3010 S POTOMAC AVE 90016
Certificate Information: 3010 S POTOMAC AVE 90016
- Application / Permit
- 11010-10000-00728
- Plan Check / Job No.
- B11LA03439
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW 1-CAR GARAGE AND STORAGE ROOM PER CITY OF LOS ANGELES STANDARD CONNECTIONS.
- Permit Issued
- Issued on 5/9/2011
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/6/2011 | APPLICANT |
| Assigned to Plan Check Engineer | 4/6/2011 | MINH VALENZUELA |
| Corrections Issued | 4/6/2011 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 5/9/2011 | SALVADOR QUINTANILLA |
| Plan Check Approved | 5/9/2011 | SALVADOR QUINTANILLA |
| Issued | 5/9/2011 | LADBS |
| CofO in Progress | 7/15/2022 | STUART CHAPMAN |
| Permit Finaled | 8/25/2022 | DEROLD HAUFF |
| CofO Issued | 8/25/2022 | DEROLD HAUFF |
| Permit Finaled | 8/25/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/9/2011 | JAMES MORALEZ |
| Roof/Waste drainage to street | Cleared | 5/9/2011 | JAMES MORALEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/5/2013 | Approved | DALE CARNEY |
| BUILDING-Rough-Frame | 2/6/2013 | Not Ready for Inspection | DALE CARNEY |
| Drywall Nailing | 2/6/2013 | Not Ready for Inspection | DALE CARNEY |
| Final | 2/6/2013 | Not Ready for Inspection | DALE CARNEY |
| Green Building Final | 2/6/2013 | Not Ready for Inspection | DEROLD HAUFF |
| Green Building Rough | 2/6/2013 | Not Ready for Inspection | DEROLD HAUFF |
| SGSOV-Seismic Gas S/O Valve | 2/6/2013 | SGSOV Not Ready | DALE CARNEY |
| Smoke Detectors | 2/6/2013 | Not Ready for Inspection | DALE CARNEY |
| BUILDING-Rough-Frame | 2/26/2014 | Not Ready for Inspection | DALE CARNEY |
| Drywall Nailing | 2/26/2014 | Not Ready for Inspection | DALE CARNEY |
| Final | 2/26/2014 | Not Ready for Inspection | DALE CARNEY |
| SGSOV-Seismic Gas S/O Valve | 2/26/2014 | SGSOV Not Ready | DALE CARNEY |
| Smoke Detectors | 2/26/2014 | Not Ready for Inspection | DALE CARNEY |
| BUILDING-Rough-Frame | 12/5/2014 | Not Ready for Inspection | DALE CARNEY |
| Drywall Nailing | 12/5/2014 | Not Ready for Inspection | DALE CARNEY |
| Final | 12/5/2014 | Not Ready for Inspection | DALE CARNEY |
| Green Building Final | 12/5/2014 | Not Ready for Inspection | DALE CARNEY |
| Green Building Rough | 12/5/2014 | Not Ready for Inspection | DALE CARNEY |
| SGSOV-Seismic Gas S/O Valve | 12/5/2014 | SGSOV Not Ready | DALE CARNEY |
| Smoke Detectors | 12/5/2014 | Not Ready for Inspection | DALE CARNEY |
| Final | 3/12/2015 | Not Ready for Inspection | ROBERTO LUERA |
| Pre-Inspection | 6/9/2022 | No Access for Inspection | STUART CHAPMAN |
| Pre-Inspection | 6/14/2022 | Corrections Issued | STUART CHAPMAN |
| BUILDING-Rough-Frame | 7/15/2022 | Approved | STUART CHAPMAN |
| Drywall Nailing | 7/15/2022 | Approved | STUART CHAPMAN |
| Final | 7/15/2022 | OK to Issue CofO | STUART CHAPMAN |
| Green Building Final | 7/15/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 7/15/2022 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 7/15/2022 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 7/15/2022 | Approved | STUART CHAPMAN |