901 W OLYMPIC BLVD 90015
Certificate Information: 901 W OLYMPIC BLVD 90015
- Application / Permit
- 11020-10000-02649
- Plan Check / Job No.
- B11LA14081
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- shoring for a New 23-story hotel with 393 hotel roomscorner of Francisco and Olympic.
- Permit Issued
- Issued on 4/17/2012
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 5/12/2014
Permit Application Status History
Submitted | 1/3/2012 | APPLICANT |
Assigned to Plan Check Engineer | 1/6/2012 | LARRY LEE |
Corrections Issued | 1/10/2012 | LARRY LEE |
Quality Review Completed | 1/10/2012 | CHARLES CHANG |
Building Plans Picked Up | 1/12/2012 | APPLICANT |
Green Plans Picked Up | 1/17/2012 | APPLICANT |
Plan Check Approved | 4/17/2012 | LARRY LEE |
Issued | 4/17/2012 | LADBS |
Permit Finaled | 5/9/2014 | SAKO AGHAZARIAN |
Permit Application Clearance Information
Eng Process Fee Ord 176,300 | Cleared | 4/17/2012 | TERRY PHAN |
Excavation more than 5-ft deep | Cleared | 4/17/2012 | CALOSHA APPROVED |
Green Code | Cleared | 4/17/2012 | ALDO UBAU |
Work Adjacent to Public Way | Cleared | 4/17/2012 | TERRY PHAN |
Contact Information
Contractor | Owner-Builder | , |
Engineer | Cefali, David Allen; Lic. No.: S3658 | 4344 LAUREL CANYON BLVD_STE 3 STUDIO CITY, CA 91604 |
Engineer | Zadoorian, Christopher John; Lic. No.: GE2493 | 1310 MIRASOL AVE IRVINE, CA 92620 |
Inspector Information
DAVID BURKHEAD, (213) 482-7294 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Deputy Grading | 5/16/2012 | Approved | SAKO AGHAZARIAN |
Deputy Steel/Welding | 5/17/2012 | Conditional Approval | JOHN CARPENTER |
Deputy Steel/Welding | 5/18/2012 | Approved | SAKO AGHAZARIAN |
Deputy Other (see comments) | 5/21/2012 | Approved | SAKO AGHAZARIAN |
Deputy Steel/Welding | 5/21/2012 | Approved | SAKO AGHAZARIAN |
Piling/Pier/Caisson | 5/21/2012 | Partial Inspection | SAKO AGHAZARIAN |
Deputy Other (see comments) | 5/22/2012 | Approved | SAKO AGHAZARIAN |
Deputy Steel/Welding | 5/22/2012 | Approved | SAKO AGHAZARIAN |
Deputy Other (see comments) | 5/23/2012 | Approved | SAKO AGHAZARIAN |
Deputy Steel/Welding | 5/23/2012 | Approved | SAKO AGHAZARIAN |
Deputy Other (see comments) | 5/24/2012 | Approved | SAKO AGHAZARIAN |
Deputy Steel/Welding | 5/24/2012 | Approved | SAKO AGHAZARIAN |
Deputy Other (see comments) | 5/25/2012 | Approved | SAKO AGHAZARIAN |
Deputy Steel/Welding | 5/25/2012 | Approved | SAKO AGHAZARIAN |
Deputy Grading | 5/29/2012 | Approved | SAKO AGHAZARIAN |
Excavation/Setback/Form/Re-Bar | 5/29/2012 | Partial Approval | SAKO AGHAZARIAN |
Deputy Grading | 5/30/2012 | Approved | SAKO AGHAZARIAN |
Deputy Grading | 5/31/2012 | Approved | SAKO AGHAZARIAN |
Deputy Grading | 6/1/2012 | Approved | SAKO AGHAZARIAN |
Deputy Grading | 6/4/2012 | Approved | SAKO AGHAZARIAN |
Piling/Pier/Caisson | 6/4/2012 | Partial Inspection | SAKO AGHAZARIAN |
Deputy Grading | 6/5/2012 | Approved | SAKO AGHAZARIAN |
Deputy Steel/Welding | 6/5/2012 | Approved | SAKO AGHAZARIAN |
Deputy Grading | 6/6/2012 | Partial Approval | SAKO AGHAZARIAN |
Deputy Reinf. Concrete | 6/6/2012 | Approved | SAKO AGHAZARIAN |
Deputy Grading | 6/7/2012 | Approved | SAKO AGHAZARIAN |
Deputy Grading | 6/8/2012 | Approved | SAKO AGHAZARIAN |
Deputy Grading | 6/12/2012 | Approved | SAKO AGHAZARIAN |
Deputy Reinf. Concrete | 6/12/2012 | Approved | SAKO AGHAZARIAN |
Deputy Steel/Welding | 6/12/2012 | Approved | SAKO AGHAZARIAN |
Piling/Pier/Caisson | 6/12/2012 | Partial Approval | SAKO AGHAZARIAN |
Deputy Grading | 6/13/2012 | Approved | SAKO AGHAZARIAN |
Deputy Reinf. Concrete | 6/13/2012 | Approved | SAKO AGHAZARIAN |
Deputy Grading | 6/14/2012 | Approved | SAKO AGHAZARIAN |
Deputy Reinf. Concrete | 6/14/2012 | Approved | SAKO AGHAZARIAN |
Deputy Steel/Welding | 6/14/2012 | Approved | SAKO AGHAZARIAN |
Deputy Grading | 6/15/2012 | Approved | SAKO AGHAZARIAN |
Deputy Reinf. Concrete | 6/15/2012 | Approved | SAKO AGHAZARIAN |
Deputy Grading | 6/18/2012 | Approved | SAKO AGHAZARIAN |
Deputy Grading | 6/19/2012 | Approved | SAKO AGHAZARIAN |
Piling/Pier/Caisson | 6/19/2012 | Partial Approval | SAKO AGHAZARIAN |
Deputy Grading | 6/20/2012 | Conditional Approval | JOHN CARPENTER |
Deputy Grading | 6/21/2012 | Conditional Approval | JOHN CARPENTER |
Deputy Reinf. Concrete | 6/21/2012 | Conditional Approval | JOHN CARPENTER |
Deputy Grading | 6/22/2012 | Conditional Approval | JOHN CARPENTER |
Piling/Pier/Caisson | 11/30/2012 | Partial Approval | SAKO AGHAZARIAN |
Piling/Pier/Caisson | 12/3/2012 | Partial Inspection | SAKO AGHAZARIAN |
Deputy Grading | 12/4/2012 | Approved | SAKO AGHAZARIAN |
Piling/Pier/Caisson | 12/4/2012 | Partial Inspection | SAKO AGHAZARIAN |
Deputy Grading | 12/5/2012 | Approved | SAKO AGHAZARIAN |
Deputy Grading | 12/6/2012 | Approved | SAKO AGHAZARIAN |
Deputy Grading | 12/7/2012 | Approved | SAKO AGHAZARIAN |
Deputy Grading | 12/10/2012 | Approved | SAKO AGHAZARIAN |
Deputy Grading | 12/11/2012 | Approved | SAKO AGHAZARIAN |
Deputy Grading | 12/12/2012 | Approved | SAKO AGHAZARIAN |
Deputy Grading | 12/13/2012 | Approved | SAKO AGHAZARIAN |
Deputy Grading | 12/14/2012 | Approved | SAKO AGHAZARIAN |
Special/Order Compliance | 5/2/2014 | Approved | SAKO AGHAZARIAN |
Final | 5/5/2014 | Partial Inspection | SAKO AGHAZARIAN |
Final | 5/9/2014 | Permit Finaled | SAKO AGHAZARIAN |