10818 N ORION AVE 91345
Certificate Information: 10818 N ORION AVE 91345
- Application / Permit
- 12014-20000-01318
- Plan Check / Job No.
- B12VN04018
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 10'6" X 29'6" (310 SF) ADDITION OF (N) BEDROOM, BATH, LAUNDRY, STORAGE, & EXPAND (E) LIVING ROOM. ADD 6'0" X 26'6" (159 SF) PATIO COVER @ REAR. INTERIOR REMODEL TO RELOCATE KITCHEN. ALL WORK IS PER ENGINEERING.
- Permit Issued
- Issued on 5/17/2012
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/23/2012 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2012 | ALEXANDER SBARDELLATI |
| Corrections Issued | 4/23/2012 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 5/15/2012 | JOSE MENDOZA |
| Plan Check Approved | 5/17/2012 | VICTOR TURCIOS |
| Issued | 5/17/2012 | LADBS |
| CofO in Progress | 2/4/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 2/13/2025 | RUBEN SALAS |
| CofO Issued | 2/13/2025 | RUBEN SALAS |
| Permit Finaled | 2/13/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Miscellaneous | Cleared | 4/26/2012 | RICK TORRES |
| Miscellaneous | Cleared | 4/26/2012 | RICK TORRES |
| Eng Process Fee Ord 176,300 | Cleared | 5/14/2012 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 5/14/2012 | LEE GUILBEAUX |
| Sewer availability | Cleared | 5/14/2012 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hanna, John Fayez; Lic. No.: C71506 | 5140 WHITE OAK AVE 201 ENCINO, CA 91316 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 7/20/2012 | Not Ready for Inspection | DANIEL ORRANTE |
| ELECTRICAL-Rough | 7/20/2012 | Not Ready for Inspection | DANIEL ORRANTE |
| Green Building Rough | 7/20/2012 | Partial Inspection | ROLLIN GETTLE III |
| PLUMBING-Rough | 7/20/2012 | Approved | DANIEL ORRANTE |
| BUILDING-Rough-Frame | 8/24/2012 | Partial Inspection | DANIEL ORRANTE |
| ELECTRICAL-Rough | 8/24/2012 | Approved | DANIEL ORRANTE |
| Green Building Rough | 8/24/2012 | No Access for Inspection | ROLLIN GETTLE III |
| Green Building Rough | 8/27/2012 | No Access for Inspection | ROLLIN GETTLE III |
| Insulation | 8/29/2012 | Approved | DANIEL ORRANTE |
| Drywall Nailing | 8/31/2012 | Not Ready for Inspection | RICHARD DOCKUS |
| Footing/Foundation/Slab | 3/5/2013 | Corrections Issued | DONALD GALLAGHER |
| Footing/Foundation/Slab | 3/11/2013 | Corrections Issued | DONALD GALLAGHER |
| Excavation/Setback/Form/Re-Bar | 3/29/2013 | Partial Approval | TIP WHITING |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2013 | Partial Approval | DONALD GALLAGHER |
| PLUMBING-Rough | 6/27/2013 | Approved | DONALD GALLAGHER |
| Excavation/Setback/Form/Re-Bar | 9/3/2013 | Not Ready for Inspection | KEN KUROWSKI |
| Excavation/Setback/Form/Re-Bar | 9/9/2013 | Corrections Issued | DONALD GALLAGHER |
| BUILDING-Rough-Frame | 10/1/2013 | Corrections Issued | DONALD GALLAGHER |
| Wood Frame | 10/1/2013 | Corrections Issued | DONALD GALLAGHER |
| BUILDING-Rough-Frame | 10/3/2013 | Corrections Issued | DONALD GALLAGHER |
| Insulation | 10/3/2013 | Partial Approval | DONALD GALLAGHER |
| BUILDING-Rough-Frame | 10/9/2013 | Corrections Issued | DONALD GALLAGHER |
| ELECTRICAL-Rough | 11/1/2013 | Approved | DONALD GALLAGHER |
| HVAC-Rough | 11/1/2013 | Approved | DONALD GALLAGHER |
| PLUMBING-Rough | 11/1/2013 | Approved | DONALD GALLAGHER |
| BUILDING-Rough-Frame | 12/6/2013 | Partial Approval | DONALD GALLAGHER |
| Green Building Final | 12/6/2013 | Corrections Issued | ROLLIN GETTLE III |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2013 | Approved | DONALD GALLAGHER |
| Green Building Rough | 12/11/2013 | Partial Inspection | ROLLIN GETTLE III |
| BUILDING-Rough-Frame | 1/8/2014 | Partial Approval | DONALD GALLAGHER |
| Green Building Rough | 1/8/2014 | Approved | ROLLIN GETTLE III |
| Insulation | 1/30/2014 | Approved | DONALD GALLAGHER |
| Drywall Nailing | 2/5/2014 | Approved | DONALD GALLAGHER |
| Final | 3/16/2015 | No Access for Inspection | JOHN KIDWELL |
| Final | 11/5/2024 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 1/14/2025 | Approved | JAVIER RAMOS JR |
| Final | 1/14/2025 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 1/14/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 1/14/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 1/14/2025 | Approved | JAVIER RAMOS JR |
| Final | 2/4/2025 | OK to Issue CofO | JENNIFER RABUCHIN |