2377 N MT OLYMPUS DR 90046
Certificate Information: 2377 N MT OLYMPUS DR 90046
- Application / Permit
- 11014-20000-00658
- Plan Check / Job No.
- B11VN01815
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- ADD STRUCTURAL DECK ON FOUR PILES/GB TO REAR OF SFD
- Permit Issued
- Issued on 5/12/2011
- Issuing Office
- Valley
- Current Status
- Issued on 5/12/2011
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/3/2011 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2011 | DEAN LEE |
| Green Plans Picked Up | 3/15/2011 | APPLICANT |
| Corrections Issued | 3/16/2011 | DEAN LEE |
| Quality Review Completed | 3/22/2011 | DOUGLAS NAKATANI |
| Building Plans Picked Up | 3/23/2011 | APPLICANT |
| Applicant returned to address corrections | 4/7/2011 | DEAN LEE |
| Applicant returned to address corrections | 4/25/2011 | DEAN LEE |
| Plan Check Approved | 5/12/2011 | DEAN LEE |
| Issued | 5/12/2011 | LADBS |
| Permit Expired-Status Void | 10/14/2014 | RAUL BARAJAS |
| Re-Activate Permit | 12/3/2025 | RAUL BARAJAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/25/2011 | LEE GUILBEAUX |
| Hillside ordinance | Cleared | 4/25/2011 | LEE GUILBEAUX |
| Hillside ordinance | Cleared | 4/25/2011 | LEE GUILBEAUX |
| Excavation more than 5-ft deep | Cleared | 4/26/2011 | CALOSHA APPROVED |
| Green Code | Cleared | 4/28/2011 | PETER FOLLING |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | , ; Lic. No.: C76828 | 21243 VENTURA BL 131 LA, CA 91364 |
| Engineer | Robles, Gustavo; Lic. No.: C66797 | PO BOX 682 SAN DIMAS, CA 91773 |
| Geologist | Robles, Gustavo; Lic. No.: EG2422 | PO BOX 682 SAN DIMAS, CA 91773 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/26/2011 | Not Ready for Inspection | RAUL BARAJAS |
| Piling/Pier/Caisson | 6/3/2011 | Conditional Approval | RAUL BARAJAS |
| Special/Order Compliance | 11/7/2011 | No Access for Inspection | RAUL BARAJAS |
| Final | 10/10/2014 | Not Ready for Inspection | RAUL BARAJAS |
| Special/Order Compliance | 12/3/2025 | Corrections Issued | SCOTT FINNILA |
| Pre-Inspection | 12/11/2025 | Partial Inspection | RAUL BARAJAS |
| Special/Order Compliance | 12/11/2025 | Partial Inspection | BRIAN SULLIVAN |