8570 W HEDGES PL 90069

Certificate Information: 8570 W HEDGES PL 90069

Application / Permit
12014-10000-02699
Plan Check / Job No.
B12LA08802
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
THREE STORY SFD WITH ATT. GARAGE (104.5FT X 57FT, 8258SQFT), REMODEL AND ADDITION TO EXISTING TWO STORY WITH BASEMENT.
Permit Issued
Issued on 3/20/2014
Issuing Office
Metro
Current Status
CofO Issued on 12/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/31/2012 APPLICANT
Assigned to Plan Check Engineer 8/9/2012 TSE MING HUANG
Corrections Issued 8/11/2012 TSE MING HUANG
Green Plans Picked Up 8/22/2012 APPLICANT
Quality Review Completed 8/27/2012 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 8/30/2012 APPLICANT
Applicant returned to address corrections 3/27/2013 TSE MING HUANG
Applicant returned to address corrections 4/25/2013 TSE MING HUANG
Applicant returned to address corrections 5/23/2013 TSE MING HUANG
Applicant returned to address corrections 6/25/2013 TSE MING HUANG
Applicant returned to address corrections 7/16/2013 TSE MING HUANG
Applicant returned to address corrections 12/5/2013 TSE MING HUANG
Plan Check Approved 12/23/2013 TSE-MING HUANG
Issued 3/20/2014 LADBS
CofO in Progress 10/14/2022 RAUL BARAJAS
Permit Finaled 12/7/2022 DEROLD HAUFF
CofO Issued 12/7/2022 DEROLD HAUFF
Permit Finaled 12/7/2022 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 8/30/2012 AVALYN KAMACHI
BHO/Hillside ordinance Cleared 8/30/2012 AVALYN KAMACHI
BHO/Hillside ordinance Cleared 8/30/2012 AVALYN KAMACHI
BHO/Hillside ordinance Cleared 8/30/2012 AVALYN KAMACHI
Roof/Waste drainage to street Cleared 8/30/2012 AVALYN KAMACHI
Sewer availability Cleared 8/30/2012 AVALYN KAMACHI
VHFHSZ Cleared 9/19/2012 JOSEPH JACKSON
BHO/Hillside ordinance Cleared 10/26/2012 AVALYN KAMACHI
Eng Process Fee Ord 176,300 Cleared 10/26/2012 JAMES MORALEZ
Grading Pre-Inspection Cleared 10/31/2012 TSE-MING HUANG
Green Code Cleared 6/10/2013 MARTHA DIAZ
Hydrant and Access approval Cleared 6/10/2013 ROBERT DUFF
Low Impact Development Cleared 7/8/2013 KOSTA KAPORIS
Stormwater Pollution Mitigatn Cleared 7/8/2013 KOSTA KAPORIS
ZI Cleared 3/19/2014 MARITZA PRZEKOP

Contact Information

Contractor Owner-Builder       ,
Engineer Mahn, Jonathan Edward; Lic. No.: C60293 12848 FOOTHILL BLVD      SYLMAR, CA 91381
Engineer Pirbadian, Amir; Lic. No.: C72413 5435 BALBOA BLVD 212      ENCINO, CA 91436
Geologist Bovenizer, Ernest; Lic. No.: EG2515 7622 GODDARD AVENUE      LOS ANGELES, CA 90045

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/8/2014 Approved BRAD BESCOS
Light Gage Steel Frame 11/25/2015 Not Ready for Inspection BRAD BESCOS
Piling/Pier/Caisson 12/30/2015 Partial Approval BRAD BESCOS
Special/Order Compliance 12/30/2015 Corrections Issued BRAD BESCOS
Footing/Foundation/Slab 2/1/2016 Corrections Issued BRAD BESCOS
Footing/Foundation/Slab 2/3/2016 No Access for Inspection BRAD BESCOS
Footing/Foundation/Slab 2/23/2016 Conditional Approval BRAD BESCOS
Footing/Foundation/Slab 3/18/2016 Corrections Issued BRAD BESCOS
Excavation/Setback/Form/Re-Bar 4/14/2016 Partial Approval BRAD BESCOS
Footing/Foundation/Slab 4/26/2016 Partial Approval BRAD BESCOS
Deputy Reinf. Concrete 4/27/2016 No Access for Inspection BRAD BESCOS
Footing/Foundation/Slab 6/9/2016 Partial Approval BRAD BESCOS
Excavation/Setback/Form/Re-Bar 7/27/2016 Partial Approval LUIS ALVAREZ
Underground Mechanical 8/23/2016 Partial Approval BRAD BESCOS
Excavation/Setback/Form/Re-Bar 9/26/2016 Partial Approval BRAD BESCOS
Excavation/Setback/Form/Re-Bar 10/26/2016 Partial Approval BRAD BESCOS
Excavation/Setback/Form/Re-Bar 10/27/2016 Partial Approval JOEL WILLIAMS
Deputy Reinf. Concrete 11/1/2016 Approved BRAD BESCOS
Excavation/Setback/Form/Re-Bar 12/2/2016 Corrections Issued BRAD BESCOS
Footing/Foundation/Slab 12/5/2016 Partial Approval JOEL WILLIAMS
Excavation/Setback/Form/Re-Bar 12/8/2016 Partial Approval BRAD BESCOS
Footing/Foundation/Slab 12/8/2016 Not Ready for Inspection BRAD BESCOS
Excavation/Setback/Form/Re-Bar 12/21/2016 Partial Approval JOEL WILLIAMS
Deputy Shotcrete 12/23/2016 No Access for Inspection BRAD BESCOS
Excavation/Setback/Form/Re-Bar 12/27/2016 Partial Approval JOEL WILLIAMS
Masonry Wall/Backfill 12/27/2016 Partial Approval JOEL WILLIAMS
Excavation/Setback/Form/Re-Bar 12/28/2016 Not Ready for Inspection BRAD BESCOS
Deputy Shotcrete 12/29/2016 No Access for Inspection BRAD BESCOS
PLUMBING-Rough 1/19/2017 Partial Approval JOEL WILLIAMS
Excavation/Setback/Form/Re-Bar 2/7/2017 Partial Approval BRAD BESCOS
Excavation/Setback/Form/Re-Bar 3/3/2017 Partial Approval BRAD BESCOS
Footing/Foundation/Slab 3/22/2017 Partial Approval JOEL WILLIAMS
Special/Order Compliance 3/22/2017 Corrections Issued JOEL WILLIAMS
Deputy Reinf. Concrete 3/24/2017 No Access for Inspection JOEL WILLIAMS
PLUMBING-Rough 5/16/2017 Partial Approval BRAD BESCOS
Excavation/Setback/Form/Re-Bar 5/25/2017 Conditional Approval JOEL WILLIAMS
Deputy Steel/Welding 6/2/2017 No Access for Inspection JOEL WILLIAMS
Pre-Inspection 6/21/2017 Partial Approval JOEL WILLIAMS
BUILDING-Rough-Frame 6/26/2017 Partial Approval JOEL WILLIAMS
Green Building Rough 6/26/2017 Not Ready for Inspection JOEL WILLIAMS
Verify Sprinkler Sign Off 6/26/2017 Not Ready for Inspection JOEL WILLIAMS
Green Building Rough 7/11/2017 Not Ready for Inspection DANIEL GONZALEZ
Structural Steel Frame 7/11/2017 Partial Approval DANIEL GONZALEZ
Verify Sprinkler Sign Off 7/11/2017 Not Ready for Inspection DANIEL GONZALEZ
Footing/Foundation/Slab 7/21/2017 Partial Approval BRAD BESCOS
PLUMBING-Rough 8/30/2017 Partial Approval BRAD BESCOS
Footing/Foundation/Slab 10/3/2017 No Access for Inspection DANIEL GONZALEZ
Excavation/Setback/Form/Re-Bar 10/4/2017 Partial Approval DANIEL GONZALEZ
Gas Test 11/16/2017 Partial Approval JOEL WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 11/22/2017 Not Ready for Inspection DANIEL GONZALEZ
Footing/Foundation/Slab 12/19/2017 Partial Inspection DANNY TOLENTINO
HVAC-Rough 2/13/2018 Conditional Approval BRAD BESCOS
Shower Pan 2/13/2018 Approved BRAD BESCOS
ELECTRICAL-Rough 2/15/2018 Corrections Issued DANNY TOLENTINO
BUILDING-Rough-Frame 2/23/2018 Corrections Issued DANNY TOLENTINO
Green Building Rough 2/23/2018 Approved DANNY TOLENTINO
PLUMBING-Rough 2/23/2018 Approved DANNY TOLENTINO
Verify Sprinkler Sign Off 2/23/2018 Approved DANNY TOLENTINO
Underground Mechanical 4/10/2018 Partial Approval DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 5/3/2018 Partial Approval DANIEL GONZALEZ
Drywall Nailing 5/8/2018 Partial Approval DANIEL GONZALEZ
BUILDING-Rough-Frame 5/29/2018 Partial Approval DANIEL GONZALEZ
Drywall Nailing 6/7/2018 Conditional Approval BRAD BESCOS
Excavation/Setback/Form/Re-Bar 6/7/2018 Corrections Issued BRAD BESCOS
Interior/Exterior Lathing 6/7/2018 Not Ready for Inspection BRAD BESCOS
Interior/Exterior Lathing 6/13/2018 Not Ready for Inspection DANIEL GONZALEZ
ELECTRICAL-Rough 6/15/2018 Approved DANIEL GONZALEZ
HVAC-Rough 6/15/2018 Approved DANIEL GONZALEZ
Interior/Exterior Lathing 6/15/2018 Partial Approval DANIEL GONZALEZ
Enclosure/Fence 7/10/2018 Not Ready for Inspection DANIEL GONZALEZ
Excavation/Setback/Form/Re-Bar 8/21/2018 Corrections Issued DANIEL GONZALEZ
Excavation/Setback/Form/Re-Bar 10/17/2018 Corrections Issued ROBERT MINASSIANS
Reinforced Masonry Frame 10/17/2018 Corrections Issued ROBERT MINASSIANS
Excavation/Setback/Form/Re-Bar 10/18/2018 Partial Approval DANIEL GONZALEZ
Excavation/Setback/Form/Re-Bar 10/25/2018 Partial Approval JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 11/6/2018 Partial Inspection DANIEL GONZALEZ
Footing/Foundation/Slab 11/6/2018 Partial Inspection DANIEL GONZALEZ
Deputy Reinf. Concrete 11/19/2018 No Access for Inspection DANIEL GONZALEZ
Excavation/Setback/Form/Re-Bar 11/20/2018 Partial Approval DANIEL GONZALEZ
Service/Power Release 12/27/2019 Corrections Issued RAUL BARAJAS
Service/Power Release 1/6/2020 Corrections Issued RAUL BARAJAS
Service/Power Release 12/3/2020 Approved RICHARD STEINBACH
BUILDING-Rough-Frame 3/11/2022 Approved RAUL BARAJAS
ELECTRICAL-Final 3/11/2022 Not Ready for Inspection RAUL BARAJAS
Final 3/11/2022 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 3/11/2022 Approved RAUL BARAJAS
Green Building Final 3/11/2022 Not Ready for Inspection RAUL BARAJAS
HVAC-Final 3/11/2022 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Final 3/11/2022 Not Ready for Inspection RAUL BARAJAS
Reinforced Concrete Frame 3/11/2022 Approved RAUL BARAJAS
Reinforced Masonry Frame 3/11/2022 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 3/11/2022 SGSOV Not Ready RAUL BARAJAS
Smoke Detectors 3/11/2022 Not Ready for Inspection RAUL BARAJAS
Structural Steel Frame 3/11/2022 Approved RAUL BARAJAS
Final 9/1/2022 Conditional Approval RAUL BARAJAS
Green Building Final 9/1/2022 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 9/1/2022 SGSOV Approved RAUL BARAJAS
Smoke Detectors 9/1/2022 Approved RAUL BARAJAS
HVAC-Final 9/13/2022 Approved RAUL BARAJAS
PLUMBING-Final 9/13/2022 Approved RAUL BARAJAS