2332 S PROSSER AVE 90064

Certificate Information: 2332 S PROSSER AVE 90064

Application / Permit
12010-30000-02840
Plan Check / Job No.
B12WL03498
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
TWO CAR GARAGE WITH ATTACHED LAUNDRY ROOM.
Permit Issued
Issued on 2/26/2013
Issuing Office
West Los Angeles
Current Status
Issued on 2/26/2013
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/13/2012 APPLICANT
Assigned to Plan Check Engineer 12/20/2012 RUDOLF KINAR MELIKOFF
Corrections Issued 12/22/2012 RUDOLF KINAR MELIKOFF
Quality Review Completed 12/26/2012 ARA SARGSYAN
Building Plans Picked Up 1/4/2013 APPLICANT
Green Plans Picked Up 1/4/2013 APPLICANT
Applicant returned to address corrections 2/5/2013 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 2/7/2013 RUDOLF KINAR MELIKOFF
Plan Check Approved 2/19/2013 RUDOLF KINAR MELIKOFF
Issued 2/26/2013 LADBS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/9/2013 KATHLEEN HUGHEY
Roof/Waste drainage to street Cleared 1/9/2013 KATHLEEN HUGHEY
Green Code Cleared 1/16/2013 MEL KHACHATOURIAN
Construction near power lines Cleared 1/28/2013 LUCIO FERRER
Construction within easement Cleared 1/28/2013 LUCIO FERRER
Grading Pre-Inspection Cleared 2/5/2013 JOHN KITCKO
Low Impact Development Cleared 2/5/2013 IDA MEISAMI-FARD

Contact Information

Architect Burdick, Craig Stewart; Lic. No.: C22882 1030 DE LA VINA ST      SANTA BARBARA, CA 93101
Contractor Estrin/Hinds Construction Co Inc; Lic. No.: 721024-B 29170 HEATHERCLIFF RD STE C      MALIBU, CA 90265
Engineer Lambe, Michael Kevin; Lic. No.: S2965 PO BOX 92129      SANTA BARBARA, CA 931902129

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/14/2013 Approved BRUCE ROZAK
Footing/Foundation/Slab 3/22/2013 Partial Approval BRUCE ROZAK
METHANE-Barrier 3/22/2013 Not Ready for Inspection BRUCE ROZAK
METHANE-Subgrade 3/22/2013 Conditional Approval BRUCE ROZAK
Footing/Foundation/Slab 3/27/2013 Not Ready for Inspection BRUCE ROZAK
METHANE-Barrier 3/27/2013 Approved BRUCE ROZAK
METHANE-Subgrade 3/27/2013 Approved BRUCE ROZAK
Deputy Methane Barrier 4/2/2013 Approved BRUCE ROZAK
PLUMBING-Rough 4/2/2013 Approved BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 4/8/2013 Partial Inspection EDWARD GOMEZ
ELECTRICAL-Rough 4/12/2013 Corrections Issued ANTHONY ANDERSON
BUILDING-Rough-Frame 4/22/2013 Partial Inspection EDWARD GOMEZ
ELECTRICAL-Rough 4/22/2013 Partial Inspection EDWARD GOMEZ
PLUMBING-Rough 4/22/2013 Partial Inspection EDWARD GOMEZ
Green Building Rough 4/25/2013 Not Ready for Inspection MEL KHACHATOURIAN
METHANE-Rough 4/25/2013 Approved EDWARD GOMEZ
PLUMBING-Rough 4/25/2013 Approved EDWARD GOMEZ
BUILDING-Rough-Frame 5/10/2013 Approved EDWARD GOMEZ
ELECTRICAL-Rough 5/10/2013 Partial Inspection EDWARD GOMEZ
Green Building Rough 5/10/2013 Approved MICKEY YAMASHITA
Interior/Exterior Lathing 5/14/2013 Partial Approval EDWARD GOMEZ
Insulation 5/15/2013 Approved EDWARD GOMEZ
Drywall Nailing 5/17/2013 Approved ROBERT WALLEN
Final 11/8/2013 Not Ready for Inspection JOHN LUMB
Footing/Foundation/Slab 11/8/2013 Approved JOHN LUMB
Green Building Final 11/8/2013 Approved MICKEY YAMASHITA
SGSOV-Seismic Gas S/O Valve 11/8/2013 SGSOV Approved JOHN LUMB
Smoke Detectors 11/8/2013 Approved JOHN LUMB
Pre-Inspection 5/27/2021 Approved GERMAN RODRIGUEZ MENDOZA
Pre-Inspection 6/15/2021 Approved GERMAN RODRIGUEZ MENDOZA
Final 7/7/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 12/9/2021 Corrections Issued BRENDAN LOONEY
PLUMBING-Rough 12/29/2021 Not Ready for Inspection BRENDAN LOONEY
Special/Order Compliance 12/29/2021 Corrections Issued BRENDAN LOONEY
Footing/Foundation/Slab 12/30/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA