1142 S HIGHLAND AVE 90019
Certificate Information: 1142 S HIGHLAND AVE 90019
- Application / Permit
- 10014-20000-03979
- Plan Check / Job No.
- B10VN10201
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ADD NEW 2-STORY ADDITION (FIRST FLOOR: 2-CAR GARAGE, STORAGE, STAIRS AND HALF BATH (40'X18'-10"), 2ND FLOOR TWO BEDROOMS, LIVING ROOM AND FULL BATH (18'-10"X50'-8")) TO EXISTING DUPLEX.
- Permit Issued
- Issued on 12/20/2011
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/26/2010 | APPLICANT |
| Assigned to Plan Check Engineer | 11/5/2010 | SHABNAM SHAHRIARI |
| Corrections Issued | 11/9/2010 | SHABNAM SHAHRIARI |
| Quality Review Completed | 11/17/2010 | DOUGLAS NAKATANI |
| Building Plans Picked Up | 11/18/2010 | APPLICANT |
| Applicant returned to address corrections | 11/30/2010 | SHABNAM SHAHRIARI |
| Applicant returned to address corrections | 12/21/2010 | SHABNAM SHAHRIARI |
| Applicant returned to address corrections | 2/15/2011 | SHABNAM SHAHRIARI |
| Applicant returned to address corrections | 6/7/2011 | SHABNAM SHAHRIARI |
| Plan Check Approved | 9/28/2011 | SHABNAM SHAHRIARI |
| Issued | 12/20/2011 | LADBS |
| CofO in Progress | 9/26/2024 | RONNIE MINDANAO |
| CofO in Progress | 12/2/2024 | JOAQUIN GREENOUGH |
| No Progress | 12/2/2024 | JOAQUIN GREENOUGH |
| Permit Finaled | 12/5/2024 | DEROLD HAUFF |
| Permit Finaled | 12/5/2024 | DEROLD HAUFF |
| CofO Issued | 12/5/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 9/12/2011 | CARLOS PELAEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/14/2011 | AVALYN KAMACHI |
| Roof/Waste drainage to street | Cleared | 9/14/2011 | AVALYN KAMACHI |
| Sewer availability | Cleared | 9/14/2011 | AVALYN KAMACHI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | , ; Lic. No.: S5345 | , |
| Engineer | Montenegro, Pedro R; Lic. No.: C49443 | 8658 MISSION DRIVE ROSEMEAD, CA 91770 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/17/2012 | Approved | ROBERT MCDOWELL |
| METHANE-Barrier | 5/17/2012 | Approved | ROBERT MCDOWELL |
| METHANE-Subgrade | 5/17/2012 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2012 | Partial Approval | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2012 | Partial Approval | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2012 | Approved | GOURGEN PETROSSIAN |
| Green Building Rough | 11/9/2012 | Not Ready for Inspection | RICHARD DOCKUS |
| Wood Frame | 1/10/2013 | Partial Inspection | ROBERT MCDOWELL |
| Green Building Rough | 1/14/2013 | Approved | DONALD CRICHLOW |
| Green Building Final | 2/26/2013 | Partial Inspection | DONALD CRICHLOW |
| Wood Frame | 3/4/2013 | Corrections Issued | GOURGEN PETROSSIAN |
| Wood Frame | 3/14/2013 | Approved | GOURGEN PETROSSIAN |
| Interior/Exterior Lathing | 3/15/2013 | Approved | GOURGEN PETROSSIAN |
| Insulation | 5/16/2013 | Corrections Issued | MICHAEL TEMPLE |
| Insulation | 5/21/2013 | Approved | GOURGEN PETROSSIAN |
| Drywall Nailing | 6/7/2013 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 12/18/2013 | Not Ready for Inspection | EDWARD GOMEZ |
| Final | 1/9/2014 | No Access for Inspection | CHARLES BOGHOSKHAN |
| Final | 5/14/2015 | Not Ready for Inspection | ROBERT MCDOWELL |
| Final | 3/1/2019 | Corrections Issued | PIERRE VEGA |
| Green Building Final | 3/1/2019 | Not Ready for Inspection | PIERRE VEGA |
| SGSOV-Seismic Gas S/O Valve | 3/1/2019 | SGSOV Not Ready | PIERRE VEGA |
| Smoke Detectors | 3/1/2019 | Not Ready for Inspection | PIERRE VEGA |
| Final | 5/29/2024 | Corrections Issued | RONNIE MINDANAO |
| Green Building Final | 5/29/2024 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 5/29/2024 | SGSOV Not Ready | RONNIE MINDANAO |
| Smoke Detectors | 5/29/2024 | Approved | RONNIE MINDANAO |
| Final | 8/22/2024 | Corrections Issued | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 8/22/2024 | SGSOV Approved | RONNIE MINDANAO |
| Final | 9/13/2024 | Conditional Approval | RONNIE MINDANAO |
| Final | 9/25/2024 | OK to Issue CofO | RONNIE MINDANAO |
| Special/Order Compliance | 11/22/2024 | Corrections Issued | RONNIE MINDANAO |
| Final | 12/2/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Pre-Inspection | 12/3/2024 | Approved | RONNIE MINDANAO |