1303 S MEADOWBROOK AVE 90019
Certificate Information: 1303 S MEADOWBROOK AVE 90019
- Application / Permit
- 11014-10000-03882
- Plan Check / Job No.
- B11LA11873
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-FLOOR ADDITION W/ BALCONY TO (E) 1-STORY SFD; ADD (N) STAIR ON 1ST FLOOR.
- Permit Issued
- Issued on 12/20/2011
- Issuing Office
- Metro
- Current Status
- Issued on 12/20/2011
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/31/2011 | APPLICANT |
| Assigned to Plan Check Engineer | 11/3/2011 | MINH VALENZUELA |
| Green Plans Picked Up | 11/16/2011 | APPLICANT |
| Corrections Issued | 11/18/2011 | MINH VALENZUELA |
| Quality Review Completed | 11/30/2011 | ARA SARGSYAN |
| Building Plans Picked Up | 12/1/2011 | APPLICANT |
| Plan Check Approved | 12/19/2011 | LARRY LEE |
| Issued | 12/20/2011 | LADBS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/14/2011 | VALENTINO PUEBLOS |
| Roof/Waste drainage to street | Cleared | 12/14/2011 | VALENTINO PUEBLOS |
| Sewer availability | Cleared | 12/14/2011 | VALENTINO PUEBLOS |
| Green Code | Cleared | 12/19/2011 | RUBEN SALAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/13/2012 | Corrections Issued | ROBERT MCDOWELL |
| METHANE-Barrier | 1/13/2012 | Approved | ROBERT MCDOWELL |
| METHANE-Subgrade | 1/13/2012 | Approved | ROBERT MCDOWELL |
| Excavation/Setback/Form/Re-Bar | 1/17/2012 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2012 | Not Ready for Inspection | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 3/1/2012 | Partial Inspection | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 3/1/2012 | Approved | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 3/1/2012 | Approved | ROBERT MCDOWELL |
| Green Building Final | 3/1/2012 | Not Ready for Inspection | DONALD CRICHLOW |
| Green Building Rough | 3/1/2012 | Corrections Issued | DONALD CRICHLOW |
| HVAC-Rough | 3/1/2012 | Approved | ROBERT MCDOWELL |
| Light Gage Steel Frame | 3/1/2012 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 3/1/2012 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 3/1/2012 | SGSOV Not Ready | ROBERT MCDOWELL |
| Smoke Detectors | 3/1/2012 | Not Ready for Inspection | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 3/14/2012 | Corrections Issued | GOURGEN PETROSSIAN |
| Green Building Rough | 3/14/2012 | Partial Approval | DONALD CRICHLOW |
| Green Building Rough | 3/16/2012 | Approved | DONALD CRICHLOW |
| Insulation | 3/19/2012 | Approved | GOURGEN PETROSSIAN |
| Drywall Nailing | 3/28/2012 | Approved | TODD MALAND |
| Interior/Exterior Lathing | 3/28/2012 | Approved | TODD MALAND |
| BUILDING-Rough-Frame | 10/6/2021 | Corrections Issued | JUSTIN HAWLEY |
| Final | 10/6/2021 | Not Ready for Inspection | JUSTIN HAWLEY |
| Green Building Final | 10/6/2021 | Not Ready for Inspection | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 10/6/2021 | SGSOV Not Ready | JUSTIN HAWLEY |
| Smoke Detectors | 10/6/2021 | Not Ready for Inspection | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 1/5/2022 | Not Ready for Inspection | JOSE AVILA |
| Final | 1/5/2022 | Corrections Issued | JOSE AVILA |
| Green Building Final | 1/5/2022 | Not Ready for Inspection | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 1/5/2022 | SGSOV Not Ready | JOSE AVILA |
| Smoke Detectors | 1/5/2022 | Not Ready for Inspection | JOSE AVILA |
| BUILDING-Rough-Frame | 1/13/2022 | Not Ready for Inspection | JOSE AVILA |
| Final | 1/13/2022 | Corrections Issued | JOSE AVILA |
| Green Building Final | 1/13/2022 | Not Ready for Inspection | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 1/13/2022 | SGSOV Not Ready | JOSE AVILA |
| Smoke Detectors | 1/13/2022 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 6/7/2022 | Corrections Issued | JOSE AVILA |
| Final | 6/7/2022 | Corrections Issued | JOSE AVILA |
| Green Building Final | 6/7/2022 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 6/7/2022 | SGSOV Not Ready | JOSE AVILA |
| Smoke Detectors | 6/7/2022 | Corrections Issued | JOSE AVILA |
| Pre-Inspection | 7/21/2025 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 7/22/2025 | Approved | ARTHUR NEGRETE |
| Final | 7/22/2025 | Partial Approval | ARTHUR NEGRETE |
| Green Building Final | 7/22/2025 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 7/22/2025 | SGSOV Approved | ARTHUR NEGRETE |
| Smoke Detectors | 7/22/2025 | Approved | ARTHUR NEGRETE |
| Final | 11/5/2025 | Corrections Issued | JUSTIN HAWLEY |