1839 S VAN NESS AVE 90019
Certificate Information: 1839 S VAN NESS AVE 90019
- Application / Permit
- 13010-10000-00848
- Plan Check / Job No.
- B13LA03568
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- CONSTRUCT NEW DETACHED 3-CAR GARAGE W/RECREATION ROOM @ 2ND FLOOR; 1,528 S.F.
- Permit Issued
- Issued on 9/25/2013
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/21/2013 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2013 | TARIK SAOUD |
| Corrections Issued | 4/2/2013 | TARIK SAOUD |
| Quality Review Completed | 4/5/2013 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 4/11/2013 | APPLICANT |
| Green Plans Picked Up | 5/16/2013 | APPLICANT |
| Applicant returned to address corrections | 7/10/2013 | TARIK SAOUD |
| Applicant returned to address corrections | 8/16/2013 | TARIK SAOUD |
| Applicant returned to address corrections | 9/13/2013 | TARIK SAOUD |
| Applicant returned to address corrections | 9/24/2013 | TARIK SAOUD |
| Plan Check Approved | 9/25/2013 | TARIK SAOUD |
| Issued | 9/25/2013 | LADBS |
| CofO in Progress | 7/16/2025 | WILLIAM SIERRA |
| Permit Finaled | 7/19/2025 | DEROLD HAUFF |
| CofO Issued | 7/19/2025 | DEROLD HAUFF |
| Permit Finaled | 7/19/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Drainage to Storm Drain | Cleared | 7/10/2013 | AVALYN KAMACHI |
| Sewer availability | Cleared | 7/10/2013 | AVALYN KAMACHI |
| Green Code | Cleared | 7/17/2013 | MICHAEL TUCK |
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2013 | AVALYN KAMACHI |
| Low Impact Development | Cleared | 8/6/2013 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 8/6/2013 | AVALYN KAMACHI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Skaf, Nazem Gabrail; Lic. No.: C46215 | 411 GREEN ORCHARD PLACE RIVERSIDE, CA 92506 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/25/2013 | Not Ready for Inspection | RONALD COWAN |
| METHANE-Barrier | 11/25/2013 | Not Ready for Inspection | RONALD COWAN |
| METHANE-Subgrade | 11/25/2013 | Not Ready for Inspection | RONALD COWAN |
| Footing/Foundation/Slab | 3/28/2014 | Not Ready for Inspection | EDWARD GOMEZ |
| METHANE-Barrier | 3/28/2014 | Not Ready for Inspection | EDWARD GOMEZ |
| METHANE-Subgrade | 3/28/2014 | Not Ready for Inspection | EDWARD GOMEZ |
| Excavation/Setback/Form/Re-Bar | 4/1/2014 | Corrections Issued | EDWARD GOMEZ |
| METHANE-Rough | 4/4/2014 | Not Ready for Inspection | EDWARD GOMEZ |
| Footing/Foundation/Slab | 4/10/2014 | Not Ready for Inspection | EDWARD GOMEZ |
| METHANE-Barrier | 4/10/2014 | Partial Approval | EDWARD GOMEZ |
| METHANE-Subgrade | 4/10/2014 | Partial Approval | EDWARD GOMEZ |
| Footing/Foundation/Slab | 4/15/2014 | Partial Inspection | EDWARD GOMEZ |
| METHANE-Barrier | 4/15/2014 | Partial Inspection | EDWARD GOMEZ |
| METHANE-Subgrade | 4/15/2014 | Partial Approval | EDWARD GOMEZ |
| Deputy Reinf. Concrete | 4/23/2014 | Conditional Approval | EDWARD GOMEZ |
| Deputy Wood Construction | 9/5/2014 | Conditional Approval | EDWARD GOMEZ |
| BUILDING-Rough-Frame | 11/21/2014 | Partial Inspection | EDWARD GOMEZ |
| Green Building Rough | 11/21/2014 | No Access for Inspection | EDWARD GOMEZ |
| METHANE-Rough | 11/21/2014 | Not Ready for Inspection | EDWARD GOMEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2014 | Partial Approval | MARK HATFIELD |
| Interior/Exterior Lathing | 12/31/2014 | Partial Inspection | EDWARD GOMEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2015 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2015 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 9/22/2015 | Corrections Issued | SCOTT FINNILA |
| METHANE-Rough | 9/22/2015 | Corrections Issued | SCOTT FINNILA |
| Gas Test | 6/8/2016 | Approved | SCOTT FINNILA |
| Underground Mechanical | 6/8/2016 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 11/16/2016 | Not Ready for Inspection | MATTHEW NUCKOLLS |
| ELECTRICAL-Final | 11/16/2016 | Not Ready for Inspection | MATTHEW NUCKOLLS |
| ELECTRICAL-Rough | 1/20/2017 | Approved | MATTHEW NUCKOLLS |
| BUILDING-Rough-Frame | 7/5/2018 | Partial Approval | SALVADOR GONZALEZ |
| Green Building Rough | 7/5/2018 | Approved | SALVADOR GONZALEZ |
| BUILDING-Rough-Frame | 11/13/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| METHANE-Rough | 11/13/2020 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 6/29/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 6/20/2025 | Approved | WILLIAM SIERRA |
| Drywall Nailing | 6/20/2025 | Approved | WILLIAM SIERRA |
| Final | 6/20/2025 | Corrections Issued | WILLIAM SIERRA |
| Footing/Foundation/Slab | 6/20/2025 | Approved | WILLIAM SIERRA |
| Green Building Final | 6/20/2025 | Corrections Issued | WILLIAM SIERRA |
| METHANE-Barrier | 6/20/2025 | Approved | WILLIAM SIERRA |
| METHANE-Subgrade | 6/20/2025 | Approved | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 6/20/2025 | SGSOV Approved | WILLIAM SIERRA |
| Smoke Detectors | 6/20/2025 | Approved | WILLIAM SIERRA |
| Final | 7/15/2025 | OK to Issue CofO | WILLIAM SIERRA |
| Green Building Final | 7/15/2025 | Approved | WILLIAM SIERRA |