631 E 108TH ST unit 1-4 90002

Certificate Information: 631 E 108TH ST unit 1-4 90002

Application / Permit
11016-10000-06265
Plan Check / Job No.
B11LA03480
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Convert an existing 3 unit apartment into a 4 unit apartment. Interior work only, no new floor area
Permit Issued
Issued on 12/2/2011
Issuing Office
Metro
Current Status
CofO Issued on 9/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/7/2011 APPLICANT
Assigned to Plan Check Engineer 4/14/2011 CORA JOHNSON
Corrections Issued 4/22/2011 CORA JOHNSON
Quality Review Completed 4/28/2011 SHAHEN AKELYAN
Building Plans Picked Up 5/17/2011 APPLICANT
Plan Check Approved 12/2/2011 CORA JOHNSON
Issued 12/2/2011 LADBS
Permit Expired-Status Void 12/26/2013 APPLICANT
Re-Activate Permit 9/1/2015 WILLIAM TORRES
CofO in Progress 9/12/2024 MARTIN TAVITIAN
CofO Issued 9/13/2024 ERNESTO CORRAL
Permit Finaled 9/13/2024 ERNESTO CORRAL

Permit Application Clearance Information

Highway dedication Cleared 9/15/2011 NATALIE MOORE
Eng Process Fee Ord 176,300 Cleared 11/29/2011 JAMES KHO
Sewer availability Cleared 11/29/2011 JAMES KHO
Address approval Cleared 12/2/2011 DAVID CHIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Final 12/18/2013 No Access for Inspection NICK DANERI
SGSOV-Seismic Gas S/O Valve 12/18/2013 SGSOV Not Ready NICK DANERI
Smoke Detectors 12/18/2013 No Access for Inspection NICK DANERI
SGSOV-Seismic Gas S/O Valve 10/20/2015 SGSOV Not Ready BYRON FUENTES
Smoke Detectors 10/20/2015 Not Ready for Inspection BYRON FUENTES
Final 10/27/2015 Not Ready for Inspection BYRON FUENTES
Final 1/8/2020 Corrections Issued RUSSELL BONVOULOIR
SGSOV-Seismic Gas S/O Valve 1/8/2020 SGSOV Not Ready RUSSELL BONVOULOIR
Smoke Detectors 1/8/2020 Not Ready for Inspection RUSSELL BONVOULOIR
Pre-Inspection 10/20/2022 Approved TIMOTHY BUXTON
Wood Frame 7/27/2023 Approved DARRYL ARNOLD
Drywall Nailing 8/23/2023 Partial Approval RAFAEL CORTES
Interior/Exterior Lathing 8/23/2023 Partial Approval RAFAEL CORTES
Final 4/17/2024 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 4/17/2024 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 4/17/2024 Not Ready for Inspection DARRYL ARNOLD
Final 5/16/2024 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 5/16/2024 SGSOV Not Ready DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 8/15/2024 SGSOV Not Ready DARRYL ARNOLD
Final 9/3/2024 Conditional Approval DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 9/3/2024 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 9/3/2024 Approved DARRYL ARNOLD
Final 9/12/2024 OK to Issue CofO MARTIN TAVITIAN
SGSOV-Seismic Gas S/O Valve 9/12/2024 SGSOV Approved MARTIN TAVITIAN
Smoke Detectors 9/12/2024 Approved MARTIN TAVITIAN