13439 W ADDISON ST 91423
Certificate Information: 13439 W ADDISON ST 91423
- Application / Permit
- 12014-20000-04620
- Plan Check / Job No.
- B12VN13682
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- Add 570 s.f on top of (e) attached garage to create 2nd dwelling unit per ZA Memorendum#120.See comments.
- Permit Issued
- Issued on 8/2/2013
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/21/2012 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2013 | FARUK SEZER |
| Green Plans Picked Up | 1/4/2013 | APPLICANT |
| Corrections Issued | 1/7/2013 | FARUK SEZER |
| Quality Review Completed | 1/9/2013 | TAMERA SVETICH |
| Building Plans Picked Up | 1/9/2013 | APPLICANT |
| Plan Check Approved | 6/14/2013 | FARUK SEZER |
| Issued | 8/2/2013 | LADBS |
| Permit Expired-Status Void | 3/19/2020 | DANIEL ORRANTE |
| Re-Activate Permit | 3/2/2023 | DANIEL ORRANTE |
| CofO in Progress | 5/10/2023 | JUAN VALENZUELA |
| Permit Finaled | 4/16/2024 | DANIEL ORRANTE |
| CofO Issued | 4/16/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/16/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 2/20/2013 | HOWARD COOPER |
| Eng Process Fee Ord 176,300 | Cleared | 2/20/2013 | CHRISTINE KEUSHGUERIAN |
| Permit | Cleared | 2/20/2013 | CHRISTINE KEUSHGUERIAN |
| Roof/Waste drainage to street | Cleared | 2/20/2013 | CHRISTINE KEUSHGUERIAN |
| Sewer availability | Cleared | 2/20/2013 | CHRISTINE KEUSHGUERIAN |
| Public Works-Highway Ded. | Cleared | 2/20/2013 | CHRISTINE KEUSHGUERIAN |
| Public Works-Open Permits | Cleared | 2/20/2013 | CHRISTINE KEUSHGUERIAN |
| Public Works-Sewers | Cleared | 2/20/2013 | CHRISTINE KEUSHGUERIAN |
| Hydrant and Access approval | Cleared | 3/5/2013 | ROBERT DUFF |
| Green Code | Cleared | 4/26/2013 | BRYAN MEYER |
| Low Impact Development | Cleared | 4/29/2013 | IDA MEISAMI-FARD |
Contact Information
| Contractor | Building Green Construction Services; Lic. No.: 947229-B | 6910 HAYVENHURST AVE #102 VAN NUYS, CA 91406 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/16/2013 | Corrections Issued | MICHAEL YOUNG |
| Footing/Foundation/Slab | 9/9/2013 | Approved | MICHAEL YOUNG |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2013 | Partial Approval | MICHAEL YOUNG |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2013 | Partial Approval | MICHAEL YOUNG |
| BUILDING-Rough-Frame | 10/21/2013 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2013 | No Access for Inspection | CHRISTOPHE COCHRAN |
| Green Building Rough | 10/21/2013 | Not Ready for Inspection | RICHARD DOCKUS |
| Rough-Elec/Plmb/HVAC | 10/21/2013 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 10/22/2013 | Approved | MICHAEL YOUNG |
| HVAC-Rough | 10/22/2013 | Approved | MICHAEL YOUNG |
| PLUMBING-Rough | 10/22/2013 | Approved | MICHAEL YOUNG |
| Green Building Rough | 10/28/2013 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 10/28/2013 | Partial Approval | MICHAEL YOUNG |
| Insulation | 10/29/2013 | Not Ready for Inspection | MICHAEL YOUNG |
| Insulation | 10/30/2013 | Approved | DONALD SUNSERI |
| Interior/Exterior Lathing | 10/30/2013 | Partial Approval | DONALD SUNSERI |
| Drywall Nailing | 11/5/2013 | Approved | MICHAEL YOUNG |
| ELECTRICAL-Final | 3/26/2014 | Not Ready for Inspection | MICHAEL YOUNG |
| HVAC-Final | 3/26/2014 | Not Ready for Inspection | MICHAEL YOUNG |
| PLUMBING-Final | 3/26/2014 | Not Ready for Inspection | MICHAEL YOUNG |
| ELECTRICAL-Final | 5/2/2014 | Partial Approval | MICHAEL YOUNG |
| Special/Order Compliance | 3/19/2020 | Permit Expired-Status Void | DANIEL ORRANTE |
| Special/Order Compliance | 3/13/2023 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/9/2023 | Approved | MISAEL ESPARZA |
| Final | 5/9/2023 | OK to Issue CofO | MISAEL ESPARZA |
| Green Building Final | 5/9/2023 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 5/9/2023 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 5/9/2023 | Approved | MISAEL ESPARZA |