1479 N VIA CRESTA 90272
Certificate Information: 1479 N VIA CRESTA 90272
- Application / Permit
- 12010-10000-00443
- Plan Check / Job No.
- B12LA01607
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- NEW GYM BUILDING
- Permit Issued
- Issued on 7/3/2013
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/13/2012 | APPLICANT |
| Green Plans Picked Up | 3/8/2012 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2012 | LARRY LEE |
| Corrections Issued | 3/30/2012 | LARRY LEE |
| Quality Review Completed | 4/2/2012 | CHARLES CHANG |
| Building Plans Picked Up | 4/2/2012 | APPLICANT |
| Applicant returned to address corrections | 9/10/2012 | LARRY LEE |
| Applicant returned to address corrections | 4/18/2013 | LARRY LEE |
| Applicant returned to address corrections | 5/2/2013 | LARRY LEE |
| Applicant returned to address corrections | 6/25/2013 | LARRY LEE |
| Plan Check Approved | 6/27/2013 | LARRY LEE |
| Issued | 7/3/2013 | LADBS |
| CofO in Progress | 5/23/2024 | EVAN COOPER |
| No Progress | 7/23/2024 | KENNETH NAGLE |
| CofO in Progress | 7/23/2024 | KENNETH NAGLE |
| Permit Finaled | 7/25/2024 | DANIEL ORRANTE |
| CofO Issued | 7/25/2024 | DANIEL ORRANTE |
| Permit Finaled | 7/25/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 4/4/2012 | ARMENIA HERNANDEZ |
| Permit | Cleared | 4/4/2012 | ARMENIA HERNANDEZ |
| Public Works-Highway Ded. | Cleared | 4/4/2012 | ARMENIA HERNANDEZ |
| Private street | Cleared | 7/25/2012 | PHYLLIS PARKER |
| ZA Case | Cleared | 7/25/2012 | PHYLLIS PARKER |
| ZA Case | Cleared | 7/25/2012 | PHYLLIS PARKER |
| ZA Case | Cleared | 7/25/2012 | PHYLLIS PARKER |
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2012 | WESLEY TANIJIRI |
| Sewer availability | Cleared | 7/27/2012 | WESLEY TANIJIRI |
| Hydrant and Access approval | Cleared | 5/7/2013 | JOSEPH JACKSON |
| VHFHSZ | Cleared | 5/7/2013 | JOSEPH JACKSON |
| Green Code | Cleared | 5/29/2013 | RUSSELL KELLY |
| Green Code | Cleared | 5/29/2013 | RUSSELL KELLY |
| Roof/Waste drainage to street | Cleared | 5/30/2013 | ARMENIA HERNANDEZ |
| Stormwater Pollution Mitigatn | Cleared | 5/30/2013 | IDA MEISAMI-FARD |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/4/2014 | Approved | DAVID LEE |
| Piling/Pier/Caisson | 9/16/2014 | Approved | KENNETH NAGLE |
| Deputy Reinf. Concrete | 9/25/2014 | No Access for Inspection | KENNETH NAGLE |
| BUILDING-Rough-Frame | 9/25/2015 | Not Ready for Inspection | DANIEL ORRANTE |
| FLOOD-Elevation Certificate | 9/25/2015 | Not Ready for Inspection | DANIEL ORRANTE |
| FLOOD-Proofing Certificate | 9/25/2015 | Not Ready for Inspection | DANIEL ORRANTE |
| Final | 9/25/2015 | Not Ready for Inspection | DANIEL ORRANTE |
| Footing/Foundation/Slab | 9/25/2015 | Not Ready for Inspection | DANIEL ORRANTE |
| Green Building Final | 9/25/2015 | Not Ready for Inspection | DANIEL ORRANTE |
| Green Building Rough | 9/25/2015 | Not Ready for Inspection | DANIEL ORRANTE |
| SGSOV-Seismic Gas S/O Valve | 9/25/2015 | SGSOV Not Ready | DANIEL ORRANTE |
| Smoke Detectors | 9/25/2015 | Not Ready for Inspection | DANIEL ORRANTE |
| Verify Sprinkler Sign Off | 9/25/2015 | Not Ready for Inspection | DANIEL ORRANTE |
| Pre-Inspection | 10/15/2018 | Partial Approval | MICHAEL PELHAM |
| PLUMBING-Rough | 11/6/2018 | Not Ready for Inspection | MICHAEL PELHAM |
| Reinforced Concrete Frame | 1/10/2019 | Corrections Issued | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 1/24/2019 | Partial Inspection | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 3/22/2019 | Partial Approval | ANDREW NAVE |
| Special/Order Compliance | 4/5/2019 | Approved | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 4/12/2019 | Partial Approval | ANDREW NAVE |
| FLOOD-Elevation Certificate | 6/25/2019 | Approved | ANDREW NAVE |
| Footing/Foundation/Slab | 6/25/2019 | Partial Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 8/8/2019 | Corrections Issued | ANDREW NAVE |
| Deck | 10/29/2019 | Corrections Issued | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 10/29/2019 | Partial Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 11/12/2019 | Conditional Approval | ANDREW NAVE |
| FLOOD-Proofing Certificate | 1/27/2020 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2020 | Partial Approval | ANDREW NAVE |
| Green Building Rough | 1/27/2020 | Not Ready for Inspection | ANDREW NAVE |
| Underground Mechanical | 1/27/2020 | Partial Inspection | ANDREW NAVE |
| ELECTRICAL-Rough | 11/29/2021 | Partial Approval | ANDREW NAVE |
| PLUMBING-Final | 1/5/2024 | Approved | EVAN COOPER |
| HVAC-Final | 1/17/2024 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 3/26/2024 | Approved | EVAN COOPER |
| Final | 3/26/2024 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 3/26/2024 | Approved | EVAN COOPER |
| Green Building Final | 3/26/2024 | Approved | EVAN COOPER |
| Green Building Rough | 3/26/2024 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 3/26/2024 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 3/26/2024 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 3/26/2024 | Approved | EVAN COOPER |
| Final | 5/15/2024 | Corrections Issued | EVAN COOPER |
| Final | 5/22/2024 | OK to Issue CofO | EVAN COOPER |