661 S IMPERIAL ST 90021

Certificate Information: 661 S IMPERIAL ST 90021

Application / Permit
12016-10000-19016
Plan Check / Job No.
B12LA11160
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
STRUCTURAL ALTERATION TO (E) TYPE IV WAREHOUSE BUILDING - CUT NEW OPENINGS ON THE ROOF TO CREATE A COURT AND NEW OPENINGS FOR WINDOWS AND DOORS; NEW MECH'L MEZZANINE & NEW BATHROOMS. (CHANGE OF USE & T.I. UNDER SEPARATE PERMIT 12016-10000-18759) SEE COMMENTS
Permit Issued
Issued on 10/25/2012
Issuing Office
Metro
Current Status
Permit Finaled on 7/2/2013
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/21/2012 APPLICANT
Assigned to Plan Check Engineer 9/27/2012 CHARLES CHANG
Corrections Issued 10/1/2012 CHARLES CHANG
Quality Review Completed 10/4/2012 BILL STUTSMAN
Building Plans Picked Up 10/11/2012 APPLICANT
Disabled Access Plans Picked Up 10/11/2012 APPLICANT
Green Plans Picked Up 10/12/2012 APPLICANT
Plan Check Approved 10/24/2012 CHARLES CHANG
Issued 10/25/2012 LADBS
Permit Finaled 7/2/2013 WILLIAM GARCIA

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/17/2012 AVALYN KAMACHI
Sewer availability Cleared 10/17/2012 AVALYN KAMACHI
ZA Case Cleared 10/17/2012 EMMANUELA GUTIERREZ
DAS Clearance Cleared 10/19/2012 CHARLES CHANG
Food Service Establishment Cleared 10/22/2012 KENNETH BROWNE
Green Code Cleared 10/23/2012 MARCUS LEVIAS

Contact Information

Contractor Owner-Builder       ,
Engineer Breaks, Matthew Calvin; Lic. No.: C70590 5056 TUJUNGA AVE APT 17      NORTH HOLLYWOOD, CA 91601

Inspector Information

JULIAN CAPUCETTI, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/17/2012 Not Ready for Inspection WILLIAM GARCIA
Footing/Foundation/Slab 12/17/2012 Not Ready for Inspection WILLIAM GARCIA
Excavation/Setback/Form/Re-Bar 12/18/2012 Not Ready for Inspection BARRY SILLS
Footing/Foundation/Slab 12/18/2012 Not Ready for Inspection BARRY SILLS
Deputy Drilled-In Anchors 12/19/2012 Conditional Approval BARRY SILLS
Excavation/Setback/Form/Re-Bar 12/20/2012 Partial Inspection WILLIAM GARCIA
Pre-Inspection 1/10/2013 Approved BARRY SILLS
Special/Order Compliance 1/10/2013 Approved BARRY SILLS
Wood Frame 1/16/2013 Partial Approval BARRY SILLS
Deputy Drilled-In Anchors 2/13/2013 Conditional Approval BARRY SILLS
Deputy Steel/Welding 2/13/2013 Conditional Approval BARRY SILLS
Insulation 2/21/2013 Partial Approval BARRY SILLS
Wood Frame 4/8/2013 Not Ready for Inspection WILLIAM GARCIA
Wood Frame 4/22/2013 Partial Approval BARRY SILLS
Drywall Nailing 5/3/2013 Partial Inspection WILLIAM GARCIA
Green Building Final 6/6/2013 Approved MICHAEL TUCK
Final 6/7/2013 OK for TCO BARRY SILLS
METHANE-Final 6/7/2013 Approved BARRY SILLS
SGSOV-Seismic Gas S/O Valve 6/7/2013 SGSOV Approved BARRY SILLS
Smoke Detectors 6/7/2013 Approved BARRY SILLS