2217 N FLORIAN PL 90210

Certificate Information: 2217 N FLORIAN PL 90210

Application / Permit
10047-10000-00063
Plan Check / Job No.
B09LA12565
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW SWIMMING POOL IN CONJUNCTION WITH 09014-10000-04595.
Permit Issued
Issued on 2/2/2011
Issuing Office
Metro
Current Status
CofO Issued on 2/5/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2009 APPLICANT
Assigned to Plan Check Engineer 1/21/2010 ROGER HYUN
Corrections Issued 2/1/2010 ROGER HYUN
Quality Review Completed 2/24/2010 JOHN VASQUEZ
Building Plans Picked Up 2/25/2010 APPLICANT
Applicant returned to address corrections 5/10/2010 ROGER HYUN
Applicant returned to address corrections 6/23/2010 ROGER HYUN
Plan Check Approved 6/24/2010 ROGER HYUN
Issued 2/2/2011 LADBS
CofO in Progress 1/28/2020 CARLOS MATAMOROS
Permit Finaled 2/5/2020 VINCENT COTTON
CofO Issued 2/5/2020 VINCENT COTTON
Permit Finaled 2/5/2020 VINCENT COTTON

Permit Application Clearance Information

Frnt yard landscape/Water mgmt Cleared 6/23/2010 ROBERT HEREDIA
Roof/Waste drainage to street Cleared 6/23/2010 GREGG VANDERGRIFF
Sewer availability Cleared 6/23/2010 JAMES MORALEZ
ZI Cleared 6/23/2010 ROBERT HEREDIA
Eng Process Fee Ord 176,300 Cleared 6/24/2010 VALENTINO PUEBLOS
Excavation more than 5-ft deep Cleared 6/24/2010 CALOSHA APPROVED
VHFHSZ Cleared 6/24/2010 TERRENCE O'CONNELL

Contact Information

Architect Dollar, Robert Alan; Lic. No.: C21420 8 TETHERMOON LANE      LADERA RANCH, CA 92694
Contractor Fischer Joel Construction Inc; Lic. No.: 528992-B PO BOX 341338      LOS ANGELES, CA 90064
Engineer Resnick, Bruce Daniel; Lic. No.: S3293 1929 PONTIUS AVE      LOS ANGELES, CA 90025

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/1/2011 Approved JOHN REGAN
Pre-Inspection 1/27/2012 Approved JOHN REGAN
Pre-Inspection 8/17/2012 Approved JOHN REGAN
Excavation/Setback/Form/Re-Bar 12/26/2012 Partial Approval JOHN REGAN
Pre-Gunite 3/27/2013 Partial Approval JOHN REGAN
Deputy Other (see comments) 3/28/2013 Approved JOHN REGAN
Excavation/Setback/Form/Re-Bar 4/15/2013 Partial Approval JOHN REGAN
Deputy Other (see comments) 4/16/2013 Approved JOHN REGAN
Grounding or Bonding 5/3/2013 Conditional Approval JOHN REGAN
Pool Piping 5/3/2013 Approved JOHN REGAN
Pre-Gunite 5/3/2013 Conditional Approval JOHN REGAN
Rough-Electrical 5/3/2013 Partial Approval JOHN REGAN
Deputy Shotcrete 5/13/2013 Approved JOHN REGAN
Gas Piping or Gas Test 5/23/2013 OK to Expire Permit JOHN REGAN
Pre-Gunite 11/12/2013 Conditional Approval JOHN REGAN
Grounding or Bonding 2/3/2014 Partial Approval JOHN LUMB
Final 12/31/2014 Partial Approval JOHN REGAN
Gunite 1/9/2015 Approved JOHN REGAN
Pre-Gunite 10/26/2017 Corrections Issued JOEL LAUNCHBAUGH
Rough-Plumbing 10/26/2017 Partial Inspection JOEL LAUNCHBAUGH
Enclosure/Fence 3/28/2019 Not Ready for Inspection CARLOS MATAMOROS
Enclosure/Fence 5/17/2019 Corrections Issued CARLOS MATAMOROS
Final 11/20/2019 Not Ready for Inspection CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 11/20/2019 SGSOV Approved CARLOS MATAMOROS
Final 12/2/2019 Partial Approval CARLOS MATAMOROS
Pool Equipment Noise Test 12/17/2019 Corrections Issued JOHN CORBIN
Enclosure/Fence 12/18/2019 Approved CARLOS MATAMOROS
Final 12/19/2019 Not Ready for Inspection CARLOS MATAMOROS
Pool Equipment Noise Test 12/20/2019 Approved BRYAN EPSTEIN
Final 12/30/2019 Corrections Issued CARLOS MATAMOROS
Final 12/30/2019 Partial Approval CARLOS MATAMOROS
ELECTRICAL-Final 1/27/2020 Approved CARLOS MATAMOROS
Final 1/27/2020 Partial Approval CARLOS MATAMOROS
PLUMBING-Final 1/27/2020 Approved CARLOS MATAMOROS