2260 N MARAVILLA DR 90068

Certificate Information: 2260 N MARAVILLA DR 90068

Application / Permit
12014-20000-03848
Plan Check / Job No.
B12VN11540
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1ST FLOOR 4' x 19' ADDITION, 2ND STORY 7' X 35' ADDITION, 6'8" X 9'6" and 5' 9'6" DECK, 3RD FLOOR 7'6" X 16'6" ADDITION AND 6'2" X 45'6" DECK. REMODEL ENTIRE 3 STORY SFD W. ATT GARAGE.
Permit Issued
Issued on 2/5/2013
Issuing Office
Valley
Current Status
CofO Issued on 10/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/26/2012 APPLICANT
Assigned to Plan Check Engineer 11/1/2012 HERNAN ARREOLA
Corrections Issued 11/5/2012 HERNAN ARREOLA
Quality Review Completed 11/6/2012 TAMERA SVETICH
Building Plans Picked Up 11/7/2012 APPLICANT
Plan Check Approved 2/5/2013 HERNAN ARREOLA
Issued 2/5/2013 LADBS
CofO in Progress 8/14/2023 BRIAN SULLIVAN
CofO Issued 10/18/2023 DEROLD HAUFF
Permit Finaled 10/18/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/29/2013 CHRISTINE KEUSHGUERIAN
Roof/Waste drainage to street Cleared 1/29/2013 CHRISTINE KEUSHGUERIAN
Sewer availability Cleared 1/29/2013 CHRISTINE KEUSHGUERIAN
Specific Plan Cleared 1/29/2013 RICK TORRES
VHFHSZ Cleared 1/29/2013 DAVID RILES
ZA Case Cleared 1/29/2013 DENNIS CHEW
Public Works-Highway Ded. Cleared 1/29/2013 CHRISTINE KEUSHGUERIAN
Public Works-Open Permits Cleared 1/29/2013 CHRISTINE KEUSHGUERIAN
Public Works-Sewers Cleared 1/29/2013 CHRISTINE KEUSHGUERIAN
Green Code Cleared 2/4/2013 ROLLIN GETTLE III
Grading Pre-Inspection Cleared 2/5/2013 HERNAN ARREOLA

Contact Information

Contractor C A A General Contractor; Lic. No.: 696570-B 5901 COLFAX AVE      NORTH HOLLYWOOD, CA 91601
Engineer Kim, Hong Kook; Lic. No.: C64529 839 S MUIRFIELD RD      LOS ANGELES, CA 90005

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Rough 7/10/2013 Approved DONALD CRICHLOW
Shower Pan 7/10/2013 Partial Approval RUBEN SALAS
BUILDING-Rough-Frame 7/15/2013 Corrections Issued RUBEN SALAS
ELECTRICAL-Rough 7/16/2013 Corrections Issued RUBEN SALAS
BUILDING-Rough-Frame 8/26/2013 Corrections Issued RUBEN SALAS
Interior/Exterior Lathing 8/27/2013 Not Ready for Inspection RUBEN SALAS
BUILDING-Rough-Frame 8/28/2013 Not Ready for Inspection RUBEN SALAS
Interior/Exterior Lathing 8/29/2013 Partial Approval RUBEN SALAS
ELECTRICAL-Rough 8/30/2013 Approved RUBEN SALAS
HVAC-Rough 8/30/2013 Approved RUBEN SALAS
Insulation 8/30/2013 Partial Approval RUBEN SALAS
PLUMBING-Rough 8/30/2013 Approved RUBEN SALAS
Interior/Exterior Lathing 9/9/2013 Approved RUBEN SALAS
Drywall Nailing 9/16/2013 Approved DOMINIC DANERI
Interior/Exterior Lathing 9/30/2013 Approved RUBEN SALAS
BUILDING-Rough-Frame 11/5/2013 Not Ready for Inspection RUBEN SALAS
BUILDING-Rough-Frame 11/7/2013 Partial Approval RUBEN SALAS
Gas Test 4/11/2014 Approved RUBEN SALAS
HVAC-Final 4/11/2014 Not Ready for Inspection RUBEN SALAS
Green Building Final 4/25/2014 Conditional Approval DONALD CRICHLOW
ELECTRICAL-Final 4/30/2014 Not Ready for Inspection RUBEN SALAS
HVAC-Final 4/30/2014 Not Ready for Inspection RUBEN SALAS
ELECTRICAL-Final 5/2/2014 Not Ready for Inspection RUBEN SALAS
PLUMBING-Final 5/2/2014 Approved RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 6/3/2014 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 8/30/2017 Not Ready for Inspection BRIAN SULLIVAN
Final 8/30/2017 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 8/30/2017 Not Ready for Inspection BRIAN SULLIVAN
Green Building Final 8/30/2017 Not Ready for Inspection BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 8/30/2017 SGSOV Not Ready BRIAN SULLIVAN
Smoke Detectors 8/30/2017 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 12/12/2017 Not Ready for Inspection BRIAN SULLIVAN
Final 12/12/2017 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 12/12/2017 Not Ready for Inspection BRIAN SULLIVAN
Green Building Final 12/12/2017 Not Ready for Inspection BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 12/12/2017 SGSOV Not Ready BRIAN SULLIVAN
Smoke Detectors 12/12/2017 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 2/20/2018 Not Ready for Inspection BRIAN SULLIVAN
Final 2/20/2018 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 2/20/2018 Not Ready for Inspection BRIAN SULLIVAN
Green Building Final 2/20/2018 Not Ready for Inspection BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 2/20/2018 SGSOV Not Ready BRIAN SULLIVAN
Smoke Detectors 2/20/2018 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 2/7/2022 Approved BRIAN SULLIVAN
Final 2/7/2022 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 2/7/2022 Approved BRIAN SULLIVAN
Green Building Final 2/7/2022 Not Ready for Inspection BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 2/7/2022 SGSOV Approved BRIAN SULLIVAN
Smoke Detectors 2/7/2022 Not Ready for Inspection BRIAN SULLIVAN
Special/Order Compliance 7/19/2022 Corrections Issued STUART CHAPMAN
Special/Order Compliance 8/3/2022 Corrections Issued BRIAN SULLIVAN
ELECTRICAL-Rough 8/9/2022 Not Ready for Inspection BRIAN SULLIVAN
Final 8/11/2023 OK to Issue CofO BRIAN SULLIVAN
Green Building Final 8/11/2023 Approved BRIAN SULLIVAN
Smoke Detectors 8/11/2023 Approved BRIAN SULLIVAN