901 W OLYMPIC BLVD 90015

Certificate Information: 901 W OLYMPIC BLVD 90015

Application / Permit
11010-10000-01477
Plan Check / Job No.
B11LA07408
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(11) Hotel
Work Description
New 23-story hotel with 393 hotel rooms with one level of basement. kitchen and restaurant are core and shell only, the rest of the building is full permit.
Permit Issued
Issued on 6/21/2012
Issuing Office
Metro
Current Status
CofO Issued on 2/23/2015
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/18/2011 APPLICANT
Assigned to Plan Check Engineer 8/25/2011 LARRY LEE
Corrections Issued 9/8/2011 LARRY LEE
Quality Review Completed 9/14/2011 CHARLES CHANG
Building Plans Picked Up 9/14/2011 APPLICANT
Applicant returned to address corrections 9/15/2011 LARRY LEE
Applicant returned to address corrections 1/18/2012 LARRY LEE
Applicant returned to address corrections 1/24/2012 LARRY LEE
Applicant returned to address corrections 2/17/2012 LARRY LEE
Applicant returned to address corrections 2/22/2012 LARRY LEE
Applicant returned to address corrections 2/23/2012 LARRY LEE
Applicant returned to address corrections 2/27/2012 CHARLES CHANG
Applicant returned to address corrections 2/29/2012 CHARLES CHANG
Plan Check Approved 6/21/2012 LARRY LEE
Issued 6/21/2012 HENRY TONGSON
TCO Issued (Expire Date: 11-05-2014) 5/9/2014 HAMID PISHEHVAR
TCO Issued (Expire Date: 05-04-2015) 11/5/2014 ANDREW CROMER
CofO in Progress 2/18/2015 SAKO AGHAZARIAN
Permit Finaled 2/23/2015 HAMID PISHEHVAR
CofO Issued 2/23/2015 HAMID PISHEHVAR
Permit Finaled 2/23/2015 HAMID PISHEHVAR

Permit Application Clearance Information

CPC Cleared 9/6/2011 TINA VACHARKULKSEMSU
CPC Cleared 9/6/2011 TINA VACHARKULKSEMSU
CPC Cleared 9/6/2011 TINA VACHARKULKSEMSU
CPC Cleared 9/6/2011 TINA VACHARKULKSEMSU
Miscellaneous Cleared 9/6/2011 TINA VACHARKULKSEMSU
Address approval Cleared 10/6/2011 DAVID CHIN
Eng Process Fee Ord 176,300 Cleared 10/6/2011 NATALIE MOORE
Sewer availability Cleared 10/14/2011 AVALYN KAMACHI
Project located in CRA area Cleared 1/23/2012 JIM URQUHART
Hydrant and Access approval Cleared 3/7/2012 JOHN DALLAS
Stormwater Pollution Mitigatn Cleared 3/8/2012 AMMAR ELTAWIL
Permit Cleared 3/28/2012 DANIEL SUE
Roof/Waste drainage to street Cleared 3/28/2012 DANIEL SUE
Work Adjacent to Public Way Cleared 4/17/2012 TERRY PHAN
Green Code Cleared 5/11/2012 ALDO UBAU
DAS Clearance Cleared 5/22/2012 LARRY LEE
Title 19 building approval Cleared 6/15/2012 DAVE MYERS
CPC Cleared 6/19/2012 TINA VACHARKULKSEMSU
Miscellaneous Cleared 6/19/2012 TINA VACHARKULKSEMSU
Miscellaneous Cleared 6/19/2012 TINA VACHARKULKSEMSU
Opn space landscape/Water mgmt Cleared 6/19/2012 TINA VACHARKULKSEMSU
Site Plan review Cleared 6/19/2012 TINA VACHARKULKSEMSU
Specific Plan Cleared 6/19/2012 TINA VACHARKULKSEMSU
Driveway location Cleared 6/20/2012 COLLINS ALLAN
Building over 3-story or 36-ft Cleared 6/21/2012 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 6/21/2012 CALOSHA APPROVED
Food Service Establishment Cleared 6/21/2012 KENNETH BROWNE
Highway dedication Cleared 6/21/2012 ARMENIA HERNANDEZ

Contact Information

Architect Johnson, Kevin Paul; Lic. No.: C30343 10855 SE OREGOLD CT.      HAPPY VALLEY, OR 97086
Contractor Sodo Builders La L L C; Lic. No.: 972792-B 930 GEORGIA STREET      LOS ANGELES, CA 90015
Engineer Heeringa, Roger L; Lic. No.: S4536 818 STEWART ST #1000      SEATTLE, WA 98101

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/2/2012 Partial Inspection SAKO AGHAZARIAN
METHANE-Barrier 7/2/2012 Partial Inspection SAKO AGHAZARIAN
METHANE-Subgrade 7/2/2012 Partial Inspection SAKO AGHAZARIAN
Footing/Foundation/Slab 7/6/2012 Partial Approval SAKO AGHAZARIAN
Green Building Rough 7/6/2012 Partial Inspection DONALD CRICHLOW
METHANE-Barrier 7/6/2012 Approved SAKO AGHAZARIAN
METHANE-Rough 7/6/2012 Approved SAKO AGHAZARIAN
METHANE-Subgrade 7/6/2012 Approved SAKO AGHAZARIAN
Reinforced Concrete Frame 7/6/2012 Partial Approval SAKO AGHAZARIAN
Excavation/Setback/Form/Re-Bar 7/11/2012 Partial Inspection SAKO AGHAZARIAN
Footing/Foundation/Slab 7/16/2012 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/17/2012 Approved SAKO AGHAZARIAN
Footing/Foundation/Slab 7/20/2012 Partial Inspection SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/24/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/25/2012 Approved SAKO AGHAZARIAN
Footing/Foundation/Slab 7/25/2012 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/26/2012 Approved SAKO AGHAZARIAN
Excavation/Setback/Form/Re-Bar 7/26/2012 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/27/2012 Approved SAKO AGHAZARIAN
Footing/Foundation/Slab 7/27/2012 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/30/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/31/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/1/2012 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/2/2012 Approved SAKO AGHAZARIAN
Deputy Shotcrete 8/2/2012 Approved SAKO AGHAZARIAN
Footing/Foundation/Slab 8/2/2012 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/3/2012 Approved SAKO AGHAZARIAN
Deputy Shotcrete 8/3/2012 Approved SAKO AGHAZARIAN
Deputy Shotcrete 8/6/2012 Approved SAKO AGHAZARIAN
Footing/Foundation/Slab 8/6/2012 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/7/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/8/2012 Conditional Approval JOHN CARPENTER
Deputy Reinf. Concrete 8/9/2012 Conditional Approval JOHN CARPENTER
Deputy Reinf. Concrete 8/10/2012 Conditional Approval JOHN CARPENTER
Deputy Reinf. Concrete 8/13/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/14/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/15/2012 Approved SAKO AGHAZARIAN
Footing/Foundation/Slab 8/15/2012 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/16/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/17/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/20/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/21/2012 Approved SAKO AGHAZARIAN
Green Building Rough 8/21/2012 Not Ready for Inspection RUBEN SALAS
Reinforced Concrete Frame 8/21/2012 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/22/2012 Approved SAKO AGHAZARIAN
Deputy Shotcrete 8/22/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/23/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/24/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/27/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/28/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/31/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 9/4/2012 Approved SAKO AGHAZARIAN
Footing/Foundation/Slab 9/4/2012 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 9/5/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 9/6/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 9/7/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 9/10/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 9/11/2012 Order to Comply Issued SAKO AGHAZARIAN
Deputy Reinf. Concrete 9/12/2012 Approved SAKO AGHAZARIAN
Pre-Inspection 9/12/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 9/13/2012 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/14/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 9/17/2012 Partial Approval WILLIAM GARCIA
Deputy Reinf. Concrete 9/18/2012 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/19/2012 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/20/2012 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 9/20/2012 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 9/21/2012 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 9/24/2012 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 9/24/2012 Approved SAKO AGHAZARIAN
Excavation/Setback/Form/Re-Bar 9/24/2012 Partial Approval SAKO AGHAZARIAN
Green Building Rough 9/24/2012 Not Ready for Inspection RUBEN SALAS
Reinforced Concrete Frame 9/24/2012 Partial Approval SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 9/25/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 9/25/2012 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 9/26/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 9/26/2012 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 9/27/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 9/27/2012 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 9/28/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 9/28/2012 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 10/1/2012 Approved SAKO AGHAZARIAN
Green Building Rough 10/1/2012 Not Ready for Inspection RUSSELL KELLY
Reinforced Concrete Frame 10/1/2012 Partial Approval SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 10/2/2012 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 10/3/2012 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 10/4/2012 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 10/5/2012 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 10/9/2012 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 10/10/2012 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 10/11/2012 Approved SAKO AGHAZARIAN
Excavation/Setback/Form/Re-Bar 10/11/2012 Partial Approval SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 10/12/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 10/12/2012 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 10/12/2012 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 10/15/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 10/16/2012 Approved SAKO AGHAZARIAN
Excavation/Setback/Form/Re-Bar 10/16/2012 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 10/19/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 10/22/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 10/23/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 10/24/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 10/25/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 10/26/2012 Partial Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 10/29/2012 Approved SAKO AGHAZARIAN
Excavation/Setback/Form/Re-Bar 10/30/2012 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 11/1/2012 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 11/5/2012 Approved SAKO AGHAZARIAN
Excavation/Setback/Form/Re-Bar 11/5/2012 Partial Approval SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 11/6/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 11/6/2012 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 11/7/2012 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 11/7/2012 Partial Approval SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 11/8/2012 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 11/9/2012 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 11/13/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 11/13/2012 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 11/14/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 11/14/2012 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 11/15/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 11/15/2012 Approved SAKO AGHAZARIAN
Green Building Rough 11/15/2012 Not Ready for Inspection MICHAEL TUCK
Reinforced Concrete Frame 11/15/2012 Partial Approval SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 11/16/2012 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/16/2012 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/19/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 11/20/2012 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 11/20/2012 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 11/21/2012 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 12/3/2012 Approved SAKO AGHAZARIAN
Footing/Foundation/Slab 12/3/2012 Partial Approval SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 12/4/2012 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 12/5/2012 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 12/6/2012 Approved SAKO AGHAZARIAN
Footing/Foundation/Slab 12/6/2012 Partial Approval SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 12/7/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 12/7/2012 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 12/10/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 12/10/2012 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 12/11/2012 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 12/12/2012 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 12/13/2012 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 12/14/2012 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 12/18/2012 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 12/19/2012 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 12/20/2012 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 12/21/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 12/21/2012 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 12/21/2012 Partial Approval SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 12/24/2012 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 12/26/2012 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 12/27/2012 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 12/28/2012 Approved SAKO AGHAZARIAN
Deputy Shotcrete 12/28/2012 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 12/28/2012 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 1/2/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 1/2/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 1/3/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 1/3/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 1/4/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 1/4/2013 Approved SAKO AGHAZARIAN
Green Building Rough 1/4/2013 Not Ready for Inspection MICHAEL TUCK
Reinforced Concrete Frame 1/4/2013 Partial Approval SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 1/7/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 1/7/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 1/8/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 1/8/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 1/9/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 1/10/2013 Approved MICHAEL KUHN
Deputy Pre-Stress Concrete 1/11/2013 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/14/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 1/15/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 1/16/2013 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 1/16/2013 Partial Inspection SAKO AGHAZARIAN
Deputy Reinf. Concrete 1/17/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 1/18/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 1/22/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 1/23/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 1/24/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 1/25/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 1/25/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 1/28/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 1/30/2013 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 1/30/2013 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 1/31/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 2/4/2013 Approved MICHAEL KUHN
Deputy Pre-Stress Concrete 2/5/2013 Approved SAKO AGHAZARIAN
Masonry Wall/Backfill 2/5/2013 Partial Approval SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 2/6/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 2/6/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 2/7/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 2/7/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 2/8/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 2/8/2013 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 2/8/2013 Partial Approval SAKO AGHAZARIAN
Masonry Wall/Backfill 2/8/2013 Partial Approval SAKO AGHAZARIAN
Deputy Shotcrete 2/11/2013 Approved SAKO AGHAZARIAN
Deputy Shotcrete 2/12/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 2/13/2013 Approved SAKO AGHAZARIAN
Deputy Shotcrete 2/13/2013 Approved SAKO AGHAZARIAN
Masonry Wall/Backfill 2/13/2013 Partial Approval SAKO AGHAZARIAN
Deputy Shotcrete 2/14/2013 Approved SAKO AGHAZARIAN
Deputy Shotcrete 2/15/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 2/19/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 2/19/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 2/19/2013 Partial Inspection SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 2/19/2013 Partial Approval SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 2/20/2013 Approved SAKO AGHAZARIAN
Masonry Wall/Backfill 2/20/2013 Partial Approval SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 2/21/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 2/21/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 2/22/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 2/25/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 2/26/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 2/27/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 2/27/2013 Partial Approval SAKO AGHAZARIAN
Masonry Wall/Backfill 2/27/2013 Partial Inspection SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 2/28/2013 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 2/28/2013 Partial Approval SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 3/1/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 3/1/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 3/4/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 3/5/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 3/6/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 3/6/2013 Approved SAKO AGHAZARIAN
Masonry Wall/Backfill 3/6/2013 Partial Approval SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 3/7/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 3/8/2013 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 3/11/2013 Partial Inspection SAKO AGHAZARIAN
Masonry Wall/Backfill 3/11/2013 Partial Approval SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 3/18/2013 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 3/18/2013 Partial Approval SAKO AGHAZARIAN
Masonry Wall/Backfill 3/18/2013 Partial Approval SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 3/19/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 3/19/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 3/19/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 3/20/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 3/21/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 3/22/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 3/26/2013 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 3/26/2013 Partial Approval SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 3/27/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 3/27/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 3/27/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 3/28/2013 Partial Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 3/29/2013 Partial Approval LESLIE TRUJILLO
Masonry Wall/Backfill 3/29/2013 Partial Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 4/1/2013 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/1/2013 Partial Approval LESLIE TRUJILLO
Deputy Steel/Welding 4/1/2013 Partial Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 4/1/2013 Partial Approval LESLIE TRUJILLO
Deputy Other (see comments) 4/2/2013 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 4/2/2013 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/2/2013 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/2/2013 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 4/3/2013 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/3/2013 Partial Approval LESLIE TRUJILLO
Deputy Steel/Welding 4/3/2013 Partial Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 4/4/2013 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/4/2013 Partial Approval LESLIE TRUJILLO
Deputy Steel/Welding 4/4/2013 Partial Approval LESLIE TRUJILLO
Masonry Wall/Backfill 4/4/2013 Partial Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 4/5/2013 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/5/2013 Partial Approval LESLIE TRUJILLO
Deputy Steel/Welding 4/5/2013 Partial Approval LESLIE TRUJILLO
Deputy Drilled-In Anchors 4/8/2013 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/8/2013 Partial Approval LESLIE TRUJILLO
Deputy Steel/Welding 4/8/2013 Partial Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 4/8/2013 Partial Approval LESLIE TRUJILLO
Deputy Drilled-In Anchors 4/9/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 4/9/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 4/9/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 4/9/2013 Partial Approval SAKO AGHAZARIAN
Masonry Wall/Backfill 4/9/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 4/10/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 4/10/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 4/10/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 4/11/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 4/11/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 4/11/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 4/12/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 4/12/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 4/12/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 4/12/2013 Partial Inspection SAKO AGHAZARIAN
Pre-Inspection 4/12/2013 Partial Inspection SAKO AGHAZARIAN
Deputy Drilled-In Anchors 4/15/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 4/15/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 4/15/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Masonry 4/15/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 4/15/2013 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 4/15/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 4/16/2013 Approved MICHAEL KUHN
Deputy Pre-Stress Concrete 4/16/2013 Approved MICHAEL KUHN
Deputy Reinf. Concrete 4/16/2013 Approved MICHAEL KUHN
Deputy Reinf. Masonry 4/16/2013 Approved MICHAEL KUHN
Deputy Steel/Welding 4/16/2013 Approved MICHAEL KUHN
Deputy Drilled-In Anchors 4/17/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 4/17/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 4/17/2013 Approved SAKO AGHAZARIAN
Insulation 4/17/2013 Partial Inspection SAKO AGHAZARIAN
Masonry Wall/Backfill 4/17/2013 Partial Inspection SAKO AGHAZARIAN
Deputy Drilled-In Anchors 4/18/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 4/18/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 4/18/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 4/18/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 4/19/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 4/19/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 4/19/2013 Approved SAKO AGHAZARIAN
Insulation 4/19/2013 Partial Inspection SAKO AGHAZARIAN
Deputy Drilled-In Anchors 4/22/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 4/22/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 4/22/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 4/22/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 4/23/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 4/23/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 4/23/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 4/23/2013 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 4/23/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 4/24/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 4/24/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 4/24/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 4/24/2013 Approved SAKO AGHAZARIAN
Insulation 4/24/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 4/25/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 4/25/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 4/25/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 4/25/2013 Approved SAKO AGHAZARIAN
Masonry Wall/Backfill 4/25/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 4/26/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 4/26/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 4/26/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 4/26/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 4/29/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 4/29/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 4/29/2013 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 4/29/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 4/30/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 4/30/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 4/30/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 4/30/2013 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 4/30/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 5/1/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 5/1/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 5/1/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/1/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 5/2/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 5/2/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 5/2/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/2/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 5/3/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 5/3/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 5/3/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/3/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 5/6/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 5/6/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 5/6/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/6/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 5/6/2013 Partial Inspection SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 5/6/2013 Partial Approval SAKO AGHAZARIAN
Insulation 5/6/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 5/7/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 5/7/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 5/7/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/7/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 5/8/2013 Approved SAKO AGHAZARIAN
Deputy Other (see comments) 5/8/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 5/8/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 5/8/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/8/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 5/9/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 5/9/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 5/9/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/9/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 5/10/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 5/10/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 5/10/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/10/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 5/13/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 5/13/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/13/2013 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 5/13/2013 Partial Approval SAKO AGHAZARIAN
Insulation 5/13/2013 Partial Inspection SAKO AGHAZARIAN
Deputy Drilled-In Anchors 5/14/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 5/14/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/14/2013 Approved SAKO AGHAZARIAN
Insulation 5/14/2013 Partial Inspection SAKO AGHAZARIAN
Deputy Drilled-In Anchors 5/15/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 5/15/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/15/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 5/16/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 5/16/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/16/2013 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 5/16/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 5/17/2013 Conditional Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 5/17/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/17/2013 Approved SAKO AGHAZARIAN
Insulation 5/17/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 5/20/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 5/20/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 5/20/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/20/2013 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 5/20/2013 Partial Approval SAKO AGHAZARIAN
Insulation 5/20/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 5/21/2013 Approved SAKO AGHAZARIAN
Deputy Other (see comments) 5/21/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 5/21/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 5/21/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/21/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 5/22/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 5/22/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 5/22/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/22/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 5/23/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 5/23/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 5/23/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/23/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 5/24/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 5/24/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 5/24/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/24/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 5/28/2013 Partial Approval WILLIAM GARCIA
Deputy Pre-Stress Concrete 5/28/2013 Partial Approval WILLIAM GARCIA
Deputy Reinf. Concrete 5/28/2013 Partial Approval WILLIAM GARCIA
Deputy Steel/Welding 5/28/2013 Partial Approval WILLIAM GARCIA
Insulation 5/28/2013 Partial Inspection WILLIAM GARCIA
Deputy Drilled-In Anchors 5/29/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 5/29/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 5/29/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/29/2013 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 5/29/2013 Partial Approval SAKO AGHAZARIAN
Light Gage Steel Frame 5/29/2013 Partial Inspection SAKO AGHAZARIAN
Deputy Drilled-In Anchors 5/30/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 5/30/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 5/30/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/30/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 5/31/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 5/31/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 5/31/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 5/31/2013 Approved SAKO AGHAZARIAN
Light Gage Steel Frame 5/31/2013 Corrections Issued SAKO AGHAZARIAN
Deputy Drilled-In Anchors 6/3/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 6/3/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 6/3/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 6/3/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 6/4/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 6/4/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 6/4/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 6/4/2013 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 6/4/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 6/5/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 6/5/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 6/5/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 6/5/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 6/6/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 6/6/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 6/6/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 6/6/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 6/6/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 6/7/2013 Approved SAKO AGHAZARIAN
Deputy Other (see comments) 6/7/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 6/7/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 6/7/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 6/7/2013 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 6/7/2013 Partial Approval SAKO AGHAZARIAN
Insulation 6/7/2013 Partial Inspection SAKO AGHAZARIAN
Deputy Drilled-In Anchors 6/10/2013 Approved SAKO AGHAZARIAN
Deputy Other (see comments) 6/10/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 6/10/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 6/10/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 6/10/2013 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 6/10/2013 Partial Approval SAKO AGHAZARIAN
Insulation 6/10/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 6/11/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 6/11/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 6/11/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 6/11/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 6/12/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 6/12/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 6/12/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 6/12/2013 Approved SAKO AGHAZARIAN
Insulation 6/12/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 6/13/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 6/13/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 6/13/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 6/13/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 6/13/2013 Partial Inspection SAKO AGHAZARIAN
Deputy Drilled-In Anchors 6/14/2013 Approved SAKO AGHAZARIAN
Deputy Other (see comments) 6/14/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 6/14/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 6/14/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 6/14/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 6/17/2013 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 6/17/2013 Partial Approval SAKO AGHAZARIAN
Insulation 6/17/2013 Partial Approval SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 6/18/2013 Approved SAKO AGHAZARIAN
Insulation 6/18/2013 Partial Inspection SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 6/19/2013 Approved SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 6/20/2013 Approved SAKO AGHAZARIAN
Insulation 6/20/2013 Partial Approval SAKO AGHAZARIAN
Deputy Pre-Stress Concrete 6/21/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 6/24/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 6/24/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 6/24/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 6/25/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 6/25/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 6/25/2013 Approved SAKO AGHAZARIAN
Insulation 6/25/2013 Partial Inspection SAKO AGHAZARIAN
Deputy Drilled-In Anchors 6/26/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 6/26/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 6/26/2013 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 6/26/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 6/27/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 6/27/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 6/27/2013 Approved SAKO AGHAZARIAN
Insulation 6/27/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 6/28/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 6/28/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 6/28/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 7/2/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/2/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/2/2013 Approved SAKO AGHAZARIAN
Insulation 7/2/2013 Partial Inspection SAKO AGHAZARIAN
Interior/Exterior Lathing 7/2/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 7/3/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/3/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/3/2013 Approved SAKO AGHAZARIAN
Insulation 7/3/2013 Partial Inspection SAKO AGHAZARIAN
Deputy Drilled-In Anchors 7/5/2013 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 7/5/2013 Partial Approval LESLIE TRUJILLO
Deputy Steel/Welding 7/5/2013 Partial Approval LESLIE TRUJILLO
Green Building Rough 7/5/2013 Partial Inspection DONALD CRICHLOW
Deputy Drilled-In Anchors 7/8/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/8/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/8/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 7/8/2013 Partial Inspection SAKO AGHAZARIAN
Green Building Rough 7/8/2013 Partial Approval MICHAEL TUCK
Light Gage Steel Frame 7/8/2013 Partial Inspection SAKO AGHAZARIAN
Deputy Drilled-In Anchors 7/9/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/9/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/9/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 7/10/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/10/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/10/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 7/10/2013 Partial Approval SAKO AGHAZARIAN
Insulation 7/10/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 7/11/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/11/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/11/2013 Approved SAKO AGHAZARIAN
Insulation 7/11/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 7/12/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/12/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/12/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 7/15/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/15/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/15/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 7/16/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/16/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/16/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 7/16/2013 Partial Approval SAKO AGHAZARIAN
Insulation 7/16/2013 Partial Approval SAKO AGHAZARIAN
Light Gage Steel Frame 7/16/2013 Partial Inspection SAKO AGHAZARIAN
Deputy Drilled-In Anchors 7/17/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/17/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/17/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 7/17/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 7/18/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/18/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/18/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 7/18/2013 Partial Approval SAKO AGHAZARIAN
Insulation 7/18/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 7/19/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/19/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/19/2013 Approved SAKO AGHAZARIAN
Insulation 7/19/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 7/22/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/22/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/22/2013 Approved SAKO AGHAZARIAN
Light Gage Steel Frame 7/22/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 7/23/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/23/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/23/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 7/24/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/24/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/24/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 7/24/2013 Partial Approval SAKO AGHAZARIAN
Insulation 7/24/2013 Partial Approval SAKO AGHAZARIAN
Light Gage Steel Frame 7/24/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 7/25/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/25/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/25/2013 Approved SAKO AGHAZARIAN
Floor/Roof Diaphrgm/Shear Wall 7/25/2013 Partial Approval SAKO AGHAZARIAN
Insulation 7/25/2013 Partial Inspection SAKO AGHAZARIAN
Light Gage Steel Frame 7/25/2013 Partial Inspection SAKO AGHAZARIAN
Deputy Drilled-In Anchors 7/26/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/26/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/26/2013 Approved SAKO AGHAZARIAN
Insulation 7/26/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 7/29/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/29/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/29/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 7/29/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 7/30/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/30/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/30/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 7/30/2013 Partial Inspection SAKO AGHAZARIAN
Deputy Drilled-In Anchors 7/31/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 7/31/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 7/31/2013 Approved SAKO AGHAZARIAN
Insulation 7/31/2013 Partial Approval SAKO AGHAZARIAN
Light Gage Steel Frame 7/31/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 8/1/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/1/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 8/1/2013 Approved SAKO AGHAZARIAN
Insulation 8/1/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 8/2/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/2/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 8/2/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 8/2/2013 Partial Approval SAKO AGHAZARIAN
Drywall Nailing 8/2/2013 Partial Inspection SAKO AGHAZARIAN
Insulation 8/2/2013 Partial Approval SAKO AGHAZARIAN
Insulation 8/2/2013 Partial Inspection SAKO AGHAZARIAN
Deputy Drilled-In Anchors 8/5/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/5/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 8/5/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 8/6/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/6/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 8/6/2013 Approved SAKO AGHAZARIAN
Light Gage Steel Frame 8/6/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 8/7/2013 Approved SAKO AGHAZARIAN
Deputy Other (see comments) 8/7/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/7/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 8/7/2013 Approved SAKO AGHAZARIAN
Insulation 8/7/2013 Partial Approval SAKO AGHAZARIAN
Light Gage Steel Frame 8/7/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 8/8/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/8/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 8/8/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 8/8/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 8/9/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/9/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 8/9/2013 Approved SAKO AGHAZARIAN
Light Gage Steel Frame 8/9/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 8/12/2013 Approved SAKO AGHAZARIAN
Deputy Other (see comments) 8/12/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/12/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 8/12/2013 Approved SAKO AGHAZARIAN
Insulation 8/12/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 8/13/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/13/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 8/13/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 8/13/2013 Partial Approval SAKO AGHAZARIAN
Insulation 8/13/2013 Partial Approval SAKO AGHAZARIAN
Light Gage Steel Frame 8/13/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 8/14/2013 Approved SAKO AGHAZARIAN
Deputy Other (see comments) 8/14/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/14/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 8/14/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 8/15/2013 Approved SAKO AGHAZARIAN
Deputy Other (see comments) 8/15/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/15/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 8/15/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 8/15/2013 Partial Approval SAKO AGHAZARIAN
Light Gage Steel Frame 8/15/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 8/16/2013 Approved SAKO AGHAZARIAN
Deputy Other (see comments) 8/16/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/16/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 8/16/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 8/19/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/19/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 8/19/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 8/19/2013 Partial Approval SAKO AGHAZARIAN
Insulation 8/19/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 8/20/2013 Approved SAKO AGHAZARIAN
Deputy Other (see comments) 8/20/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/20/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 8/20/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 8/21/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/21/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 8/21/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 8/22/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/22/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 8/22/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 8/22/2013 Partial Approval SAKO AGHAZARIAN
Insulation 8/22/2013 Partial Approval SAKO AGHAZARIAN
Light Gage Steel Frame 8/22/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 8/23/2013 Approved SAKO AGHAZARIAN
Deputy Other (see comments) 8/23/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/23/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 8/23/2013 Approved SAKO AGHAZARIAN
Insulation 8/23/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 8/26/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/26/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 8/26/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 8/26/2013 Partial Approval SAKO AGHAZARIAN
Insulation 8/26/2013 Partial Inspection SAKO AGHAZARIAN
Light Gage Steel Frame 8/26/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 8/27/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/27/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 8/27/2013 Approved SAKO AGHAZARIAN
Light Gage Steel Frame 8/27/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 8/28/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/28/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 8/28/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 8/29/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/29/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 8/29/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 8/29/2013 Partial Approval SAKO AGHAZARIAN
Light Gage Steel Frame 8/29/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 8/30/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 8/30/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 8/30/2013 Approved SAKO AGHAZARIAN
Insulation 8/30/2013 Partial Approval SAKO AGHAZARIAN
Drywall Nailing 9/5/2013 Partial Inspection MICHAEL KUHN
Light Gage Steel Frame 9/5/2013 Partial Inspection MICHAEL KUHN
Insulation 9/6/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 9/9/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 9/9/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 9/9/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 9/9/2013 Partial Approval SAKO AGHAZARIAN
Interior/Exterior Lathing 9/9/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 9/10/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 9/10/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 9/10/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 9/10/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 9/11/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 9/11/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 9/11/2013 Approved SAKO AGHAZARIAN
Insulation 9/11/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 9/12/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 9/12/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Masonry 9/12/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 9/12/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 9/12/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 9/13/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 9/13/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 9/13/2013 Approved SAKO AGHAZARIAN
Light Gage Steel Frame 9/16/2013 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Masonry 9/17/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Masonry 9/18/2013 Approved SAKO AGHAZARIAN
Insulation 9/18/2013 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Masonry 9/19/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Masonry 9/20/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 9/20/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 9/23/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 9/23/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 9/23/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 9/24/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 9/24/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 9/24/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 9/25/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 9/25/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 9/25/2013 Approved SAKO AGHAZARIAN
Light Gage Steel Frame 9/25/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 9/26/2013 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/26/2013 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/26/2013 Partial Approval JAMES POWERS
Insulation 9/26/2013 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 9/27/2013 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/27/2013 Partial Approval LESLIE TRUJILLO
Deputy Steel/Welding 9/27/2013 Partial Approval LESLIE TRUJILLO
Deputy Drilled-In Anchors 9/30/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 9/30/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 9/30/2013 Approved SAKO AGHAZARIAN
Insulation 9/30/2013 Partial Approval SAKO AGHAZARIAN
Light Gage Steel Frame 9/30/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 10/1/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 10/1/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 10/1/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 10/2/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 10/2/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 10/2/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 10/2/2013 Partial Approval SAKO AGHAZARIAN
Light Gage Steel Frame 10/2/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 10/3/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 10/3/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 10/3/2013 Approved SAKO AGHAZARIAN
Insulation 10/3/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 10/4/2013 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 10/4/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 10/4/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 10/8/2013 Partial Approval SAKO AGHAZARIAN
Deputy Drilled-In Anchors 10/9/2013 Approved SAKO AGHAZARIAN
Deputy Seismic Resistance 10/9/2013 Approved SAKO AGHAZARIAN
Deputy Shotcrete 10/9/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 10/9/2013 Approved SAKO AGHAZARIAN
Deputy Drilled-In Anchors 10/10/2013 Approved SAKO AGHAZARIAN
Deputy Seismic Resistance 10/10/2013 Approved SAKO AGHAZARIAN
Deputy Shotcrete 10/10/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 10/10/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 10/10/2013 Partial Approval SAKO AGHAZARIAN
Light Gage Steel Frame 10/10/2013 Partial Approval SAKO AGHAZARIAN
Light Gage Steel Frame 10/11/2013 Partial Approval SAKO AGHAZARIAN
Light Gage Steel Frame 10/15/2013 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 10/16/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 10/16/2013 Approved SAKO AGHAZARIAN
Insulation 10/17/2013 Partial Approval SAKO AGHAZARIAN
Drywall Nailing 10/21/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 10/22/2013 Partial Approval SAKO AGHAZARIAN
Deputy Steel/Welding 10/23/2013 Approved SAKO AGHAZARIAN
Light Gage Steel Frame 10/30/2013 Partial Approval SAKO AGHAZARIAN
Light Gage Steel Frame 11/6/2013 Partial Approval SAKO AGHAZARIAN
Deputy Steel/Welding 11/8/2013 Approved SAKO AGHAZARIAN
Drywall Nailing 11/12/2013 Partial Approval SAKO AGHAZARIAN
Drywall Nailing 11/14/2013 Partial Inspection SAKO AGHAZARIAN
Insulation 11/14/2013 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 11/15/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 11/15/2013 Approved SAKO AGHAZARIAN
Interior/Exterior Lathing 11/15/2013 Partial Approval SAKO AGHAZARIAN
Insulation 11/19/2013 Partial Inspection SAKO AGHAZARIAN
Light Gage Steel Frame 11/19/2013 Partial Approval SAKO AGHAZARIAN
Drywall Nailing 11/25/2013 Partial Approval SAKO AGHAZARIAN
Insulation 11/25/2013 Partial Approval SAKO AGHAZARIAN
Interior/Exterior Lathing 11/25/2013 Partial Approval SAKO AGHAZARIAN
Deputy Steel/Welding 11/26/2013 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 11/27/2013 Approved SAKO AGHAZARIAN
Interior/Exterior Lathing 12/3/2013 Partial Approval SAKO AGHAZARIAN
Light Gage Steel Frame 12/3/2013 Partial Approval SAKO AGHAZARIAN
Deputy Steel/Welding 12/6/2013 Approved SAKO AGHAZARIAN
Interior/Exterior Lathing 12/9/2013 Partial Approval SAKO AGHAZARIAN
Insulation 12/23/2013 Partial Inspection SAKO AGHAZARIAN
Light Gage Steel Frame 12/23/2013 Partial Approval SAKO AGHAZARIAN
Drywall Nailing 12/31/2013 Partial Approval SAKO AGHAZARIAN
Interior/Exterior Lathing 12/31/2013 Partial Approval SAKO AGHAZARIAN
Drywall Nailing 1/8/2014 Partial Approval SAKO AGHAZARIAN
Light Gage Steel Frame 1/8/2014 Partial Approval SAKO AGHAZARIAN
Drywall Nailing 1/16/2014 Approved SAKO AGHAZARIAN
Deputy Reinf. Concrete 1/23/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 1/23/2014 Approved SAKO AGHAZARIAN
Drywall Nailing 1/24/2014 Approved SAKO AGHAZARIAN
Grading Pre-Inspection 2/13/2014 Approved SAKO AGHAZARIAN
Green Building Rough 2/13/2014 Approved MICHAEL TUCK
T-Bar Ceiling 2/13/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 2/21/2014 Approved SAKO AGHAZARIAN
Deputy Steel/Welding 2/27/2014 Partial Approval WILLIAM GARCIA
Deputy Steel/Welding 3/5/2014 Approved SAKO AGHAZARIAN
T-Bar Ceiling 3/18/2014 Approved SAKO AGHAZARIAN
Green Building Final 5/5/2014 Partial Approval MICHAEL TUCK
Final 5/6/2014 Partial Inspection SAKO AGHAZARIAN
Footing/Foundation/Slab 5/6/2014 Approved SAKO AGHAZARIAN
Reinforced Concrete Frame 5/6/2014 Approved SAKO AGHAZARIAN
SGSOV-Seismic Gas S/O Valve 5/6/2014 SGSOV Approved SAKO AGHAZARIAN
Smoke Detectors 5/6/2014 Approved SAKO AGHAZARIAN
Green Building Final 5/9/2014 Approved MICHAEL TUCK
Special/Order Compliance 10/7/2014 Approved SAKO AGHAZARIAN
Final 1/22/2015 Partial Approval SAKO AGHAZARIAN