2317 S GLYNDON AVE 90291

Certificate Information: 2317 S GLYNDON AVE 90291

Application / Permit
12010-10000-00668
Plan Check / Job No.
B12LA03011
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED NEW 42'6"X32'3" 2-STORY SFD W/ MEZZANINE, BALCONY (7'X32'3") & BASEMENT WINE CELLAR (18'7"X8'4") BELOW KITCHEN AREA - 2 BEDRMS TOTAL.
Permit Issued
Issued on 10/3/2014
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/4/2012 APPLICANT
Assigned to Plan Check Engineer 4/12/2012 HAYATO TSUCHIYA
Corrections Issued 4/18/2012 HAYATO TSUCHIYA
Quality Review Completed 4/19/2012 JOHN VASQUEZ
Building Plans Picked Up 5/16/2012 APPLICANT
Applicant returned to address corrections 8/2/2013 HAYATO TSUCHIYA
Green Plans Picked Up 9/19/2013 APPLICANT
Applicant returned to address corrections 2/11/2014 HAYATO TSUCHIYA
Applicant returned to address corrections 5/20/2014 HAYATO TSUCHIYA
Applicant returned to address corrections 5/27/2014 HAYATO TSUCHIYA
Applicant returned to address corrections 6/6/2014 HAYATO TSUCHIYA
Applicant returned to address corrections 6/20/2014 HAYATO TSUCHIYA
Plan Check Approved 8/6/2014 HAYATO TSUCHIYA
Issued 10/3/2014 LADBS
Permit Expired-Status Void 10/27/2016 APPLICANT
Re-Activate Permit 11/1/2016 NEWTON GERHARDT
Permit Finaled-Status Void 11/29/2023 MICHAEL PELHAM
Re-Activate Permit 3/4/2024 MICHAEL PELHAM
CofO in Progress 3/6/2024 MICHAEL PELHAM
Permit Finaled 3/6/2024 DANIEL ORRANTE
CofO Issued 3/6/2024 DANIEL ORRANTE
Permit Finaled 3/6/2024 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/22/2014 AVALYN KAMACHI
Sewer availability Cleared 5/22/2014 AVALYN KAMACHI
Building over 3-story or 36-ft Cleared 6/6/2014 CALOSHA APPROVED
Green Code Cleared 6/27/2014 MICHAEL TUCK
Eng Process Fee Ord 176,300 Cleared 6/30/2014 AVALYN KAMACHI
Hydrant and Access approval Cleared 6/30/2014 ROBERT DUFF
"D" conditions Cleared 7/15/2014 VICTOR VALLEJO
Low Impact Development Cleared 7/24/2014 MICHAEL SCADUTO
Permit Cleared 7/24/2014 VALENTINO PUEBLOS
Green Code Cleared 8/5/2014 MICHAEL TUCK
Excavation more than 5-ft deep Cleared 8/6/2014 CALOSHA APPROVED

Contact Information

Architect Chu, Tien Hsi; Lic. No.: C15558 3354 E COLORADO BLVD      PASADENA, CA 91107
Contractor Tan Randy; Lic. No.: 816849-B 859 PERU AVEENUE      SAN FRANCISCO, CA 94112
Engineer Lee, Jack C; Lic. No.: GE2153 576 E LAMBERT RD      BREA, CA 92821
Engineer Li, Dacheng David; Lic. No.: C58075 23240 RIDGELINE DR      DIAMOND BAR, CA 91765

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/1/2016 Approved CARLOS MATAMOROS
Gas Test 8/22/2017 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 8/22/2017 Partial Approval CARLOS MATAMOROS
Sewer 8/22/2017 Approved CARLOS MATAMOROS
Gas Test 8/23/2017 Approved CARLOS MATAMOROS
Deputy Steel/Welding 9/8/2017 Conditional Approval CARLOS MATAMOROS
Special/Order Compliance 12/28/2017 No Access for Inspection CARLOS MATAMOROS
Special/Order Compliance 1/8/2018 Not Ready for Inspection CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 8/9/2018 Approved CARLOS MATAMOROS
Green Building Rough 8/9/2018 Not Ready for Inspection CARLOS MATAMOROS
Verify Sprinkler Sign Off 8/9/2018 Not Ready for Inspection CARLOS MATAMOROS
Deputy Steel/Welding 8/7/2019 Partial Approval DAVID HEINE
PLUMBING-Rough 4/28/2021 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Rough 4/30/2021 Corrections Issued JOHNNY MIRANDA
Pre-Inspection 5/4/2021 Approved JOHNNY MIRANDA
Special/Order Compliance 5/4/2021 Partial Approval PIERRE VEGA
Special/Order Compliance 8/25/2021 Partial Approval JOHNNY MIRANDA
Special/Order Compliance 8/27/2021 Corrections Issued JOHNNY MIRANDA
HVAC-Rough 10/6/2021 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 10/7/2021 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 10/7/2021 Corrections Issued JOHNNY MIRANDA
HVAC-Rough 10/14/2021 Corrections Issued DAVID FEILER
PLUMBING-Rough 10/14/2021 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 10/15/2021 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 10/15/2021 Partial Approval DAVID FEILER
Green Building Rough 10/15/2021 Not Ready for Inspection DAVID FEILER
HVAC-Rough 10/15/2021 Approved DAVID FEILER
Verify Sprinkler Sign Off 10/15/2021 Approved DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 10/20/2021 Partial Inspection DAVID FEILER
PLUMBING-Rough 10/20/2021 Approved DAVID FEILER
BUILDING-Rough-Frame 5/11/2022 Approved DAVID FEILER
Drywall Nailing 5/11/2022 Approved DAVID FEILER
Green Building Rough 5/11/2022 Approved DAVID FEILER
Final 8/31/2023 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 8/31/2023 Approved JESUS RODRIGUEZ
Green Building Final 8/31/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 8/31/2023 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 8/31/2023 Approved JESUS RODRIGUEZ
Structural Steel Frame 8/31/2023 Approved JESUS RODRIGUEZ
Final 9/20/2023 Partial Inspection MICHAEL PELHAM
Special/Order Compliance 11/29/2023 Partial Approval MICHAEL PELHAM
Final 3/6/2024 OK to Issue CofO MICHAEL PELHAM