706 N LAUSANNE ROAD 90077
Certificate Information: 706 N LAUSANNE ROAD 90077
- Application / Permit
- 12014-10000-03441
- Plan Check / Job No.
- B12LA11297
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION (2,066 SF) OF 2 STY. S.F.D. W/ATTACHED NEW 2 CAR GARAGE (600 SF)
- Permit Issued
- Issued on 3/14/2013
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/25/2012 | APPLICANT |
| Assigned to Plan Check Engineer | 10/5/2012 | SALVADOR QUINTANILLA |
| Corrections Issued | 10/11/2012 | SALVADOR QUINTANILLA |
| Quality Review Completed | 10/22/2012 | ARA SARGSYAN |
| Building Plans Picked Up | 11/2/2012 | APPLICANT |
| Green Plans Picked Up | 11/2/2012 | APPLICANT |
| Applicant returned to address corrections | 2/25/2013 | SALVADOR QUINTANILLA |
| Plan Check Approved | 3/14/2013 | SALVADOR QUINTANILLA |
| Issued | 3/14/2013 | LADBS |
| CofO in Progress | 9/22/2014 | ANTHONY ANDERSON |
| Permit Finaled | 2/14/2022 | DANIEL ORRANTE |
| CofO Issued | 2/14/2022 | DANIEL ORRANTE |
| Permit Finaled | 2/14/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Frnt yard landscape/Water mgmt | Cleared | 1/8/2013 | BRIDGETTE WOOTEN |
| Green Code | Cleared | 1/11/2013 | RUSSELL KELLY |
| Hydrant and Access approval | Cleared | 1/15/2013 | ROBERT DUFF |
| VHFHSZ | Cleared | 1/15/2013 | ROBERT DUFF |
| Low Impact Development | Cleared | 1/24/2013 | AMMAR ELTAWIL |
| BHO/Hillside ordinance | Cleared | 1/25/2013 | WESLEY TANIJIRI |
| BHO/Hillside ordinance | Cleared | 1/25/2013 | WESLEY TANIJIRI |
| BHO/Hillside ordinance | Cleared | 1/25/2013 | WESLEY TANIJIRI |
| BHO/Hillside ordinance | Cleared | 1/25/2013 | WESLEY TANIJIRI |
| Eng Process Fee Ord 176,300 | Cleared | 1/25/2013 | WESLEY TANIJIRI |
| Roof/Waste drainage to street | Cleared | 1/25/2013 | WESLEY TANIJIRI |
| Public Works-Highway Ded. | Cleared | 1/25/2013 | WESLEY TANIJIRI |
| Public Works-Open Permits | Cleared | 1/25/2013 | WESLEY TANIJIRI |
| Public Works-Sewers | Cleared | 1/25/2013 | WESLEY TANIJIRI |
| Excavation more than 5-ft deep | Cleared | 2/25/2013 | CALOSHA APPROVED |
Contact Information
| Architect | Oreck, Kevin Robert; Lic. No.: C23895 | 113 1/2 N LA BREA AVENUE # 114 LOS ANGELES, CA 90036 |
| Contractor | Morrow & Morrow Corporation; Lic. No.: 602075-B | 426 GEORGINA AVENUE SANTA MONICA, CA 90402 |
| Engineer | Chung, Jun Sung; Lic. No.: S2766 | 15909 CARMENIA DR WHITTIER, CA 90603 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/15/2013 | Not Ready for Inspection | RONALD MYRICK |
| Posting Pre-Inspection | 3/18/2013 | Approved | RONALD MYRICK |
| Footing/Foundation/Slab | 4/8/2013 | Partial Inspection | ANTHONY ANDERSON |
| Excavation/Setback/Form/Re-Bar | 5/7/2013 | Not Ready for Inspection | ANTHONY ANDERSON |
| Footing/Foundation/Slab | 5/8/2013 | Partial Approval | ANTHONY ANDERSON |
| Deputy Reinf. Concrete | 5/9/2013 | Approved | ANTHONY ANDERSON |
| Footing/Foundation/Slab | 5/10/2013 | Partial Approval | ANTHONY ANDERSON |
| Deputy Reinf. Concrete | 5/13/2013 | Conditional Approval | ANTHONY ANDERSON |
| Footing/Foundation/Slab | 5/17/2013 | Partial Approval | ANTHONY ANDERSON |
| Deputy Reinf. Concrete | 5/20/2013 | Approved | ANTHONY ANDERSON |
| Excavation/Setback/Form/Re-Bar | 5/20/2013 | Partial Approval | ANTHONY ANDERSON |
| Deputy Reinf. Concrete | 5/28/2013 | Approved | ANTHONY ANDERSON |
| Footing/Foundation/Slab | 5/28/2013 | Partial Approval | ANTHONY ANDERSON |
| PLUMBING-Rough | 6/11/2013 | Partial Approval | ANTHONY ANDERSON |
| Deputy Reinf. Concrete | 7/11/2013 | Conditional Approval | ANTHONY ANDERSON |
| Footing/Foundation/Slab | 7/12/2013 | Partial Approval | ANTHONY ANDERSON |
| ELECTRICAL-Rough | 7/18/2013 | Partial Approval | ANTHONY ANDERSON |
| PLUMBING-Rough | 7/18/2013 | Partial Approval | ANTHONY ANDERSON |
| Footing/Foundation/Slab | 7/24/2013 | Approved | ANTHONY ANDERSON |
| ELECTRICAL-Rough | 8/5/2013 | Partial Approval | ANTHONY ANDERSON |
| PLUMBING-Rough | 8/5/2013 | Partial Approval | ANTHONY ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2013 | Partial Approval | ANTHONY ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2013 | Approved | JOHN LUMB |
| PLUMBING-Rough | 10/2/2013 | Conditional Approval | JOHN REGAN |
| ELECTRICAL-Rough | 10/4/2013 | Approved | JOHN LUMB |
| Green Building Rough | 10/7/2013 | Corrections Issued | MICKEY YAMASHITA |
| HVAC-Rough | 10/7/2013 | Approved | JOHN LUMB |
| BUILDING-Rough-Frame | 10/28/2013 | Approved | ANTHONY ANDERSON |
| Green Building Rough | 10/28/2013 | Approved | MEL KHACHATOURIAN |
| Insulation | 11/4/2013 | Approved | ANTHONY ANDERSON |
| Interior/Exterior Lathing | 11/6/2013 | No Access for Inspection | ANTHONY ANDERSON |
| Interior/Exterior Lathing | 11/7/2013 | Partial Approval | ANTHONY ANDERSON |
| Drywall Nailing | 11/15/2013 | Approved | ANTHONY ANDERSON |
| Interior/Exterior Lathing | 11/19/2013 | Approved | ANTHONY ANDERSON |
| Gas Test | 2/24/2014 | Approved | ANTHONY ANDERSON |
| ELECTRICAL-Final | 4/8/2014 | Approved | ANTHONY ANDERSON |
| HVAC-Final | 4/8/2014 | Approved | ANTHONY ANDERSON |
| PLUMBING-Final | 4/8/2014 | Approved | ANTHONY ANDERSON |
| Final | 5/8/2014 | Corrections Issued | ANTHONY ANDERSON |
| Green Building Final | 5/8/2014 | Corrections Issued | MICKEY YAMASHITA |
| SGSOV-Seismic Gas S/O Valve | 5/8/2014 | SGSOV Approved | ANTHONY ANDERSON |
| Smoke Detectors | 5/8/2014 | Approved | ANTHONY ANDERSON |
| Green Building Final | 6/6/2014 | Approved | RUSSELL KELLY |
| ELECTRICAL-Rough | 7/1/2014 | Partial Inspection | ANTHONY ANDERSON |
| Final | 9/18/2014 | OK to Issue CofO | ANTHONY ANDERSON |