2006 S PREUSS ROAD 90034

Certificate Information: 2006 S PREUSS ROAD 90034

Application / Permit
12010-10000-01302
Plan Check / Job No.
B12LA06295
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONSTRUCTION OF (1) NEW SINGLE FAMLIY DWELLING (PER SMALL LOT SUBDIVISION ORDINANCE 176,354)
Permit Issued
Issued on 11/15/2012
Issuing Office
Metro
Current Status
CofO Corrected on 1/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/4/2012 APPLICANT
Assigned to Plan Check Engineer 6/7/2012 ARA SARGSYAN
Corrections Issued 6/12/2012 ARA SARGSYAN
Quality Review Completed 6/22/2012 BILL STUTSMAN
Building Plans Picked Up 6/25/2012 APPLICANT
Green Plans Picked Up 6/25/2012 APPLICANT
Applicant returned to address corrections 8/7/2012 ARA SARGSYAN
Plan Check Approved 11/15/2012 ARA SARGSYAN
Issued 11/15/2012 LADBS
CofO in Progress 4/8/2014 DAVID CHAN
CofO Issued-Status Void 4/14/2014 CHERYL CHISOLM
Permit Finaled-Status Void 4/14/2014 CHERYL CHISOLM
Re-Activate Permit 7/11/2014 CHERYL CHISOLM
No Progress 7/11/2014 CHERYL CHISOLM
CofO in Progress 8/8/2018 KATHRYN BUTTERWORTH
Permit Finaled 1/29/2022 DEROLD HAUFF
CofO Corrected 1/29/2022 DEROLD HAUFF
Permit Finaled 1/29/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/5/2012 DAVID CHIN
Eng Process Fee Ord 176,300 Cleared 7/5/2012 JAMES MORALEZ
Hydrant and Access approval Cleared 7/18/2012 TERRENCE O'CONNELL
Miscellaneous Cleared 8/16/2012 EMMANUELA GUTIERREZ
ZA Case Cleared 8/16/2012 EMMANUELA GUTIERREZ
Stormwater Pollution Mitigatn Cleared 9/20/2012 IDA MEISAMI-FARD
Drainage to Storm Drain Cleared 10/31/2012 GREGG VANDERGRIFF
Highway dedication Cleared 10/31/2012 AVALYN KAMACHI
Permit Cleared 10/31/2012 GREGG VANDERGRIFF
Roof/Waste drainage to street Cleared 10/31/2012 GREGG VANDERGRIFF
Sewer availability Cleared 10/31/2012 AVALYN KAMACHI
Green Code Cleared 11/6/2012 RUSSELL KELLY
Public Works-Highway Ded. Cleared 3/10/2014 ROBERT SUTHERLIN
Public Works-Open Permits Cleared 3/10/2014 ROBERT SUTHERLIN
Public Works-Sewers Cleared 3/10/2014 ROBERT SUTHERLIN

Contact Information

Contractor Owner-Builder       ,
Engineer Alemozafar, Jilla; Lic. No.: C36047 728 WESTBOURNE DRIVE      WEST HOLLYWOOD, CA 90069

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/18/2013 Partial Approval DAVID CHAN
Sewer 1/18/2013 Partial Approval DAVID CHAN
ELECTRICAL-Rough 1/31/2013 Partial Approval DAVID CHAN
Underground Mechanical 2/1/2013 Partial Approval DAVID CHAN
Excavation/Setback/Form/Re-Bar 2/12/2013 Partial Inspection DAVID CHAN
Footing/Foundation/Slab 2/25/2013 Conditional Approval DAVID CHAN
Footing/Foundation/Slab 2/26/2013 Partial Approval DAVID CHAN
Deputy Drilled-In Anchors 3/14/2013 No Access for Inspection DAVID CHAN
BUILDING-Rough-Frame 4/19/2013 Partial Approval DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 4/19/2013 Approved DAVID CHAN
Green Building Rough 4/19/2013 Partial Inspection DONALD CRICHLOW
ELECTRICAL-Rough 4/24/2013 Approved DAVID CHAN
HVAC-Rough 5/9/2013 Approved DAVID CHAN
PLUMBING-Rough 5/9/2013 Partial Approval DAVID CHAN
PLUMBING-Rough 5/10/2013 Approved DAVID CHAN
BUILDING-Rough-Frame 5/13/2013 Corrections Issued DAVID CHAN
Green Building Rough 5/13/2013 Corrections Issued DONALD CRICHLOW
Green Building Rough 5/16/2013 Partial Approval DONALD CRICHLOW
Insulation 5/21/2013 Approved DAVID CHAN
Interior/Exterior Lathing 5/22/2013 Approved DAVID CHAN
Drywall Nailing 5/31/2013 Approved DAVID CHAN
Green Building Rough 5/31/2013 Approved DONALD CRICHLOW
Excavation/Setback/Form/Re-Bar 6/11/2013 Partial Approval DAVID CHAN
Footing/Foundation/Slab 6/11/2013 Partial Approval DAVID CHAN
Excavation/Setback/Form/Re-Bar 6/14/2013 Approved DAVID CHAN
PLUMBING-Rough 6/24/2013 Partial Approval DAVID CHAN
Interior/Exterior Lathing 6/28/2013 Approved CHARLES BOGHOSKHAN
Excavation/Setback/Form/Re-Bar 7/30/2013 Not Ready for Inspection DAVID CHAN
Footing/Foundation/Slab 7/31/2013 Partial Approval DAVID CHAN
Excavation/Setback/Form/Re-Bar 8/1/2013 Approved DAVID CHAN
Footing/Foundation/Slab 8/1/2013 Approved DAVID CHAN
Excavation/Setback/Form/Re-Bar 8/5/2013 Partial Approval DAVID CHAN
PLUMBING-Rough 8/13/2013 Partial Approval DAVID CHAN
ELECTRICAL-Rough 8/14/2013 Partial Approval DAVID CHAN
ELECTRICAL-Rough 8/15/2013 Partial Approval DAVID CHAN
ELECTRICAL-Final 9/13/2013 Approved ROBERT MCDOWELL
PLUMBING-Final 9/20/2013 Approved ROBERT MCDOWELL
Green Building Final 1/8/2014 Approved DONALD CRICHLOW
BUILDING-Rough-Frame 1/23/2014 Approved DAVID CHAN
Final 1/23/2014 Corrections Issued DAVID CHAN
SGSOV-Seismic Gas S/O Valve 1/23/2014 SGSOV Approved DAVID CHAN
Smoke Detectors 1/23/2014 Approved DAVID CHAN
Verify Sprinkler Sign Off 1/23/2014 Approved DAVID CHAN
Final 2/3/2014 Not Ready for Inspection DAVID CHAN
SUSMP-Std. Urban Storm Water 2/3/2014 Not Ready for Inspection DAVID CHAN
Final 2/13/2014 OK to Issue CofO DAVID CHAN
SUSMP-Std. Urban Storm Water 2/13/2014 Approved DAVID CHAN