200 S LOS ANGELES ST 1-104 90012

Certificate Information: 200 S LOS ANGELES ST 1-104 90012

Application / Permit
12010-10000-01294
Plan Check / Job No.
B12LA06243
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
PROPOSED MIXED USE PROJECT: 104 UNIT APARTMENT ON FLOORS 2 TO 6 (TYPE IIIA), RETAIL AND OFFICE ON THE 1ST FLOOR (TYPE I), PARKING ON 2 BASEMENT LEVELS AND 1ST FLOOR (TYPE I). SPRINKLERS USED FOR A STORY INCREASE. STEEL STAIRS, RAILS, PT SLABS ARE DEFERRED SUBMITTAL/APPROVAL
Permit Issued
Issued on 4/29/2013
Issuing Office
Metro
Current Status
CofO Issued on 8/14/2015
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/13/2012 APPLICANT
Assigned to Plan Check Engineer 6/21/2012 JOHN VASQUEZ
Corrections Issued 6/26/2012 JOHN VASQUEZ
Quality Review Completed 6/28/2012 BILL STUTSMAN
Building Plans Picked Up 6/29/2012 APPLICANT
Green Plans Picked Up 6/29/2012 APPLICANT
Disabled Access Plans Picked Up 7/6/2012 APPLICANT
Applicant returned to address corrections 7/23/2012 JOHN VASQUEZ
Applicant returned to address corrections 7/31/2012 JOHN VASQUEZ
Applicant returned to address corrections 8/7/2012 JOHN VASQUEZ
Applicant returned to address corrections 8/16/2012 JOHN VASQUEZ
Applicant returned to address corrections 8/21/2012 JOHN VASQUEZ
Applicant returned to address corrections 8/23/2012 JOHN VASQUEZ
Applicant returned to address corrections 8/29/2012 JOHN VASQUEZ
Applicant returned to address corrections 9/10/2012 JOHN VASQUEZ
Applicant returned to address corrections 9/20/2012 JOHN VASQUEZ
Applicant returned to address corrections 10/3/2012 JOHN VASQUEZ
Applicant returned to address corrections 11/8/2012 JOHN VASQUEZ
Applicant returned to address corrections 11/19/2012 JOHN VASQUEZ
Plan Check Approved 12/6/2012 JOHN VASQUEZ
Issued 4/29/2013 LADBS
TCO Issued (Expire Date: 01-17-2015) 7/21/2014 JAMES POWERS
TCO Issued (Expire Date: 07-16-2015) 1/17/2015 HAMID PISHEHVAR
TCO Issued (Expire Date: 01-12-2016) 7/16/2015 RICKEY JACKSON
CofO in Progress 8/14/2015 WINSTON DUNNING
Permit Finaled 8/14/2015 WINSTON DUNNING
CofO Issued 8/14/2015 WINSTON DUNNING
Permit Finaled 8/14/2015 WINSTON DUNNING

Permit Application Clearance Information

Address approval Cleared 6/26/2012 DAVID CHIN
Eng Process Fee Ord 176,300 Cleared 7/11/2012 DAVID CHIN
Project located in CRA area Cleared 7/18/2012 JIM URQUHART
Highway dedication Cleared 7/19/2012 JAMES MORALEZ
Driveway location Cleared 7/24/2012 COLLINS ALLAN
Internal circulation Cleared 7/25/2012 COLLINS ALLAN
Encroachment in public way Cleared 8/16/2012 ARMENIA HERNANDEZ
DAS Clearance Cleared 8/17/2012 JOHN VASQUEZ
Green Code Cleared 8/17/2012 DONALD CRICHLOW
Housing density bonus Cleared 8/17/2012 MARITES CUNANAN
Hydrant and Access approval Cleared 8/17/2012 JOHN DALLAS
Sewer availability Cleared 8/17/2012 AVALYN KAMACHI
"D" conditions Cleared 8/20/2012 BRIDGETTE WOOTEN
"Q" conditions Cleared 8/20/2012 BRIDGETTE WOOTEN
CPC Cleared 8/20/2012 BRIDGETTE WOOTEN
Opn space landscape/Water mgmt Cleared 8/20/2012 BRIDGETTE WOOTEN
Site Plan review Cleared 8/20/2012 BRIDGETTE WOOTEN
Tract Map conditions Cleared 8/20/2012 BRIDGETTE WOOTEN
ZA Case Cleared 8/20/2012 BRIDGETTE WOOTEN
Title 19 building approval Cleared 9/12/2012 GHASSEM NIKKHOO
Building over 3-story or 36-ft Cleared 9/20/2012 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 9/20/2012 CALOSHA APPROVED
Permit Cleared 9/24/2012 GREGG VANDERGRIFF
Roof/Waste drainage to street Cleared 9/24/2012 JAMES MORALEZ
Work Adjacent to Public Way Cleared 10/1/2012 ARMENIA HERNANDEZ
Drainage to Storm Drain Cleared 11/8/2012 AVALYN KAMACHI
Stormwater Pollution Mitigatn Cleared 11/8/2012 AMMAR ELTAWIL

Contact Information

Architect Cox, Thomas Phillips; Lic. No.: C10877 19782 MACARTHUR BLVD #300      IRVINE, CA 92612
Contractor Avalonbay Communities Inc; Lic. No.: 719040-B 400 RACE STREET   SUITE 200    SAN JOSE, CA 95124
Engineer Cefali, David Allen; Lic. No.: S3658 4344 LAUREL CANYON BLVD_STE 3      STUDIO CITY, CA 91604
Engineer Vandorpe, Thomas Daniel; Lic. No.: S4611 2200 W ORANGEWOOD AVE #150      ORANGE, CA 92868

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Wood Construction 8/1/2013 Partial Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 8/5/2013 Partial Approval LESLIE TRUJILLO
Deputy Wood Construction 9/4/2013 Approved SAKO AGHAZARIAN
Excavation/Setback/Form/Re-Bar 9/13/2013 Conditional Approval LESLIE TRUJILLO
Deputy Wood Construction 9/18/2013 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 9/25/2013 Partial Approval LESLIE TRUJILLO
Deputy Wood Construction 9/27/2013 Partial Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 10/1/2013 Partial Approval LESLIE TRUJILLO
Deputy Wood Construction 10/2/2013 Partial Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 10/3/2013 Partial Approval LESLIE TRUJILLO
Wood Frame 11/12/2013 Partial Approval LESLIE TRUJILLO
Wood Frame 11/13/2013 Partial Approval LESLIE TRUJILLO
Wood Frame 11/14/2013 Partial Approval LESLIE TRUJILLO
Wood Frame 11/15/2013 Partial Approval LESLIE TRUJILLO
Deputy Wood Construction 11/18/2013 Partial Approval LESLIE TRUJILLO
Wood Frame 11/18/2013 Partial Approval LESLIE TRUJILLO
Wood Frame 11/19/2013 Partial Approval LESLIE TRUJILLO
Wood Frame 11/21/2013 Partial Approval LESLIE TRUJILLO
Wood Frame 11/27/2013 Not Ready for Inspection LESLIE TRUJILLO
Wood Frame 12/2/2013 Partial Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 12/3/2013 Not Ready for Inspection LESLIE TRUJILLO
Wood Frame 12/4/2013 Not Ready for Inspection LESLIE TRUJILLO
Wood Frame 12/5/2013 Not Ready for Inspection LESLIE TRUJILLO
Wood Frame 12/9/2013 Partial Approval LESLIE TRUJILLO
Insulation 12/11/2013 Partial Approval LESLIE TRUJILLO
Wood Frame 12/12/2013 Partial Approval LESLIE TRUJILLO
Wood Frame 12/13/2013 Partial Approval LESLIE TRUJILLO
Wood Frame 12/16/2013 Partial Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 12/17/2013 Partial Approval LESLIE TRUJILLO
Deputy Drilled-In Anchors 12/18/2013 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 12/18/2013 Partial Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 12/18/2013 Not Ready for Inspection LESLIE TRUJILLO
Wood Frame 12/19/2013 Partial Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 12/20/2013 Partial Approval LESLIE TRUJILLO
Insulation 12/23/2013 Partial Approval LESLIE TRUJILLO
Wood Frame 12/26/2013 Partial Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 12/27/2013 Partial Approval LESLIE TRUJILLO
Wood Frame 12/27/2013 Partial Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 1/3/2014 Partial Approval LESLIE TRUJILLO
Insulation 1/3/2014 Partial Approval LESLIE TRUJILLO
Insulation 1/7/2014 Order to Comply Issued LESLIE TRUJILLO
Wood Frame 1/7/2014 Partial Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 1/9/2014 Partial Approval LESLIE TRUJILLO
Wood Frame 1/13/2014 Partial Approval LESLIE TRUJILLO
Drywall Nailing 1/14/2014 Partial Approval LESLIE TRUJILLO
Insulation 1/14/2014 Partial Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 1/15/2014 Partial Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 1/17/2014 Partial Approval LESLIE TRUJILLO
Insulation 1/17/2014 Partial Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 1/21/2014 Partial Approval LESLIE TRUJILLO
Wood Frame 1/21/2014 Partial Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 1/22/2014 Partial Inspection LESLIE TRUJILLO
Insulation 1/22/2014 Not Ready for Inspection LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 1/24/2014 Partial Approval LESLIE TRUJILLO
Insulation 1/24/2014 Partial Approval LESLIE TRUJILLO
Interior/Exterior Lathing 1/24/2014 Not Ready for Inspection LESLIE TRUJILLO
Drywall Nailing 1/27/2014 Partial Approval LESLIE TRUJILLO
Insulation 1/27/2014 Partial Approval LESLIE TRUJILLO
Interior/Exterior Lathing 1/27/2014 Not Ready for Inspection LESLIE TRUJILLO
Insulation 1/28/2014 Partial Approval LESLIE TRUJILLO
Interior/Exterior Lathing 1/28/2014 Partial Approval LESLIE TRUJILLO
Drywall Nailing 1/29/2014 Partial Approval LESLIE TRUJILLO
Insulation 1/29/2014 Partial Approval LESLIE TRUJILLO
Wood Frame 1/29/2014 Partial Approval LESLIE TRUJILLO
Drywall Nailing 1/30/2014 Partial Approval LESLIE TRUJILLO
Wood Frame 1/31/2014 Partial Approval LESLIE TRUJILLO
Insulation 2/3/2014 Partial Approval LESLIE TRUJILLO
Interior/Exterior Lathing 2/3/2014 Not Ready for Inspection LESLIE TRUJILLO
Wood Frame 2/3/2014 Partial Approval LESLIE TRUJILLO
Wood Frame 2/4/2014 Partial Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 2/5/2014 Partial Approval LESLIE TRUJILLO
Insulation 2/5/2014 Partial Approval LESLIE TRUJILLO
Interior/Exterior Lathing 2/5/2014 Partial Approval LESLIE TRUJILLO
Insulation 2/6/2014 Not Ready for Inspection LESLIE TRUJILLO
Interior/Exterior Lathing 2/6/2014 Partial Approval LESLIE TRUJILLO
Wood Frame 2/6/2014 Partial Approval LESLIE TRUJILLO
Interior/Exterior Lathing 2/7/2014 Partial Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 2/10/2014 Partial Approval LESLIE TRUJILLO
Insulation 2/11/2014 Partial Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 2/12/2014 Partial Approval LESLIE TRUJILLO
Insulation 2/12/2014 Partial Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 2/13/2014 Partial Approval LESLIE TRUJILLO
Insulation 2/13/2014 Partial Approval LESLIE TRUJILLO
Insulation 2/14/2014 Partial Approval LESLIE TRUJILLO
Wood Frame 2/14/2014 No Access for Inspection LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 2/18/2014 Partial Approval LESLIE TRUJILLO
Insulation 2/18/2014 Partial Approval LESLIE TRUJILLO
Drywall Nailing 2/19/2014 Partial Approval LESLIE TRUJILLO
Insulation 2/19/2014 Partial Inspection LESLIE TRUJILLO
Insulation 2/20/2014 Not Ready for Inspection LESLIE TRUJILLO
Interior/Exterior Lathing 2/20/2014 Not Ready for Inspection LESLIE TRUJILLO
Insulation 2/21/2014 Partial Approval LESLIE TRUJILLO
Interior/Exterior Lathing 2/21/2014 Partial Approval LESLIE TRUJILLO
Interior/Exterior Lathing 2/24/2014 Partial Approval LESLIE TRUJILLO
Drywall Nailing 2/26/2014 Partial Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 2/26/2014 Partial Approval LESLIE TRUJILLO
Insulation 3/3/2014 Partial Approval LESLIE TRUJILLO
Insulation 3/4/2014 Not Ready for Inspection LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 3/5/2014 Partial Approval LESLIE TRUJILLO
Insulation 3/6/2014 Partial Approval LESLIE TRUJILLO
Interior/Exterior Lathing 3/6/2014 Approved LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 3/7/2014 Partial Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 3/12/2014 Partial Approval LESLIE TRUJILLO
Insulation 3/12/2014 Not Ready for Inspection LESLIE TRUJILLO
Drywall Nailing 3/13/2014 Partial Approval LESLIE TRUJILLO
Insulation 3/13/2014 Not Ready for Inspection LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 3/14/2014 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 3/14/2014 Partial Approval LESLIE TRUJILLO
Insulation 3/17/2014 Not Ready for Inspection LESLIE TRUJILLO
Insulation 3/21/2014 Partial Approval LESLIE TRUJILLO
Insulation 3/26/2014 Partial Inspection LESLIE TRUJILLO
Insulation 3/27/2014 Partial Approval LESLIE TRUJILLO
Insulation 3/28/2014 Partial Approval LESLIE TRUJILLO
Insulation 4/1/2014 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/3/2014 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 4/15/2014 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 4/15/2014 Approved LESLIE TRUJILLO
METHANE-Subgrade 4/15/2014 Approved LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 4/16/2014 Not Ready for Inspection LESLIE TRUJILLO
Insulation 4/16/2014 Partial Approval LESLIE TRUJILLO
Light Gage Steel Frame 4/21/2014 Not Ready for Inspection LESLIE TRUJILLO
Drywall Nailing 4/30/2014 Partial Approval LESLIE TRUJILLO
Excavation/Setback/Form/Re-Bar 4/30/2014 Partial Approval LESLIE TRUJILLO
Wood Frame 6/2/2014 Partial Approval LESLIE TRUJILLO
Pre-Inspection 6/13/2014 Partial Inspection LESLIE TRUJILLO
Final 6/26/2014 Not Ready for Inspection LESLIE TRUJILLO
Footing/Foundation/Slab 6/26/2014 Partial Approval LESLIE TRUJILLO
Green Building Final 6/26/2014 Partial Approval MICHAEL TUCK
Green Building Rough 6/26/2014 Approved MICHAEL TUCK
METHANE-Final 6/26/2014 Not Ready for Inspection LESLIE TRUJILLO
METHANE-Rough 6/26/2014 Approved LESLIE TRUJILLO
Reinforced Concrete Frame 6/26/2014 Partial Approval LESLIE TRUJILLO
Reinforced Masonry Frame 6/26/2014 Partial Approval LESLIE TRUJILLO
SGSOV-Seismic Gas S/O Valve 6/26/2014 SGSOV Approved LESLIE TRUJILLO
SUSMP-Std. Urban Storm Water 6/26/2014 Approved LESLIE TRUJILLO
Smoke Detectors 6/26/2014 Approved LESLIE TRUJILLO
Final 6/30/2014 Not Ready for Inspection LESLIE TRUJILLO
Footing/Foundation/Slab 6/30/2014 Not Ready for Inspection LESLIE TRUJILLO
Green Building Final 6/30/2014 Not Ready for Inspection MICHAEL TUCK
Reinforced Concrete Frame 6/30/2014 Approved LESLIE TRUJILLO
Reinforced Masonry Frame 6/30/2014 Approved LESLIE TRUJILLO
Excavation/Setback/Form/Re-Bar 7/7/2014 Partial Approval WILLIAM THOMPSON
Final 7/8/2014 Corrections Issued LESLIE TRUJILLO
Footing/Foundation/Slab 7/8/2014 Partial Approval LESLIE TRUJILLO
Final 7/16/2014 Not Ready for Inspection LESLIE TRUJILLO
Footing/Foundation/Slab 7/16/2014 Approved LESLIE TRUJILLO
Final 7/18/2014 OK for TCO LESLIE TRUJILLO
Final 7/21/2014 OK for TCO LESLIE TRUJILLO
Green Building Final 12/17/2014 Approved RICHARD DOCKUS
Special/Order Compliance 12/23/2014 Partial Inspection LESLIE TRUJILLO
Final 5/20/2015 Partial Inspection LESLIE TRUJILLO
Special/Order Compliance 6/17/2015 Partial Inspection LESLIE TRUJILLO