1027 W WILSHIRE BLVD 90017

Certificate Information: 1027 W WILSHIRE BLVD 90017

Application / Permit
12010-10000-01448
Plan Check / Job No.
B12LA07023
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Construct 9-story (over 2-story basement) live work containing 376-units including 3-level garage with office and neighborhood retail (retail for core and shell only).
Permit Issued
Issued on 3/31/2015
Issuing Office
Metro
Current Status
Issued on 3/31/2015
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/3/2012 APPLICANT
Assigned to Plan Check Engineer 7/12/2012 CHARLES CHANG
Corrections Issued 7/16/2012 CHARLES CHANG
Quality Review Completed 7/16/2012 COLIN KUMABE
Building Plans Picked Up 7/17/2012 APPLICANT
Applicant returned to address corrections 4/8/2013 CHARLES CHANG
Plan Check Approved 3/10/2015 CHARLES CHANG
No Progress 3/10/2015 CHARLES CHANG
Plan Check Approved 3/10/2015 CHARLES CHANG
Issued 3/31/2015 LADBS
Permit Expired-Status Void 4/25/2017 APPLICANT
Re-Activate Permit 9/15/2017 SAKO AGHAZARIAN
TCO Issued (Expire Date: 02-27-2022) 8/31/2021 ERNESTO CORRAL
TCO Issued (Expire Date: 08-27-2022) 2/28/2022 TED RIES
TCO Issued (Expire Date: 02-13-2023) 8/17/2022 ERNESTO CORRAL
TCO Issued (Expire Date: 08-16-2023) 2/17/2023 TERRY HERR
TCO Issued (Expire Date: 01-24-2024) 7/28/2023 TED RIES
TCO Issued (Expire Date: 07-22-2024) 1/24/2024 ERNESTO CORRAL
TCO Issued (Expire Date: 01-13-2025) 7/17/2024 ERNESTO CORRAL
TCO Issued (Expire Date: 07-14-2025) 1/15/2025 ADAM BURGESS
TCO Issued (Expire Date: 01-10-2026) 7/14/2025 ERNESTO CORRAL
TCO Issued (Expire Date: 06-22-2026) 12/24/2025 ERNESTO CORRAL
TCO Issued (Expire Date: 12-19-2026) 6/22/2026 RAFAEL ESPINOZA

Permit Application Clearance Information

Grading in hillside Cleared 9/18/2012 HERMAN VAN BUREN
Grading in hillside Cleared 9/18/2012 HERMAN VAN BUREN
APC Cleared 9/20/2012 MARITZA PRZEKOP
Address approval Cleared 9/20/2012 DAVID CHIN
Eng Process Fee Ord 176,300 Cleared 9/20/2012 ARMENIA HERNANDEZ
Miscellaneous Cleared 9/20/2012 MARITZA PRZEKOP
Roof/Waste drainage to street Cleared 10/9/2012 JAMES MORALEZ
Encroachment in public way Cleared 10/18/2012 ARMENIA HERNANDEZ
Highway dedication Cleared 10/18/2012 ARMENIA HERNANDEZ
Permit Cleared 1/10/2013 ARMENIA HERNANDEZ
Stormwater Pollution Mitigatn Cleared 2/20/2013 AYMAN JABBOURI
Stormwater Pollution Mitigatn Cleared 2/20/2013 AYMAN JABBOURI
Hydrant and Access approval Cleared 2/26/2013 JOHN DALLAS
Driveway location Cleared 3/13/2013 TAIMOUR TANAVOLI
Internal circulation Cleared 3/13/2013 TAIMOUR TANAVOLI
Title 19 building approval Cleared 5/2/2013 DAVE MYERS
Building over 3-story or 35-ft Cleared 5/8/2013 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 5/8/2013 CALOSHA APPROVED
Grading Pre-Inspection Cleared 5/8/2013 CHARLES CHANG
CEQA clearance Cleared 6/25/2013 MARITZA PRZEKOP
Frnt yard landscape/Water mgmt Cleared 6/25/2013 MARITZA PRZEKOP
Miscellaneous Cleared 6/25/2013 MARITZA PRZEKOP
Opn space landscape/Water mgmt Cleared 6/25/2013 MARITZA PRZEKOP
Prkng lot landscape/Water mgmt Cleared 6/25/2013 MARITZA PRZEKOP
Specific Plan Cleared 6/25/2013 MARITZA PRZEKOP
Specific Plan Cleared 6/25/2013 MARITZA PRZEKOP
Tract Map conditions Cleared 6/25/2013 MARITZA PRZEKOP
ZA Case Cleared 6/25/2013 MARITZA PRZEKOP
DAS Clearance Cleared 7/16/2013 WAI LAU
Sewer availability Cleared 7/29/2013 ARMENIA HERNANDEZ
Work Adjacent to Public Way Cleared 8/27/2013 TERRY PHAN
Green Code Cleared 10/29/2014 ALDO UBAU
APC Cleared 2/3/2015 MARITZA PRZEKOP
Site Plan review Cleared 2/3/2015 MARITZA PRZEKOP
ZI Cleared 2/3/2015 MARITZA PRZEKOP
DAS Clearance Cleared 2/9/2015 CHARLES CHANG
Low Impact Development Cleared 2/9/2015 AYMAN JABBOURI
Fire Marshall Fire Life Safety Cleared 2/13/2015 DAVE MYERS
Public Swimming Pool approval Cleared 3/10/2015 LACDHS APPROVED

Contact Information

Architect Armandpour, Bijan; Lic. No.: C15034 6399 WILSHIRE BLVD SUITE 105      LOS ANGELES, CA 90048
Contractor Macrocons Inc; Lic. No.: 832326-B 370 CONVENTION WAY      REDWOOD CITY, CA 94063
Engineer Youssef, Nabih Fouad Guirg; Lic. No.: S2026 550 S HOPE ST SUITE 1700      LOS ANGELES, CA 90017

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 3/30/2017 Approved SAKO AGHAZARIAN
Pre-Inspection 9/27/2017 Approved SAKO AGHAZARIAN
Excavation/Setback/Form/Re-Bar 3/14/2018 Partial Inspection LESLIE TRUJILLO
Piling/Pier/Caisson 3/14/2018 Partial Inspection LESLIE TRUJILLO
Pre-Inspection 3/14/2018 Approved LESLIE TRUJILLO
Deputy Grading 4/30/2018 Conditional Approval LESLIE TRUJILLO
Deputy Grading 5/1/2018 Conditional Approval LESLIE TRUJILLO
Deputy Grading 5/2/2018 Conditional Approval LESLIE TRUJILLO
Deputy Grading 5/3/2018 Conditional Approval LESLIE TRUJILLO
Deputy Grading 5/4/2018 Partial Approval JAMES POWERS
Deputy Grading 5/14/2018 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 5/14/2018 Partial Approval LESLIE TRUJILLO
Deputy Grading 5/15/2018 Conditional Approval LESLIE TRUJILLO
Deputy Grading 5/16/2018 Conditional Approval LESLIE TRUJILLO
Deputy Grading 5/17/2018 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 5/17/2018 Partial Approval LESLIE TRUJILLO
Deputy Grading 5/18/2018 Conditional Approval LESLIE TRUJILLO
Deputy Grading 5/21/2018 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 5/21/2018 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 5/21/2018 Partial Approval LESLIE TRUJILLO
Deputy Grading 5/22/2018 Conditional Approval LESLIE TRUJILLO
Deputy Grading 5/23/2018 Conditional Approval LESLIE TRUJILLO
Deputy Grading 5/24/2018 Conditional Approval LESLIE TRUJILLO
Deputy Grading 5/25/2018 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 5/31/2018 Conditional Approval LESLIE TRUJILLO
Excavation/Setback/Form/Re-Bar 5/31/2018 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 5/31/2018 Partial Approval LESLIE TRUJILLO
Excavation/Setback/Form/Re-Bar 6/4/2018 Partial Approval WINSTON DUNNING
Footing/Foundation/Slab 6/8/2018 Partial Approval WINSTON DUNNING
Deputy Reinf. Concrete 6/11/2018 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 6/15/2018 Conditional Approval WINSTON DUNNING
Footing/Foundation/Slab 6/15/2018 Partial Approval WINSTON DUNNING
Deputy Reinf. Concrete 6/19/2018 Conditional Approval LESLIE TRUJILLO
Green Building Rough 7/10/2018 Partial Inspection LESLIE TRUJILLO
Reinforced Concrete Frame 7/10/2018 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 7/10/2018 Partial Inspection LESLIE TRUJILLO
Deputy Reinf. Concrete 7/12/2018 Conditional Approval LESLIE TRUJILLO
Green Building Rough 7/12/2018 Partial Inspection LESLIE TRUJILLO
Reinforced Concrete Frame 7/12/2018 Partial Inspection LESLIE TRUJILLO
Verify Sprinkler Sign Off 7/12/2018 Partial Inspection LESLIE TRUJILLO
Deputy Shotcrete 7/13/2018 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 7/16/2018 Conditional Approval LESLIE TRUJILLO
Green Building Rough 7/16/2018 Partial Inspection LESLIE TRUJILLO
Reinforced Concrete Frame 7/16/2018 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 7/16/2018 Partial Inspection LESLIE TRUJILLO
Deputy Shotcrete 7/17/2018 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 7/18/2018 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 7/19/2018 Conditional Approval LESLIE TRUJILLO
Green Building Rough 7/23/2018 Partial Inspection LESLIE TRUJILLO
Reinforced Concrete Frame 7/23/2018 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 7/23/2018 Partial Inspection LESLIE TRUJILLO
Deputy Reinf. Concrete 7/24/2018 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 7/24/2018 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 7/24/2018 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 7/25/2018 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 7/25/2018 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 7/26/2018 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 7/27/2018 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 7/27/2018 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 7/30/2018 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 8/3/2018 Conditional Approval LESLIE TRUJILLO
Green Building Rough 8/3/2018 Partial Inspection LESLIE TRUJILLO
Reinforced Concrete Frame 8/3/2018 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 8/3/2018 Partial Inspection LESLIE TRUJILLO
Deputy Reinf. Concrete 8/7/2018 Conditional Approval LESLIE TRUJILLO
Piling/Pier/Caisson 8/7/2018 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/8/2018 Conditional Approval LESLIE TRUJILLO
Deputy Grading 8/17/2018 Conditional Approval LESLIE TRUJILLO
Deputy Grading 8/23/2018 Conditional Approval LESLIE TRUJILLO
Deputy Grading 8/24/2018 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/29/2018 Conditional Approval LESLIE TRUJILLO
Green Building Rough 8/29/2018 Conditional Approval LESLIE TRUJILLO
Piling/Pier/Caisson 8/29/2018 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 8/29/2018 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 8/29/2018 Conditional Approval LESLIE TRUJILLO
Deputy Grading 8/30/2018 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/30/2018 Conditional Approval LESLIE TRUJILLO
Deputy Grading 8/31/2018 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 8/31/2018 Partial Inspection LESLIE TRUJILLO
Footing/Foundation/Slab 9/7/2018 Partial Approval LESLIE TRUJILLO
Piling/Pier/Caisson 9/10/2018 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/11/2018 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 9/12/2018 Partial Approval LESLIE TRUJILLO
Green Building Rough 9/13/2018 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 9/13/2018 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 9/13/2018 Conditional Approval LESLIE TRUJILLO
Deputy Grading 9/14/2018 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/17/2018 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 9/17/2018 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/18/2018 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/20/2018 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 9/20/2018 Partial Approval LESLIE TRUJILLO
Deputy Shotcrete 9/26/2018 Partial Approval LESLIE TRUJILLO
Deputy Shotcrete 9/27/2018 Conditional Approval WINSTON DUNNING
Footing/Foundation/Slab 9/27/2018 Not Ready for Inspection WINSTON DUNNING
Green Building Rough 9/28/2018 Partial Inspection LESLIE TRUJILLO
Reinforced Concrete Frame 9/28/2018 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 9/28/2018 Partial Inspection LESLIE TRUJILLO
Deputy Shotcrete 10/1/2018 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 10/2/2018 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 10/3/2018 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 10/4/2018 Partial Approval LESLIE TRUJILLO
Green Building Rough 10/4/2018 Partial Inspection LESLIE TRUJILLO
Reinforced Concrete Frame 10/4/2018 Partial Approval LESLIE TRUJILLO
Reinforced Masonry Frame 10/4/2018 Partial Inspection LESLIE TRUJILLO
Verify Sprinkler Sign Off 10/4/2018 Partial Inspection LESLIE TRUJILLO
Deputy Reinf. Concrete 10/5/2018 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/9/2018 Conditional Approval LESLIE TRUJILLO
Green Building Rough 10/9/2018 Partial Inspection LESLIE TRUJILLO
Reinforced Concrete Frame 10/9/2018 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 10/9/2018 Partial Inspection LESLIE TRUJILLO
Deputy Reinf. Concrete 10/10/2018 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/11/2018 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 10/11/2018 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/12/2018 Conditional Approval LESLIE TRUJILLO
Piling/Pier/Caisson 10/12/2018 Partial Approval LESLIE TRUJILLO
Deputy Shotcrete 10/15/2018 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 10/18/2018 Conditional Approval LESLIE TRUJILLO
Green Building Rough 10/18/2018 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 10/18/2018 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 10/18/2018 Not Ready for Inspection LESLIE TRUJILLO
Deputy Shotcrete 10/19/2018 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 10/19/2018 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/22/2018 Conditional Approval LESLIE TRUJILLO
Green Building Rough 10/23/2018 Partial Inspection LESLIE TRUJILLO
Reinforced Concrete Frame 10/23/2018 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 10/23/2018 Partial Inspection LESLIE TRUJILLO
Footing/Foundation/Slab 10/24/2018 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/25/2018 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/26/2018 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/29/2018 Conditional Approval LESLIE TRUJILLO
Green Building Rough 10/29/2018 Partial Inspection LESLIE TRUJILLO
Reinforced Concrete Frame 10/29/2018 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 10/29/2018 Partial Inspection LESLIE TRUJILLO
Deputy Reinf. Concrete 11/13/2018 Conditional Approval LESLIE TRUJILLO
Green Building Rough 11/14/2018 Partial Inspection LESLIE TRUJILLO
Reinforced Concrete Frame 11/14/2018 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 11/14/2018 Partial Inspection LESLIE TRUJILLO
Deputy Reinf. Concrete 11/15/2018 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/16/2018 Conditional Approval LESLIE TRUJILLO
Green Building Rough 11/21/2018 Partial Inspection LESLIE TRUJILLO
Reinforced Concrete Frame 11/21/2018 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 11/21/2018 Partial Inspection LESLIE TRUJILLO
Footing/Foundation/Slab 11/30/2018 Partial Inspection LESLIE TRUJILLO
Deputy Reinf. Concrete 12/5/2018 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 12/5/2018 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 12/7/2018 Not Ready for Inspection LESLIE TRUJILLO
Green Building Rough 12/7/2018 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 12/7/2018 Not Ready for Inspection LESLIE TRUJILLO
Verify Sprinkler Sign Off 12/7/2018 Partial Approval LESLIE TRUJILLO
Piling/Pier/Caisson 12/8/2018 Corrections Issued LESLIE TRUJILLO
Green Building Rough 12/11/2018 Not Ready for Inspection LESLIE TRUJILLO
Reinforced Concrete Frame 12/11/2018 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 12/11/2018 Partial Inspection LESLIE TRUJILLO
Green Building Rough 12/13/2018 Approved LESLIE TRUJILLO
Reinforced Concrete Frame 12/13/2018 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 12/13/2018 Approved LESLIE TRUJILLO
Footing/Foundation/Slab 12/18/2018 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 12/21/2018 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 12/21/2018 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 12/27/2018 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 12/28/2018 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/3/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 1/3/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 1/4/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 1/9/2019 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 1/10/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 1/11/2019 Partial Approval LESLIE TRUJILLO
Excavation/Setback/Form/Re-Bar 1/15/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 1/18/2019 Not Ready for Inspection LESLIE TRUJILLO
Reinforced Concrete Frame 1/21/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 1/23/2019 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 1/23/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/25/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 1/25/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/28/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/29/2019 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 1/29/2019 Corrections Issued LESLIE TRUJILLO
Deputy Reinf. Concrete 1/30/2019 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 1/30/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 1/30/2019 Not Ready for Inspection LESLIE TRUJILLO
Reinforced Concrete Frame 1/31/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 2/1/2019 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 2/1/2019 Partial Inspection LESLIE TRUJILLO
Footing/Foundation/Slab 2/4/2019 No Access for Inspection LESLIE TRUJILLO
Reinforced Concrete Frame 2/5/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 2/13/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 2/15/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 2/15/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 2/19/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 2/22/2019 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 2/27/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 2/28/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 3/8/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 3/12/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 3/12/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 3/13/2019 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 3/18/2019 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 3/21/2019 Partial Approval LESLIE TRUJILLO
Deputy Shotcrete 3/22/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 3/27/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 4/1/2019 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 4/2/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 4/8/2019 Not Ready for Inspection LESLIE TRUJILLO
Deputy Reinf. Concrete 4/9/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 4/9/2019 Partial Approval LESLIE TRUJILLO
Piling/Pier/Caisson 4/10/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 4/11/2019 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 4/17/2019 Partial Inspection LESLIE TRUJILLO
Reinforced Concrete Frame 4/18/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/23/2019 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 4/23/2019 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 4/24/2019 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 4/29/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 4/30/2019 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 5/2/2019 Partial Approval TED RIES
Footing/Foundation/Slab 5/3/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/6/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 5/7/2019 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 5/8/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 5/14/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 5/21/2019 Partial Approval JAMES POWERS
Footing/Foundation/Slab 5/24/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 5/24/2019 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 5/28/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 5/29/2019 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 5/30/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 5/31/2019 Conditional Approval LESLIE TRUJILLO
Light Gage Steel Frame 5/31/2019 Partial Inspection LESLIE TRUJILLO
Reinforced Concrete Frame 6/5/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 6/10/2019 Partial Inspection LESLIE TRUJILLO
Footing/Foundation/Slab 6/11/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 6/12/2019 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 6/12/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 6/20/2019 Conditional Approval LESLIE TRUJILLO
Excavation/Setback/Form/Re-Bar 6/21/2019 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 6/24/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 6/24/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 6/28/2019 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 7/2/2019 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 7/3/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 7/3/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 7/9/2019 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 7/12/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 7/18/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 7/22/2019 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 7/23/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 7/24/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 7/26/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 8/1/2019 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 8/5/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 8/6/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/7/2019 Conditional Approval LESLIE TRUJILLO
Insulation 8/9/2019 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 8/9/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/12/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/13/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/14/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/15/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 8/15/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 8/20/2019 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 8/28/2019 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 9/3/2019 Partial Inspection LESLIE TRUJILLO
Reinforced Concrete Frame 9/4/2019 Partial Inspection LESLIE TRUJILLO
Deputy Reinf. Concrete 9/10/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 9/11/2019 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 9/12/2019 Partial Inspection LESLIE TRUJILLO
Reinforced Concrete Frame 9/12/2019 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 9/13/2019 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 9/19/2019 Partial Inspection LESLIE TRUJILLO
Reinforced Concrete Frame 9/19/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/24/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 10/1/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 10/4/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/10/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 10/10/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 10/10/2019 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 10/15/2019 Partial Approval JAMES POWERS
Reinforced Concrete Frame 10/16/2019 Partial Approval JAMES POWERS
Reinforced Concrete Frame 10/17/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/18/2019 Approved JEFF BYTHEWAY
Light Gage Steel Frame 10/23/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 10/24/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/25/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 10/28/2019 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 10/28/2019 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 10/31/2019 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 11/4/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/6/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 11/14/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/15/2019 Conditional Approval LESLIE TRUJILLO
Light Gage Steel Frame 11/18/2019 Not Ready for Inspection LESLIE TRUJILLO
Reinforced Concrete Frame 11/18/2019 Corrections Issued LESLIE TRUJILLO
Deputy Reinf. Concrete 11/19/2019 Conditional Approval LESLIE TRUJILLO
Interior/Exterior Lathing 11/25/2019 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 11/25/2019 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 12/11/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 12/12/2019 Partial Approval LESLIE TRUJILLO
Deputy Steel/Welding 12/13/2019 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 12/17/2019 Conditional Approval LESLIE TRUJILLO
Light Gage Steel Frame 12/19/2019 Partial Approval LESLIE TRUJILLO
Deputy Steel/Welding 12/31/2019 Conditional Approval LESLIE TRUJILLO
Light Gage Steel Frame 1/3/2020 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 1/6/2020 Partial Inspection LESLIE TRUJILLO
Structural Steel Frame 1/6/2020 Partial Inspection LESLIE TRUJILLO
Light Gage Steel Frame 1/17/2020 Partial Approval LESLIE TRUJILLO
Insulation 1/22/2020 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 1/22/2020 Partial Approval LESLIE TRUJILLO
Drywall Nailing 1/28/2020 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 1/28/2020 Partial Approval LESLIE TRUJILLO
Insulation 1/31/2020 Partial Approval LESLIE TRUJILLO
Drywall Nailing 2/6/2020 Partial Approval LESLIE TRUJILLO
Interior/Exterior Lathing 2/7/2020 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 2/7/2020 Partial Inspection LESLIE TRUJILLO
Reinforced Concrete Frame 2/10/2020 Partial Approval LESLIE TRUJILLO
Deputy Steel/Welding 2/11/2020 Conditional Approval LESLIE TRUJILLO
Light Gage Steel Frame 2/12/2020 Partial Approval LESLIE TRUJILLO
Interior/Exterior Lathing 2/13/2020 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 2/14/2020 Partial Approval LESLIE TRUJILLO
Structural Steel Frame 2/19/2020 Partial Approval LESLIE TRUJILLO
Deputy Steel/Welding 2/20/2020 Conditional Approval LESLIE TRUJILLO
Deputy Steel/Welding 2/24/2020 Conditional Approval LESLIE TRUJILLO
Insulation 2/25/2020 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 2/27/2020 Partial Approval RAFAEL ESPINOZA
Insulation 3/4/2020 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 3/4/2020 Partial Approval RAFAEL ESPINOZA
Insulation 3/6/2020 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 3/6/2020 Partial Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 3/6/2020 Partial Approval RAFAEL ESPINOZA
Insulation 3/9/2020 Partial Inspection LESLIE TRUJILLO
Light Gage Steel Frame 3/9/2020 Partial Approval LESLIE TRUJILLO
Drywall Nailing 3/11/2020 Partial Approval LESLIE TRUJILLO
Drywall Nailing 3/16/2020 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 3/16/2020 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 3/18/2020 Partial Approval LESLIE TRUJILLO
Insulation 3/20/2020 Not Ready for Inspection LESLIE TRUJILLO
Reinforced Concrete Frame 3/20/2020 Partial Approval LESLIE TRUJILLO
Insulation 3/25/2020 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 3/26/2020 Partial Inspection LESLIE TRUJILLO
Reinforced Concrete Frame 3/26/2020 Not Ready for Inspection LESLIE TRUJILLO
Footing/Foundation/Slab 3/27/2020 Partial Approval LESLIE TRUJILLO
Drywall Nailing 3/31/2020 Partial Approval LESLIE TRUJILLO
Insulation 4/1/2020 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 4/1/2020 Partial Inspection LESLIE TRUJILLO
Light Gage Steel Frame 4/2/2020 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 4/3/2020 Partial Approval LESLIE TRUJILLO
Insulation 4/6/2020 Partial Approval LESLIE TRUJILLO
Drywall Nailing 4/8/2020 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 4/16/2020 Partial Approval LESLIE TRUJILLO
Drywall Nailing 4/20/2020 Partial Approval LESLIE TRUJILLO
Insulation 4/20/2020 Partial Approval LESLIE TRUJILLO
Drywall Nailing 4/21/2020 Not Ready for Inspection LESLIE TRUJILLO
Light Gage Steel Frame 4/21/2020 Not Ready for Inspection LESLIE TRUJILLO
Drywall Nailing 4/22/2020 Partial Approval LESLIE TRUJILLO
Insulation 4/22/2020 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 4/22/2020 Partial Approval LESLIE TRUJILLO
Drywall Nailing 4/27/2020 Partial Approval LESLIE TRUJILLO
Insulation 4/27/2020 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 4/27/2020 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 4/29/2020 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 5/11/2020 Partial Approval NICK DANERI
Drywall Nailing 5/13/2020 Partial Approval NICK DANERI
Light Gage Steel Frame 5/13/2020 Partial Approval NICK DANERI
Interior/Exterior Lathing 5/15/2020 Partial Approval NICK DANERI
Light Gage Steel Frame 5/18/2020 Not Ready for Inspection NICK DANERI
Drywall Nailing 5/21/2020 Partial Approval NICK DANERI
Light Gage Steel Frame 5/21/2020 Partial Approval NICK DANERI
Reinforced Concrete Frame 5/21/2020 Partial Approval NICK DANERI
Light Gage Steel Frame 5/27/2020 Partial Approval NICK DANERI
Insulation 5/28/2020 Conditional Approval NICK DANERI
Reinforced Concrete Frame 5/28/2020 Partial Approval NICK DANERI
Deputy Drilled-In Anchors 6/3/2020 Conditional Approval NICK DANERI
Interior/Exterior Lathing 6/3/2020 Partial Approval NICK DANERI
Light Gage Steel Frame 6/3/2020 Partial Approval NICK DANERI
Reinforced Concrete Frame 6/3/2020 Partial Approval NICK DANERI
Light Gage Steel Frame 6/4/2020 Partial Approval NICK DANERI
Light Gage Steel Frame 6/5/2020 Partial Approval NICK DANERI
Insulation 6/9/2020 Partial Approval NICK DANERI
Drywall Nailing 6/11/2020 Partial Approval NICK DANERI
Light Gage Steel Frame 6/11/2020 Partial Approval NICK DANERI
Light Gage Steel Frame 6/17/2020 Partial Approval NICK DANERI
Drywall Nailing 6/19/2020 Partial Approval NICK DANERI
Insulation 6/19/2020 Partial Approval NICK DANERI
Reinforced Concrete Frame 6/26/2020 Partial Approval NICK DANERI
Light Gage Steel Frame 6/29/2020 Partial Approval NICK DANERI
Light Gage Steel Frame 7/6/2020 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 7/8/2020 Partial Approval NICK DANERI
Light Gage Steel Frame 7/8/2020 Partial Approval NICK DANERI
Light Gage Steel Frame 7/9/2020 Partial Approval NICK DANERI
Light Gage Steel Frame 7/10/2020 Conditional Approval NICK DANERI
Reinforced Concrete Frame 7/10/2020 Partial Approval NICK DANERI
Light Gage Steel Frame 7/13/2020 Partial Approval NICK DANERI
Light Gage Steel Frame 7/15/2020 Partial Approval NICK DANERI
Insulation 7/20/2020 Partial Approval NICK DANERI
Light Gage Steel Frame 7/20/2020 Partial Approval NICK DANERI
Reinforced Concrete Frame 7/22/2020 Partial Approval NICK DANERI
Light Gage Steel Frame 7/23/2020 Partial Inspection NICK DANERI
Reinforced Masonry Frame 7/24/2020 Partial Approval NICK DANERI
Insulation 7/30/2020 Partial Approval NICK DANERI
Light Gage Steel Frame 8/3/2020 Partial Approval NICK DANERI
Insulation 8/10/2020 Partial Approval NICK DANERI
Drywall Nailing 8/14/2020 Partial Approval RAFAEL ESPINOZA
Structural Steel Frame 8/14/2020 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 8/20/2020 Partial Approval NICK DANERI
Light Gage Steel Frame 8/20/2020 Partial Approval NICK DANERI
Light Gage Steel Frame 8/21/2020 Partial Approval NICK DANERI
Interior/Exterior Lathing 8/24/2020 Partial Approval NICK DANERI
Light Gage Steel Frame 8/25/2020 Partial Approval NICK DANERI
Insulation 8/31/2020 Partial Approval NICK DANERI
Drywall Nailing 9/9/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 9/9/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 9/15/2020 Partial Approval NICK DANERI
Masonry Wall/Backfill 9/18/2020 Partial Approval NICK DANERI
Light Gage Steel Frame 9/22/2020 Partial Approval NICK DANERI
Interior/Exterior Lathing 9/24/2020 Partial Approval NICK DANERI
Insulation 9/29/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 10/1/2020 Partial Approval NICK DANERI
Insulation 10/8/2020 Partial Approval NICK DANERI
Light Gage Steel Frame 10/15/2020 Partial Approval NICK DANERI
Insulation 10/23/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 10/23/2020 Partial Approval DANIEL COLLINS
Masonry Wall/Backfill 10/29/2020 Partial Approval NICK DANERI
Light Gage Steel Frame 11/12/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 11/18/2020 Partial Approval NICK DANERI
Interior/Exterior Lathing 11/18/2020 Partial Approval NICK DANERI
Pre-Inspection 11/24/2020 Partial Approval NICK DANERI
Light Gage Steel Frame 11/30/2020 Partial Approval NICK DANERI
Interior/Exterior Lathing 12/3/2020 Partial Approval NICK DANERI
T-Bar Ceiling 12/7/2020 Partial Approval NICK DANERI
Light Gage Steel Frame 12/15/2020 Partial Approval NICK DANERI
Interior/Exterior Lathing 12/18/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 12/18/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 12/22/2020 Partial Approval NICK DANERI
Special/Order Compliance 12/29/2020 Partial Inspection NICK DANERI
Drywall Nailing 12/30/2020 Partial Approval NICK DANERI
Light Gage Steel Frame 12/30/2020 Partial Approval NICK DANERI
Light Gage Steel Frame 1/8/2021 Partial Approval NICK DANERI
T-Bar Ceiling 1/11/2021 Partial Approval NICK DANERI
Light Gage Steel Frame 1/15/2021 Partial Approval LANNY MERRICK
Light Gage Steel Frame 1/20/2021 Partial Approval DAVID BURKHEAD
Light Gage Steel Frame 1/25/2021 Partial Approval NICK DANERI
Insulation 2/1/2021 Partial Approval NICK DANERI
Light Gage Steel Frame 2/4/2021 Partial Approval NICK DANERI
Interior/Exterior Lathing 2/10/2021 Partial Approval NICK DANERI
Final 2/16/2021 Partial Inspection NICK DANERI
Footing/Foundation/Slab 2/16/2021 Approved NICK DANERI
Green Building Final 2/16/2021 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 2/16/2021 Approved NICK DANERI
SGSOV-Seismic Gas S/O Valve 2/16/2021 SGSOV Not Ready NICK DANERI
SUSMP-Std. Urban Storm Water 2/16/2021 Not Ready for Inspection NICK DANERI
Smoke Detectors 2/16/2021 Not Ready for Inspection NICK DANERI
Special/Order Compliance 2/18/2021 Partial Approval NICK DANERI
Final 2/22/2021 Partial Inspection NICK DANERI
Green Building Final 2/22/2021 Not Ready for Inspection NICK DANERI
SGSOV-Seismic Gas S/O Valve 2/22/2021 SGSOV Not Ready NICK DANERI
SUSMP-Std. Urban Storm Water 2/22/2021 Not Ready for Inspection NICK DANERI
Smoke Detectors 2/22/2021 Partial Approval NICK DANERI
T-Bar Ceiling 2/25/2021 Partial Approval NICK DANERI
Final 3/3/2021 Partial Inspection NICK DANERI
Special/Order Compliance 3/5/2021 Partial Approval NICK DANERI
T-Bar Ceiling 3/16/2021 Partial Approval RAFAEL ESPINOZA
Posting Pre-Inspection 3/22/2021 Not Ready for Inspection NICK DANERI
Final 3/24/2021 Not Ready for Inspection NICK DANERI
Green Building Final 3/24/2021 Not Ready for Inspection NICK DANERI
SGSOV-Seismic Gas S/O Valve 3/24/2021 SGSOV Not Ready NICK DANERI
SUSMP-Std. Urban Storm Water 3/24/2021 Not Ready for Inspection NICK DANERI
Smoke Detectors 3/24/2021 Not Ready for Inspection NICK DANERI
Special/Order Compliance 3/31/2021 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 4/3/2021 Partial Approval DAVID BURKHEAD
Light Gage Steel Frame 4/9/2021 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 4/15/2021 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 5/11/2021 Partial Approval TIMOTHY BUXTON
T-Bar Ceiling 5/19/2021 Partial Approval NICK DANERI
Light Gage Steel Frame 5/20/2021 Partial Approval NICK DANERI
Drywall Nailing 5/27/2021 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 5/27/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 6/1/2021 Partial Approval NICK DANERI
Final 6/2/2021 Not Ready for Inspection NICK DANERI
Green Building Final 6/2/2021 Not Ready for Inspection NICK DANERI
SGSOV-Seismic Gas S/O Valve 6/2/2021 SGSOV Not Ready NICK DANERI
SUSMP-Std. Urban Storm Water 6/2/2021 Not Ready for Inspection NICK DANERI
Smoke Detectors 6/2/2021 Not Ready for Inspection NICK DANERI
Special/Order Compliance 6/2/2021 Partial Inspection NICK DANERI
Light Gage Steel Frame 6/15/2021 Partial Approval KATY RAMIREZ
Pre-Inspection 6/15/2021 Partial Inspection KATY RAMIREZ
Final 6/22/2021 Partial Inspection ERNESTO CORRAL
Green Building Final 6/22/2021 Partial Inspection ERNESTO CORRAL
SGSOV-Seismic Gas S/O Valve 6/22/2021 SGSOV Approved ERNESTO CORRAL
SUSMP-Std. Urban Storm Water 6/22/2021 Partial Inspection ERNESTO CORRAL
Smoke Detectors 6/22/2021 Partial Inspection ERNESTO CORRAL
Drywall Nailing 6/28/2021 Partial Approval DANIEL COLLINS
Final 8/18/2021 Partial Inspection ERNESTO CORRAL
Green Building Final 8/18/2021 Partial Inspection ERNESTO CORRAL
SUSMP-Std. Urban Storm Water 8/18/2021 Approved ERNESTO CORRAL
Smoke Detectors 8/18/2021 Partial Inspection ERNESTO CORRAL
Final 8/31/2021 OK for TCO ERNESTO CORRAL
Green Building Final 8/31/2021 Partial Approval ERNESTO CORRAL
Smoke Detectors 8/31/2021 Approved ERNESTO CORRAL
Pre-Inspection 9/9/2021 Completed (special insp) ERNESTO CORRAL
Special/Order Compliance 2/2/2022 Conditional Approval NICK DANERI
Final 2/10/2022 Not Ready for Inspection NICK DANERI
Green Building Final 2/10/2022 Not Ready for Inspection NICK DANERI
Final 2/28/2022 OK for TCO NICK DANERI
Green Building Final 2/28/2022 Conditional Approval NICK DANERI
Special/Order Compliance 8/4/2022 Conditional Approval NICK DANERI
Final 8/15/2022 Not Ready for Inspection TED RIES
Green Building Final 8/15/2022 Not Ready for Inspection TED RIES
Final 8/16/2022 OK for TCO NICK DANERI
Green Building Final 8/16/2022 Not Ready for Inspection NICK DANERI
Special/Order Compliance 1/18/2023 Conditional Approval NICK DANERI
Special/Order Compliance 7/18/2023 Conditional Approval NICK DANERI
Special/Order Compliance 1/3/2024 Conditional Approval NICK DANERI
Special/Order Compliance 6/26/2024 Conditional Approval NICK DANERI
Special/Order Compliance 12/18/2024 Conditional Approval NICK DANERI
Special/Order Compliance 6/17/2025 Approved JOEY BUCHANAN
Special/Order Compliance 12/16/2025 Approved JOEY BUCHANAN
Special/Order Compliance 5/27/2026 Approved JOEY BUCHANAN