321 N AVENUE 65 90042
Certificate Information: 321 N AVENUE 65 90042
- Application / Permit
- 12014-10000-03953
- Plan Check / Job No.
- B12LA13053
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 1ST AND 2ND FLOOR ADDITIONS & REMODEL OF EXISTING SINGLE FAMILY DWELLING. ENCLOSED EXISTING FRONT PORCH. THE EXISTING STRUCTURE IS BEING REMOVED WITH THE EXCEPTION OF A FEW WALLS AND FOOTINGS. THE EXISTING FLOOR AREA IS 660 SF, 1005 BEING ADDED FOR A TOTAL OF 1665 SF.
- Permit Issued
- Issued on 8/2/2017
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/2/2012 | APPLICANT |
| Assigned to Plan Check Engineer | 11/8/2012 | JOHN VASQUEZ |
| Corrections Issued | 11/13/2012 | JOHN VASQUEZ |
| Quality Review Completed | 11/14/2012 | BILL STUTSMAN |
| Building Plans Picked Up | 11/16/2012 | APPLICANT |
| Green Plans Picked Up | 5/8/2013 | APPLICANT |
| Applicant returned to address corrections | 7/12/2017 | JOHN VASQUEZ |
| Plan Check Approved | 8/1/2017 | JOHN VASQUEZ |
| Issued | 8/2/2017 | LADBS |
| CofO in Progress | 8/7/2025 | DAVID WILLIAMS |
| Permit Finaled | 8/10/2025 | DEROLD HAUFF |
| CofO Issued | 8/10/2025 | DEROLD HAUFF |
| Permit Finaled | 8/10/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 5/7/2013 | ROBERT DUFF |
| Roof/Waste drainage to street | Cleared | 5/7/2013 | AVALYN KAMACHI |
| Sewer availability | Cleared | 5/7/2013 | AVALYN KAMACHI |
| Grading Pre-Inspection | Cleared | 3/16/2017 | JOHN VASQUEZ |
| Mailing Labels | Cleared | 3/16/2017 | JOHN VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/18/2017 | CARLA VALLADARES |
| Frnt yard landscape/Water mgmt | Cleared | 5/30/2017 | EDBER MACEDO |
| Green Code | Cleared | 6/7/2017 | JOHN VASQUEZ |
| HPOZ | Cleared | 6/30/2017 | ARIANE BRISKI |
| Miscellaneous | Cleared | 7/25/2017 | DANALYNN DOMINGUEZ |
| ZA Case | Cleared | 7/25/2017 | DANALYNN DOMINGUEZ |
| Low Impact Development | Cleared | 7/27/2017 | RYAN HUDSON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo, Margarito; Lic. No.: S4808 | 1327 LOMA AVE LONG BEACH, CA 90804 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/10/2018 | Corrections Issued | RUBEN SALAS |
| Footing/Foundation/Slab | 3/29/2018 | Not Ready for Inspection | RUBEN SALAS |
| Footing/Foundation/Slab | 4/5/2018 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 7/5/2018 | Partial Approval | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2018 | Approved | ENRIQUE MIRELES |
| Gas Test | 7/5/2018 | Partial Approval | ENRIQUE MIRELES |
| Green Building Rough | 7/5/2018 | Partial Approval | ENRIQUE MIRELES |
| PLUMBING-Rough | 7/5/2018 | Partial Approval | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 8/3/2018 | Not Ready for Inspection | RUBEN SALAS |
| Gas Test | 8/3/2018 | Not Ready for Inspection | RUBEN SALAS |
| PLUMBING-Rough | 8/3/2018 | Not Ready for Inspection | RUBEN SALAS |
| Sewer | 8/3/2018 | Not Ready for Inspection | RUBEN SALAS |
| BUILDING-Rough-Frame | 8/17/2018 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 8/17/2018 | Approved | ENRIQUE MIRELES |
| Gas Test | 8/17/2018 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 8/17/2018 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 8/17/2018 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 8/17/2018 | Approved | ENRIQUE MIRELES |
| Insulation | 8/22/2018 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 9/18/2018 | Approved | ENRIQUE MIRELES |
| Special/Order Compliance | 9/19/2018 | Corrections Issued | RUBEN SALAS |
| Special/Order Compliance | 10/17/2018 | Not Ready for Inspection | ENRIQUE MIRELES |
| Special/Order Compliance | 10/26/2018 | Partial Approval | ENRIQUE MIRELES |
| Special/Order Compliance | 10/26/2018 | Partial Inspection | RUBEN SALAS |
| Final | 3/14/2019 | Not Ready for Inspection | OSVALDO PARAMO |
| Green Building Final | 3/14/2019 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 3/14/2019 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 3/14/2019 | Not Ready for Inspection | OSVALDO PARAMO |
| Special/Order Compliance | 3/14/2019 | Partial Inspection | RUBEN SALAS |
| Pre-Inspection | 3/18/2019 | Not Ready for Inspection | CRAIG VAUGHAN |
| Special/Order Compliance | 3/18/2019 | Partial Inspection | RUBEN SALAS |
| Final | 10/30/2019 | Partial Inspection | CRAIG VAUGHAN |
| Green Building Final | 10/30/2019 | Not Ready for Inspection | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 10/30/2019 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 10/30/2019 | Not Ready for Inspection | CRAIG VAUGHAN |
| Special/Order Compliance | 10/30/2019 | Partial Inspection | RUBEN SALAS |
| Special/Order Compliance | 11/1/2019 | Corrections Issued | RUBEN SALAS |
| Special/Order Compliance | 11/1/2019 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 8/17/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Final | 8/17/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Smoke Detectors | 8/17/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 9/14/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Final | 9/14/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Smoke Detectors | 9/14/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Special/Order Compliance | 3/24/2021 | Corrections Issued | ELMER BLAND |
| ELECTRICAL-Final | 2/6/2023 | Partial Inspection | SCOTT FINNILA |
| Final | 2/6/2023 | Partial Inspection | SCOTT FINNILA |
| Green Building Final | 2/6/2023 | Partial Inspection | SCOTT FINNILA |
| Smoke Detectors | 2/6/2023 | Partial Inspection | SCOTT FINNILA |
| Special/Order Compliance | 2/9/2023 | Order to Comply Issued | CRAIG VAUGHAN |
| Special/Order Compliance | 3/16/2023 | Corrections Issued | CRAIG VAUGHAN |
| Special/Order Compliance | 3/31/2023 | Order to Comply Issued | CRAIG VAUGHAN |
| Pre-Inspection | 8/6/2024 | No Access for Inspection | CRAIG VAUGHAN |
| Special/Order Compliance | 12/9/2024 | Partial Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 4/16/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Wood Frame | 4/16/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| ELECTRICAL-Rough | 4/24/2025 | Approved | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2025 | Approved | DAVID WILLIAMS |
| Deck | 5/12/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2025 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 5/12/2025 | Corrections Issued | DAVID WILLIAMS |
| Interior/Exterior Lathing | 5/16/2025 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 5/29/2025 | Approved | REGINA MENDEZ |
| Final | 7/1/2025 | Corrections Issued | DAVID WILLIAMS |
| Green Building Final | 7/1/2025 | Approved | DAVID WILLIAMS |
| Smoke Detectors | 7/1/2025 | Approved | DAVID WILLIAMS |
| Final | 7/14/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Final | 7/31/2025 | Corrections Issued | DAVID WILLIAMS |
| Service/Power Release | 7/31/2025 | Approved | DAVID WILLIAMS |
| Final | 8/7/2025 | OK to Issue CofO | DAVID WILLIAMS |