2102 N HOLLY DR 90068

Certificate Information: 2102 N HOLLY DR 90068

Application / Permit
12014-20000-02784
Plan Check / Job No.
B12VN08318
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
7'6" X 9'6" BATHROOM ADDITION TO REAR OF (E) ONE STORY SINGLE FAMILY DWELLING PER WFPP
Permit Issued
Issued on 8/17/2012
Issuing Office
Valley
Current Status
CofO Issued on 4/17/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/8/2012 APPLICANT
Assigned to Plan Check Engineer 8/8/2012 JIN KANG TAN
Corrections Issued 8/8/2012 JIN KANG TAN
Plan Check Approved 8/10/2012 MOHAMMAD FIROUZBAKHT
Issued 8/17/2012 LADBS
CofO in Progress 4/17/2026 CRAIG VAUGHAN
Permit Finaled 4/17/2026 DEROLD HAUFF
CofO Issued 4/17/2026 DEROLD HAUFF
Permit Finaled 4/17/2026 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/8/2012 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/10/2012 LEE GUILBEAUX
Grading Pre-Inspection Cleared 8/10/2012 PATRICK MISCHLICH
VHFHSZ Cleared 8/10/2012 JOHN DALLAS
Public Works-Highway Ded. Cleared 8/10/2012 LEE GUILBEAUX
Public Works-Open Permits Cleared 8/10/2012 LEE GUILBEAUX
Public Works-Sewers Cleared 8/10/2012 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/6/2012 Partial Approval WILLIAM JIMENEZ
Footing/Foundation/Slab 9/17/2012 Approved KEN KUROWSKI
BUILDING-Rough-Frame 10/16/2012 Partial Approval WILLIAM JIMENEZ
Green Building Rough 10/16/2012 Partial Inspection DONALD CRICHLOW
BUILDING-Rough-Frame 12/19/2012 Partial Approval WILLIAM JIMENEZ
Green Building Rough 12/19/2012 Approved DONALD CRICHLOW
Rough-Elec/Plmb/HVAC 12/19/2012 Approved WILLIAM JIMENEZ
Drywall Nailing 2/14/2013 Approved WILLIAM JIMENEZ
BUILDING-Rough-Frame 6/27/2013 Approved ROBERT MINASSIANS
Final 6/27/2013 Corrections Issued ROBERT MINASSIANS
Green Building Final 6/27/2013 Approved DONALD CRICHLOW
SGSOV-Seismic Gas S/O Valve 6/27/2013 SGSOV Not Ready ROBERT MINASSIANS
Smoke Detectors 6/27/2013 Corrections Issued ROBERT MINASSIANS
Final 10/22/2013 Not Ready for Inspection WILLIAM JIMENEZ
SGSOV-Seismic Gas S/O Valve 10/22/2013 SGSOV Not Ready WILLIAM JIMENEZ
Smoke Detectors 10/22/2013 Corrections Issued WILLIAM JIMENEZ
Final 11/1/2021 Not Ready for Inspection BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 11/1/2021 SGSOV Approved BRIAN SULLIVAN
Smoke Detectors 11/1/2021 Partial Approval BRIAN SULLIVAN
Special/Order Compliance 1/24/2022 No Access for Inspection BRIAN SULLIVAN
Final 4/3/2026 Corrections Issued BRIAN SULLIVAN
Smoke Detectors 4/3/2026 Not Ready for Inspection BRIAN SULLIVAN
Final 4/15/2026 OK to Issue CofO CRAIG VAUGHAN
Order to Comply 4/15/2026 Not Required CRAIG VAUGHAN
Pre-Inspection 4/15/2026 Approved CRAIG VAUGHAN
Smoke Detectors 4/15/2026 Approved CRAIG VAUGHAN