/29/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 10/2/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 10/3/2017 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 10/3/2017 Partial Inspection ERNESTO CORRAL
METHANE-Barrier 10/3/2017 Partial Inspection ERNESTO CORRAL
METHANE-Rough 10/3/2017 Partial Inspection ERNESTO CORRAL
METHANE-Subgrade 10/3/2017 Partial Inspection ERNESTO CORRAL
Reinforced Concrete Frame 10/3/2017 Partial Inspection ERNESTO CORRAL
Verify Sprinkler Sign Off 10/3/2017 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 10/4/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 10/5/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 10/6/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 10/10/2017 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 10/10/2017 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 10/11/2017 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 10/11/2017 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 10/12/2017 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 10/12/2017 Partial Inspection ERNESTO CORRAL
METHANE-Barrier 10/12/2017 Partial Inspection ERNESTO CORRAL
METHANE-Rough 10/12/2017 Partial Inspection ERNESTO CORRAL
METHANE-Subgrade 10/12/2017 Partial Inspection ERNESTO CORRAL
Reinforced Concrete Frame 10/12/2017 Partial Inspection ERNESTO CORRAL
Verify Sprinkler Sign Off 10/12/2017 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 10/13/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 10/16/2017 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 10/16/2017 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 10/17/2017 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 10/17/2017 Partial Inspection ERNESTO CORRAL
METHANE-Barrier 10/17/2017 Partial Inspection ERNESTO CORRAL
METHANE-Rough 10/17/2017 Partial Inspection ERNESTO CORRAL
METHANE-Subgrade 10/17/2017 Partial Inspection ERNESTO CORRAL
Reinforced Concrete Frame 10/17/2017 Partial Inspection ERNESTO CORRAL
Verify Sprinkler Sign Off 10/17/2017 Partial Inspection ERNESTO CORRAL
Pre-Inspection 10/18/2017 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 10/19/2017 Conditional Approval ERNESTO CORRAL
Pre-Inspection 10/19/2017 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 10/20/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 10/23/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 10/24/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/25/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 10/26/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 10/27/2017 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 10/27/2017 Partial Inspection ERNESTO CORRAL
Footing/Foundation/Slab 10/27/2017 Partial Inspection ERNESTO CORRAL
METHANE-Barrier 10/27/2017 Not Ready for Inspection ERNESTO CORRAL
METHANE-Subgrade 10/27/2017 Not Ready for Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 10/30/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 10/31/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 11/1/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/2/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/3/2017 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 11/3/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/6/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/7/2017 Partial Approval JAMES POWERS
Deputy Shotcrete 11/7/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/8/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/9/2017 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/13/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 11/14/2017 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 11/14/2017 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 11/15/2017 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 11/15/2017 Not Ready for Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 11/16/2017 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 11/16/2017 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 11/17/2017 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 11/17/2017 Partial Inspection ERNESTO CORRAL
METHANE-Barrier 11/17/2017 Partial Inspection ERNESTO CORRAL
METHANE-Subgrade 11/17/2017 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 11/20/2017 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 11/20/2017 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 11/21/2017 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 11/21/2017 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 11/22/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 11/27/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 11/28/2017 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 11/28/2017 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 11/29/2017 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 11/29/2017 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 11/30/2017 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 12/1/2017 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 12/1/2017 Not Ready for Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 12/4/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 12/5/2017 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 12/5/2017 Not Ready for Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 12/6/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 12/7/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 12/8/2017 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 12/8/2017 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 12/11/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 12/12/2017 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 12/12/2017 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 12/13/2017 Conditional Approval ERNESTO CORRAL
Deputy Methane Barrier 12/14/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 12/14/2017 Conditional Approval ERNESTO CORRAL
METHANE-Barrier 12/14/2017 Partial Inspection ERNESTO CORRAL
METHANE-Subgrade 12/14/2017 Partial Approval ERNESTO CORRAL
Deputy Methane Barrier 12/15/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 12/15/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 12/18/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 12/20/2017 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 12/21/2017 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 12/21/2017 Corrections Issued ERNESTO CORRAL
Deputy Reinf. Concrete 12/22/2017 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 12/22/2017 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 12/26/2017 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 12/27/2017 Partial Inspection ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 12/28/2017 Partial Inspection ERNESTO CORRAL
Grading Pre-Inspection 12/28/2017 Not Ready for Inspection ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 1/3/2018 Partial Approval LESLIE TRUJILLO
Excavation/Setback/Form/Re-Bar 1/8/2018 Not Ready for Inspection LESLIE TRUJILLO
Excavation/Setback/Form/Re-Bar 1/9/2018 Not Ready for Inspection JAMES POWERS
Pre-Inspection 1/10/2018 Partial Inspection ERNESTO CORRAL
Deputy Drilled-In Anchors 1/12/2018 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 1/12/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 1/24/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 1/25/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 1/26/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 1/29/2018 Conditional Approval ERNESTO CORRAL
Deputy Methane Barrier 1/30/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 1/30/2018 Conditional Approval ERNESTO CORRAL
Deputy Methane Barrier 1/31/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 1/31/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 2/1/2018 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 2/1/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 2/2/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 2/5/2018 Conditional Approval ERNESTO CORRAL
Deputy Methane Barrier 2/6/2018 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 2/6/2018 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 2/7/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 2/7/2018 Conditional Approval ERNESTO CORRAL
Deputy Methane Barrier 2/8/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 2/8/2018 Conditional Approval ERNESTO CORRAL
Deputy Methane Barrier 2/9/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 2/9/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 2/12/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 2/13/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 2/14/2018 Conditional Approval ERNESTO CORRAL
Green Building Rough 2/14/2018 Not Ready for Inspection ERNESTO CORRAL
METHANE-Rough 2/14/2018 Partial Approval ERNESTO CORRAL
Reinforced Concrete Frame 2/14/2018 Partial Inspection ERNESTO CORRAL
Verify Sprinkler Sign Off 2/14/2018 Not Ready for Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 2/15/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 2/16/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 2/20/2018 Conditional Approval ERNESTO CORRAL
Green Building Rough 2/20/2018 Partial Inspection ERNESTO CORRAL
METHANE-Rough 2/20/2018 Partial Inspection ERNESTO CORRAL
Reinforced Concrete Frame 2/20/2018 Partial Inspection ERNESTO CORRAL
Verify Sprinkler Sign Off 2/20/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 2/21/2018 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 2/21/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 2/22/2018 Conditional Approval ERNESTO CORRAL
Green Building Rough 2/22/2018 Not Ready for Inspection ERNESTO CORRAL
METHANE-Rough 2/22/2018 Approved ERNESTO CORRAL
Reinforced Concrete Frame 2/22/2018 Partial Inspection ERNESTO CORRAL
Verify Sprinkler Sign Off 2/22/2018 Not Ready for Inspection ERNESTO CORRAL
Deputy Methane Barrier 2/23/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 2/23/2018 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 2/23/2018 Partial Inspection ERNESTO CORRAL
Reinforced Masonry Frame 2/23/2018 Partial Inspection ERNESTO CORRAL
Deputy Methane Barrier 2/26/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 2/26/2018 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 2/26/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 2/27/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 2/28/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 3/1/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 3/2/2018 Conditional Approval ERNESTO CORRAL
Green Building Rough 3/5/2018 Not Ready for Inspection ERNESTO CORRAL
Reinforced Concrete Frame 3/5/2018 Partial Inspection ERNESTO CORRAL
Verify Sprinkler Sign Off 3/5/2018 Not Ready for Inspection ERNESTO CORRAL
Deputy Drilled-In Anchors 3/6/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 3/6/2018 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 3/6/2018 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 3/7/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 3/7/2018 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 3/7/2018 Conditional Approval ERNESTO CORRAL
Green Building Rough 3/7/2018 Partial Inspection ERNESTO CORRAL
Reinforced Concrete Frame 3/7/2018 Partial Inspection ERNESTO CORRAL
Verify Sprinkler Sign Off 3/7/2018 Not Ready for Inspection ERNESTO CORRAL
Deputy Drilled-In Anchors 3/8/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 3/8/2018 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 3/8/2018 Conditional Approval ERNESTO CORRAL
Green Building Rough 3/8/2018 Not Ready for Inspection ERNESTO CORRAL
Reinforced Concrete Frame 3/8/2018 Partial Inspection ERNESTO CORRAL
Verify Sprinkler Sign Off 3/8/2018 Not Ready for Inspection ERNESTO CORRAL
Deputy Drilled-In Anchors 3/9/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 3/9/2018 Conditional Approval NICK DANERI
Deputy Shotcrete 3/9/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 3/12/2018 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 3/12/2018 Conditional Approval ERNESTO CORRAL
Reinforced Masonry Frame 3/12/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 3/13/2018 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 3/13/2018 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 3/13/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 3/14/2018 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 3/14/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 3/15/2018 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 3/15/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 3/15/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 3/16/2018 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 3/16/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 3/19/2018 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 3/20/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 3/21/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 3/22/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 3/23/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 3/27/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 3/28/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 3/29/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 3/30/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 4/2/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 4/3/2018 Conditional Approval ERNESTO CORRAL
Green Building Rough 4/3/2018 Not Ready for Inspection ERNESTO CORRAL
Reinforced Concrete Frame 4/3/2018 Partial Inspection ERNESTO CORRAL
Verify Sprinkler Sign Off 4/3/2018 Not Ready for Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 4/4/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 4/5/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 4/6/2018 Conditional Approval ERNESTO CORRAL
Green Building Rough 4/6/2018 Partial Inspection ERNESTO CORRAL
Pre-Inspection 4/6/2018 Approved ERNESTO CORRAL
Reinforced Concrete Frame 4/6/2018 Partial Inspection ERNESTO CORRAL
Verify Sprinkler Sign Off 4/6/2018 Not Ready for Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 4/9/2018 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 4/9/2018 Partial Inspection ERNESTO CORRAL
METHANE-Barrier 4/9/2018 Approved ERNESTO CORRAL
METHANE-Subgrade 4/9/2018 Approved ERNESTO CORRAL
Pre-Inspection 4/9/2018 Approved ERNESTO CORRAL
Deputy Reinf. Concrete 4/10/2018 Conditional Approval ERNESTO CORRAL
Pre-Inspection 4/10/2018 Approved ERNESTO CORRAL
Deputy Reinf. Concrete 4/11/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 4/12/2018 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/13/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 4/16/2018 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 4/16/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 4/17/2018 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 4/17/2018 Conditional Approval ERNESTO CORRAL
Green Building Rough 4/17/2018 Not Ready for Inspection ERNESTO CORRAL
Reinforced Concrete Frame 4/17/2018 Partial Inspection ERNESTO CORRAL
Verify Sprinkler Sign Off 4/17/2018 Not Ready for Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 4/18/2018 Conditional Approval NICK DANERI
Deputy Shotcrete 4/18/2018 Conditional Approval NICK DANERI
Reinforced Masonry Frame 4/18/2018 Partial Approval NICK DANERI
Deputy Reinf. Concrete 4/19/2018 Conditional Approval NICK DANERI
Deputy Shotcrete 4/19/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 4/20/2018 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 4/20/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 4/20/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 4/23/2018 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 4/23/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 4/24/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 4/25/2018 Conditional Approval NICK DANERI
Green Building Rough 4/25/2018 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 4/25/2018 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 4/25/2018 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 4/26/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 4/27/2018 Corrections Issued ERNESTO CORRAL
Deputy Methane Barrier 4/30/2018 Conditional Approval ERNESTO CORRAL
Deputy Methane Barrier 5/1/2018 Conditional Approval ERNESTO CORRAL
Deputy Methane Barrier 5/2/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 5/3/2018 Partial Inspection ERNESTO CORRAL
Deputy Drilled-In Anchors 5/4/2018 Conditional Approval ERNESTO CORRAL
Deputy Methane Barrier 5/4/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 5/4/2018 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 5/7/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 5/7/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 5/7/2018 Partial Inspection ERNESTO CORRAL
Deputy Drilled-In Anchors 5/8/2018 Conditional Approval ERNESTO CORRAL
Deputy Methane Barrier 5/8/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 5/8/2018 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 5/9/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 5/9/2018 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 5/10/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 5/10/2018 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 5/10/2018 Partial Inspection ERNESTO CORRAL
Reinforced Masonry Frame 5/10/2018 Partial Inspection ERNESTO CORRAL
Deputy Drilled-In Anchors 5/11/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 5/11/2018 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 5/15/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 5/15/2018 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 5/16/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 5/16/2018 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 5/17/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 5/17/2018 Conditional Approval NICK DANERI
Deputy Drilled-In Anchors 5/18/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 5/18/2018 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 5/21/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 5/21/2018 Conditional Approval ERNESTO CORRAL
Reinforced Masonry Frame 5/21/2018 Partial Inspection ERNESTO CORRAL
Deputy Drilled-In Anchors 5/22/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 5/22/2018 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 5/22/2018 Partial Inspection ERNESTO CORRAL
Deputy Drilled-In Anchors 5/23/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 5/23/2018 Conditional Approval NICK DANERI
Deputy Drilled-In Anchors 5/24/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 5/24/2018 Conditional Approval NICK DANERI
Deputy Drilled-In Anchors 5/25/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 5/25/2018 Conditional Approval NICK DANERI
Reinforced Concrete Frame 5/29/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 5/30/2018 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 5/30/2018 Conditional Approval ERNESTO CORRAL
Reinforced Masonry Frame 5/30/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 5/31/2018 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 5/31/2018 Conditional Approval ERNESTO CORRAL
Structural Steel Frame 5/31/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 6/1/2018 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 6/1/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/4/2018 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 6/4/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 6/4/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 6/5/2018 Conditional Approval WINSTON DUNNING
Deputy Reinf. Concrete 6/5/2018 Partial Approval FELIX CEBALLOS
Deputy Shotcrete 6/5/2018 Conditional Approval WINSTON DUNNING
Deputy Reinf. Concrete 6/6/2018 Conditional Approval NICK DANERI
Deputy Shotcrete 6/6/2018 Conditional Approval NICK DANERI
Deputy Methane Barrier 6/7/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/7/2018 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 6/7/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/8/2018 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 6/8/2018 Conditional Approval ERNESTO CORRAL
Reinforced Masonry Frame 6/11/2018 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 6/12/2018 Conditional Approval ERNESTO CORRAL
Structural Steel Frame 6/12/2018 Off-Hour Fees Due
Deputy Reinf. Concrete 6/13/2018 Partial Approval JAMES POWERS
Reinforced Concrete Frame 6/13/2018 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/14/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 6/15/2018 Conditional Approval JAMES POWERS
Reinforced Masonry Frame 6/15/2018 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/18/2018 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 6/18/2018 Conditional Approval ERNESTO CORRAL
Reinforced Masonry Frame 6/18/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 6/19/2018 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 6/19/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/20/2018 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 6/20/2018 Conditional Approval ERNESTO CORRAL
Masonry Wall/Backfill 6/20/2018 Partial Approval ERNESTO CORRAL
Reinforced Masonry Frame 6/20/2018 Partial Inspection ERNESTO CORRAL
Structural Steel Frame 6/20/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 6/21/2018 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 6/21/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/22/2018 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 6/22/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/26/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/27/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 6/27/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 6/28/2018 Conditional Approval ERNESTO CORRAL
Masonry Wall/Backfill 6/28/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 6/29/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 6/29/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 7/2/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/6/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 7/6/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 7/10/2018 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 7/10/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 7/10/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 7/11/2018 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 7/11/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/12/2018 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 7/12/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/13/2018 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 7/13/2018 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 7/16/2018 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 7/16/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/18/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 7/18/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 7/19/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/20/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/23/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/24/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 7/27/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 7/30/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/31/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/1/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/2/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/3/2018 Conditional Approval ERNESTO CORRAL
Structural Steel Frame 8/6/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 8/7/2018 Conditional Approval LESLIE TRUJILLO
Light Gage Steel Frame 8/7/2018 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/8/2018 Conditional Approval ERNESTO CORRAL
Light Gage Steel Frame 8/11/2018 Off-Hour Fees Due
Light Gage Steel Frame 8/11/2018 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/15/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 8/15/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 8/16/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/20/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 8/20/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 8/21/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/22/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/23/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/24/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/28/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/29/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/30/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 8/31/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 9/4/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 9/6/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 9/6/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 9/7/2018 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 9/7/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 9/10/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 9/11/2018 Conditional Approval ERNESTO CORRAL
Deputy Pre-Stress Concrete 9/12/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 9/12/2018 Conditional Approval ERNESTO CORRAL
Deputy Pre-Stress Concrete 9/13/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 9/13/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 9/13/2018 Partial Inspection ERNESTO CORRAL
Deputy Pre-Stress Concrete 9/14/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 9/18/2018 Partial Inspection ERNESTO CORRAL
Deputy Pre-Stress Concrete 9/19/2018 Conditional Approval ERNESTO CORRAL
Green Building Rough 9/19/2018 Approved ERNESTO CORRAL
Reinforced Concrete Frame 9/19/2018 Partial Inspection ERNESTO CORRAL
Verify Sprinkler Sign Off 9/19/2018 Approved ERNESTO CORRAL
Deputy Pre-Stress Concrete 9/20/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 9/20/2018 Partial Inspection ERNESTO CORRAL
Deputy Pre-Stress Concrete 9/21/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 9/21/2018 Conditional Approval ERNESTO CORRAL
Deputy Pre-Stress Concrete 9/24/2018 Conditional Approval ERNESTO CORRAL
Deputy Pre-Stress Concrete 9/25/2018 Conditional Approval ERNESTO CORRAL
Deputy Pre-Stress Concrete 9/26/2018 Conditional Approval ERNESTO CORRAL
Deputy Pre-Stress Concrete 9/27/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 9/27/2018 Partial Inspection ERNESTO CORRAL
Deputy Pre-Stress Concrete 9/28/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 9/28/2018 Partial Inspection ERNESTO CORRAL
Deputy Pre-Stress Concrete 10/2/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 10/2/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 10/3/2018 Conditional Approval ERNESTO CORRAL
Deputy Methane Barrier 10/5/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 10/10/2018 Partial Inspection ERNESTO CORRAL
Deputy Pre-Stress Concrete 10/11/2018 Conditional Approval ERNESTO CORRAL
Reinforced Masonry Frame 10/11/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 10/12/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 10/15/2018 Partial Approval JAMES POWERS
Deputy Shotcrete 10/15/2018 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/17/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 10/17/2018 Partial Inspection ERNESTO CORRAL
Reinforced Masonry Frame 10/18/2018 Partial Inspection ERNESTO CORRAL
Deputy Pre-Stress Concrete 10/19/2018 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/19/2018 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 10/24/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 10/24/2018 Partial Inspection ERNESTO CORRAL
Deputy Pre-Stress Concrete 10/25/2018 Conditional Approval ERNESTO CORRAL
Reinforced Masonry Frame 10/25/2018 Partial Inspection ERNESTO CORRAL
Deputy Pre-Stress Concrete 10/26/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 10/26/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 10/31/2018 Partial Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 11/1/2018 Conditional Approval LESLIE TRUJILLO
Reinforced Masonry Frame 11/1/2018 Partial Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 11/2/2018 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 11/5/2018 Conditional Approval ERNESTO CORRAL
Deputy Pre-Stress Concrete 11/6/2018 Conditional Approval ERNESTO CORRAL
Deputy Pre-Stress Concrete 11/7/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 11/7/2018 Partial Inspection ERNESTO CORRAL
Deputy Pre-Stress Concrete 11/8/2018 Conditional Approval ERNESTO CORRAL
Reinforced Masonry Frame 11/8/2018 Partial Inspection ERNESTO CORRAL
Deputy Pre-Stress Concrete 11/9/2018 Conditional Approval ERNESTO CORRAL
Structural Steel Frame 11/9/2018 Partial Inspection ERNESTO CORRAL
Deputy Pre-Stress Concrete 11/14/2018 Conditional Approval ERNESTO CORRAL
Deputy Pre-Stress Concrete 11/15/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 11/15/2018 Partial Inspection ERNESTO CORRAL
Deputy Pre-Stress Concrete 11/16/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 11/16/2018 Partial Inspection ERNESTO CORRAL
Structural Steel Frame 11/19/2018 Partial Inspection ERNESTO CORRAL
Deputy Pre-Stress Concrete 11/28/2018 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 11/28/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 11/28/2018 Partial Inspection ERNESTO CORRAL
Deputy Pre-Stress Concrete 11/29/2018 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 11/29/2018 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 11/29/2018 Partial Inspection ERNESTO CORRAL
Pre-Inspection 11/29/2018 Approved ERNESTO CORRAL
Deputy Pre-Stress Concrete 11/30/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 11/30/2018 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 11/30/2018 Conditional Approval ERNESTO CORRAL
Deputy Pre-Stress Concrete 12/5/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 12/5/2018 Partial Inspection ERNESTO CORRAL
Reinforced Masonry Frame 12/6/2018 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 12/7/2018 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 12/12/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 12/12/2018 Partial Inspection ERNESTO CORRAL
Deputy Pre-Stress Concrete 12/13/2018 Conditional Approval ERNESTO CORRAL
Structural Steel Frame 12/13/2018 Partial Inspection ERNESTO CORRAL
Deputy Pre-Stress Concrete 12/14/2018 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 12/14/2018 Conditional Approval JEFFREY FULTON
Deputy Pre-Stress Concrete 12/19/2018 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 12/19/2018 Partial Inspection ERNESTO CORRAL
Deputy Pre-Stress Concrete 12/20/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 12/20/2018 Partial Inspection ERNESTO CORRAL
Deputy Pre-Stress Concrete 12/21/2018 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 12/21/2018 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 12/31/2018 Partial Inspection ERNESTO CORRAL
Deputy Pre-Stress Concrete 1/2/2019 Partial Approval JAMES POWERS
Reinforced Concrete Frame 1/2/2019 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 1/3/2019 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 1/4/2019 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 1/7/2019 Conditional Approval ERNESTO CORRAL
Light Gage Steel Frame 1/8/2019 Partial Inspection ERNESTO CORRAL
Reinforced Concrete Frame 1/8/2019 Partial Inspection ERNESTO CORRAL
Deputy Pre-Stress Concrete 1/9/2019 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 1/9/2019 Partial Inspection ERNESTO CORRAL
Deputy Pre-Stress Concrete 1/10/2019 Conditional Approval ERNESTO CORRAL
Structural Steel Frame 1/10/2019 Partial Inspection ERNESTO CORRAL
Deputy Pre-Stress Concrete 1/16/2019 Conditional Approval ERNESTO CORRAL
Insulation 1/16/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 1/16/2019 Partial Inspection ERNESTO CORRAL
Reinforced Concrete Frame 1/16/2019 Partial Inspection ERNESTO CORRAL
Deputy Pre-Stress Concrete 1/17/2019 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 1/17/2019 Partial Inspection ERNESTO CORRAL
Deputy Pre-Stress Concrete 1/18/2019 Conditional Approval ERNESTO CORRAL
Deputy Pre-Stress Concrete 1/22/2019 Conditional Approval ERNESTO CORRAL
Deputy Pre-Stress Concrete 1/23/2019 Conditional Approval ERNESTO CORRAL
Light Gage Steel Frame 1/23/2019 Partial Inspection ERNESTO CORRAL
Reinforced Concrete Frame 1/23/2019 Partial Inspection ERNESTO CORRAL
Structural Steel Frame 1/24/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 1/25/2019 Conditional Approval ERNESTO CORRAL
Light Gage Steel Frame 1/30/2019 Partial Inspection ERNESTO CORRAL
Reinforced Concrete Frame 1/30/2019 Partial Inspection ERNESTO CORRAL
Reinforced Concrete Frame 1/31/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 2/4/2019 Conditional Approval ERNESTO CORRAL
Insulation 2/6/2019 Not Ready for Inspection ERNESTO CORRAL
Light Gage Steel Frame 2/6/2019 Partial Inspection ERNESTO CORRAL
Deputy Pre-Stress Concrete 2/7/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 2/7/2019 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 2/7/2019 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 2/7/2019 Partial Inspection ERNESTO CORRAL
Deputy Pre-Stress Concrete 2/13/2019 Conditional Approval ERNESTO CORRAL
Insulation 2/13/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 2/13/2019 Partial Inspection ERNESTO CORRAL
Reinforced Concrete Frame 2/13/2019 Partial Inspection ERNESTO CORRAL
Deputy Pre-Stress Concrete 2/14/2019 Conditional Approval ERNESTO CORRAL
Light Gage Steel Frame 2/14/2019 Partial Inspection ERNESTO CORRAL
Deputy Pre-Stress Concrete 2/15/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 2/20/2019 Conditional Approval ERNESTO CORRAL
Light Gage Steel Frame 2/20/2019 Partial Inspection ERNESTO CORRAL
Reinforced Concrete Frame 2/20/2019 Corrections Issued ERNESTO CORRAL
Light Gage Steel Frame 2/25/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 2/28/2019 Partial Inspection ERNESTO CORRAL
Reinforced Concrete Frame 2/28/2019 Partial Inspection ERNESTO CORRAL
Reinforced Masonry Frame 3/4/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 3/5/2019 Conditional Approval ERNESTO CORRAL
Light Gage Steel Frame 3/7/2019 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 3/11/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 3/14/2019 Partial Inspection ERNESTO CORRAL
Deputy Other (see comments) 3/15/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 3/15/2019 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 3/15/2019 Partial Inspection ERNESTO CORRAL
Deputy Other (see comments) 3/18/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 3/18/2019 Conditional Approval ERNESTO CORRAL
Reinforced Masonry Frame 3/18/2019 Partial Inspection ERNESTO CORRAL
Deputy Other (see comments) 3/19/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 3/19/2019 Conditional Approval ERNESTO CORRAL
Deputy Other (see comments) 3/20/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 3/20/2019 Conditional Approval ERNESTO CORRAL
Deputy Other (see comments) 3/21/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 3/21/2019 Conditional Approval ERNESTO CORRAL
Drywall Nailing 3/21/2019 Partial Inspection ERNESTO CORRAL
Reinforced Concrete Frame 3/22/2019 Not Ready for Inspection NICK DANERI
Drywall Nailing 3/26/2019 Partial Inspection ERNESTO CORRAL
Reinforced Concrete Frame 3/26/2019 Partial Inspection ERNESTO CORRAL
Drywall Nailing 3/27/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 3/27/2019 Partial Inspection ERNESTO CORRAL
Reinforced Masonry Frame 3/27/2019 Partial Inspection ERNESTO CORRAL
Drywall Nailing 3/28/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 3/28/2019 Partial Inspection ERNESTO CORRAL
Reinforced Concrete Frame 3/28/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 3/29/2019 Conditional Approval ERNESTO CORRAL
Drywall Nailing 4/2/2019 Partial Inspection ERNESTO CORRAL
Drywall Nailing 4/4/2019 Partial Inspection ERNESTO CORRAL
Reinforced Concrete Frame 4/4/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 4/5/2019 Conditional Approval LESLIE TRUJILLO
Drywall Nailing 4/12/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 4/12/2019 Partial Inspection ERNESTO CORRAL
Reinforced Concrete Frame 4/17/2019 Partial Inspection ERNESTO CORRAL
Drywall Nailing 4/18/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 4/18/2019 Partial Inspection ERNESTO CORRAL
Reinforced Masonry Frame 4/18/2019 Partial Inspection ERNESTO CORRAL
Deputy Steel/Welding 4/22/2019 Conditional Approval ERNESTO CORRAL
Drywall Nailing 4/22/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 4/22/2019 Partial Inspection ERNESTO CORRAL
Drywall Nailing 4/24/2019 Partial Inspection ERNESTO CORRAL
Insulation 4/24/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 4/24/2019 Partial Inspection ERNESTO CORRAL
Drywall Nailing 5/1/2019 Partial Inspection ERNESTO CORRAL
Insulation 5/1/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 5/1/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 5/2/2019 Partial Inspection ERNESTO CORRAL
Drywall Nailing 5/8/2019 Partial Inspection ERNESTO CORRAL
Insulation 5/8/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 5/8/2019 Partial Inspection ERNESTO CORRAL
Drywall Nailing 5/16/2019 Partial Inspection ERNESTO CORRAL
Insulation 5/16/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 5/16/2019 Partial Inspection ERNESTO CORRAL
Drywall Nailing 5/23/2019 Partial Inspection ERNESTO CORRAL
Insulation 5/23/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 5/23/2019 Corrections Issued ERNESTO CORRAL
Insulation 5/30/2019 Not Ready for Inspection ERNESTO CORRAL
Light Gage Steel Frame 5/30/2019 Partial Inspection ERNESTO CORRAL
Drywall Nailing 6/6/2019 Partial Approval JAMES POWERS
Insulation 6/6/2019 Partial Approval JAMES POWERS
Light Gage Steel Frame 6/6/2019 Partial Approval JAMES POWERS
Insulation 6/12/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 6/12/2019 Partial Inspection ERNESTO CORRAL
Drywall Nailing 6/17/2019 Partial Inspection ERNESTO CORRAL
Insulation 6/20/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 6/20/2019 Partial Inspection ERNESTO CORRAL
Drywall Nailing 6/26/2019 Partial Inspection ERNESTO CORRAL
Insulation 7/2/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 7/2/2019 Partial Inspection ERNESTO CORRAL
Drywall Nailing 7/10/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 7/10/2019 Partial Inspection ERNESTO CORRAL
Drywall Nailing 7/17/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 7/17/2019 Partial Inspection ERNESTO CORRAL
Pre-Inspection 7/18/2019 Approved ERNESTO CORRAL
Insulation 7/23/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 7/23/2019 Partial Inspection ERNESTO CORRAL
Drywall Nailing 7/25/2019 Partial Approval LESLIE TRUJILLO
Insulation 7/25/2019 Partial Approval LESLIE TRUJILLO
Drywall Nailing 7/30/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 7/30/2019 Partial Inspection ERNESTO CORRAL
Drywall Nailing 8/2/2019 Partial Inspection ERNESTO CORRAL
Insulation 8/2/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 8/7/2019 Partial Inspection ERNESTO CORRAL
Insulation 8/13/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 8/13/2019 Partial Inspection ERNESTO CORRAL
Drywall Nailing 8/15/2019 Partial Inspection ERNESTO CORRAL
Insulation 8/15/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 8/16/2019 Partial Inspection ERNESTO CORRAL
Insulation 8/19/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 8/19/2019 Partial Inspection ERNESTO CORRAL
Drywall Nailing 8/26/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 8/28/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 9/3/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 9/5/2019 Partial Inspection ERNESTO CORRAL
Drywall Nailing 9/25/2019 Partial Approval DANIEL MC AULIFFE
Light Gage Steel Frame 10/10/2019 Partial Approval JOEY BUCHANAN
Drywall Nailing 10/16/2019 Not Ready for Inspection ERNESTO CORRAL
Final 10/16/2019 Partial Inspection ERNESTO CORRAL
Footing/Foundation/Slab 10/16/2019 Approved ERNESTO CORRAL
Green Building Final 10/16/2019 Not Ready for Inspection ERNESTO CORRAL
Reinforced Concrete Frame 10/16/2019 Not Ready for Inspection ERNESTO CORRAL
SGSOV-Seismic Gas S/O Valve 10/16/2019 SGSOV Not Ready ERNESTO CORRAL
Smoke Detectors 10/16/2019 Not Ready for Inspection ERNESTO CORRAL
Drywall Nailing 10/18/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 10/18/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 11/5/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 11/21/2019 Partial Inspection DANIEL MC AULIFFE
Light Gage Steel Frame 11/25/2019 Not Ready for Inspection ERNESTO CORRAL
Light Gage Steel Frame 11/27/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 12/6/2019 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 12/12/2019 Partial Inspection ERNESTO CORRAL
Drywall Nailing 12/18/2019 Partial Inspection ERNESTO CORRAL
Special/Order Compliance 12/18/2019 Corrections Issued ERNESTO CORRAL
Pre-Inspection 12/23/2019 No Access for Inspection ERNESTO CORRAL
Pre-Inspection 12/27/2019 Approved ERNESTO CORRAL
Deputy Drilled-In Anchors 12/31/2019 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 1/6/2020 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 2/21/2020 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 2/21/2020 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 2/21/2020 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 2/24/2020 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 2/24/2020 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 2/24/2020 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 2/25/2020 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 2/25/2020 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 2/25/2020 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 2/26/2020 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 2/26/2020 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 2/26/2020 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 2/27/2020 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 2/27/2020 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 2/27/2020 Conditional Approval ERNESTO CORRAL
Drywall Nailing 4/16/2020 Not Ready for Inspection ERNESTO CORRAL
Green Building Final 4/16/2020 Not Ready for Inspection ERNESTO CORRAL
Reinforced Concrete Frame 4/16/2020 Not Ready for Inspection ERNESTO CORRAL
SGSOV-Seismic Gas S/O Valve 4/16/2020 SGSOV Not Ready ERNESTO CORRAL
Smoke Detectors 4/16/2020 Not Ready for Inspection ERNESTO CORRAL
Final 4/17/2020 Corrections Issued ERNESTO CORRAL
Drywall Nailing 4/20/2020 Partial Inspection ERNESTO CORRAL
Final 4/20/2020 Partial Inspection ERNESTO CORRAL
Green Building Final 4/20/2020 Not Ready for Inspection ERNESTO CORRAL
Reinforced Concrete Frame 4/20/2020 Not Ready for Inspection ERNESTO CORRAL
SGSOV-Seismic Gas S/O Valve 4/20/2020 SGSOV Not Ready ERNESTO CORRAL
Smoke Detectors 4/20/2020 Not Ready for Inspection ERNESTO CORRAL
Drywall Nailing 4/28/2020 Partial Inspection ERNESTO CORRAL
Final 4/28/2020 Partial Inspection ERNESTO CORRAL
Green Building Final 4/28/2020 Partial Inspection ERNESTO CORRAL
Reinforced Concrete Frame 4/28/2020 Partial Inspection ERNESTO CORRAL
SGSOV-Seismic Gas S/O Valve 4/28/2020 SGSOV Approved ERNESTO CORRAL
Smoke Detectors 4/28/2020 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 5/14/2020 Partial Approval NICK DANERI
Light Gage Steel Frame 6/16/2020 Partial Approval NICK DANERI
Pre-Inspection 7/9/2020 Conditional Approval NICK DANERI
Drywall Nailing 7/29/2020 Approved NICK DANERI
Final 7/29/2020 Not Ready for Inspection NICK DANERI
Green Building Final 7/29/2020 Not Ready for Inspection NICK DANERI
Pre-Inspection 7/29/2020 Partial Inspection NICK DANERI
Reinforced Concrete Frame 7/29/2020 Partial Inspection NICK DANERI
Smoke Detectors 7/29/2020 Not Ready for Inspection NICK DANERI
Final 8/10/2020 Not Ready for Inspection NICK DANERI
Green Building Final 8/10/2020 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 8/10/2020 Not Ready for Inspection NICK DANERI
Smoke Detectors 8/10/2020 Not Ready for Inspection NICK DANERI
Special/Order Compliance 8/10/2020 Conditional Approval NICK DANERI
Special/Order Compliance 8/13/2020 Corrections Issued NICK DANERI
Green Building Final 8/14/2020 Not Ready for Inspection NICK DANERI
Special/Order Compliance 8/17/2020 Partial Approval NICK DANERI
Special/Order Compliance 8/18/2020 Partial Approval NICK DANERI
Special/Order Compliance 8/19/2020 Partial Approval NICK DANERI
Special/Order Compliance 8/20/2020 Partial Approval NICK DANERI
Special/Order Compliance 8/21/2020 Partial Approval NICK DANERI
Special/Order Compliance 8/24/2020 Partial Approval NICK DANERI
Special/Order Compliance 8/25/2020 Partial Approval NICK DANERI
Special/Order Compliance 8/26/2020 Partial Inspection NICK DANERI
Special/Order Compliance 8/27/2020 Partial Approval NICK DANERI
Final 8/28/2020 OK for TCO NICK DANERI
Green Building Final 8/28/2020 Approved NICK DANERI
Reinforced Concrete Frame 8/28/2020 Approved NICK DANERI
Smoke Detectors 8/28/2020 Approved NICK DANERI
Special/Order Compliance 1/27/2021 Conditional Approval NICK DANERI
Special/Order Compliance 7/28/2021 Approved ERNESTO CORRAL
Special/Order Compliance 2/2/2022 Partial Inspection RAFAEL ESPINOZA
Special/Order Compliance 8/19/2022 Conditional Approval NICK DANERI
Final 10/21/2022 No Access for Inspection RAFAEL ESPINOZA
Special/Order Compliance 3/1/2023 Conditional Approval NICK DANERI
Special/Order Compliance 8/29/2023 No Access for Inspection LARRY ARNICK
Final 3/15/2024 OK to Issue CofO RAFAEL ESPINOZA