1142 S HIGHLAND AVE 90019

Certificate Information: 1142 S HIGHLAND AVE 90019

Application / Permit
10014-20000-03979
Plan Check / Job No.
B10VN10201
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ADD NEW 2-STORY ADDITION (FIRST FLOOR: 2-CAR GARAGE, STORAGE, STAIRS AND HALF BATH (40'X18'-10"), 2ND FLOOR TWO BEDROOMS, LIVING ROOM AND FULL BATH (18'-10"X50'-8")) TO EXISTING DUPLEX.
Permit Issued
Issued on 12/20/2011
Issuing Office
Valley
Current Status
CofO Issued on 12/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/26/2010 APPLICANT
Assigned to Plan Check Engineer 11/5/2010 SHABNAM SHAHRIARI
Corrections Issued 11/9/2010 SHABNAM SHAHRIARI
Quality Review Completed 11/17/2010 DOUGLAS NAKATANI
Building Plans Picked Up 11/18/2010 APPLICANT
Applicant returned to address corrections 11/30/2010 SHABNAM SHAHRIARI
Applicant returned to address corrections 12/21/2010 SHABNAM SHAHRIARI
Applicant returned to address corrections 2/15/2011 SHABNAM SHAHRIARI
Applicant returned to address corrections 6/7/2011 SHABNAM SHAHRIARI
Plan Check Approved 9/28/2011 SHABNAM SHAHRIARI
Issued 12/20/2011 LADBS
CofO in Progress 9/26/2024 RONNIE MINDANAO
CofO in Progress 12/2/2024 JOAQUIN GREENOUGH
No Progress 12/2/2024 JOAQUIN GREENOUGH
Permit Finaled 12/5/2024 DEROLD HAUFF
Permit Finaled 12/5/2024 DEROLD HAUFF
CofO Issued 12/5/2024 DEROLD HAUFF

Permit Application Clearance Information

Housing rent stabilization Cleared 9/12/2011 CARLOS PELAEZ
Eng Process Fee Ord 176,300 Cleared 9/14/2011 AVALYN KAMACHI
Roof/Waste drainage to street Cleared 9/14/2011 AVALYN KAMACHI
Sewer availability Cleared 9/14/2011 AVALYN KAMACHI

Contact Information

Contractor Owner-Builder       ,
Engineer , ; Lic. No.: S5345       ,
Engineer Montenegro, Pedro R; Lic. No.: C49443 8658 MISSION DRIVE      ROSEMEAD, CA 91770

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/17/2012 Approved ROBERT MCDOWELL
METHANE-Barrier 5/17/2012 Approved ROBERT MCDOWELL
METHANE-Subgrade 5/17/2012 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 8/15/2012 Partial Approval DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 8/27/2012 Partial Approval DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 9/12/2012 Approved GOURGEN PETROSSIAN
Green Building Rough 11/9/2012 Not Ready for Inspection RICHARD DOCKUS
Wood Frame 1/10/2013 Partial Inspection ROBERT MCDOWELL
Green Building Rough 1/14/2013 Approved DONALD CRICHLOW
Green Building Final 2/26/2013 Partial Inspection DONALD CRICHLOW
Wood Frame 3/4/2013 Corrections Issued GOURGEN PETROSSIAN
Wood Frame 3/14/2013 Approved GOURGEN PETROSSIAN
Interior/Exterior Lathing 3/15/2013 Approved GOURGEN PETROSSIAN
Insulation 5/16/2013 Corrections Issued MICHAEL TEMPLE
Insulation 5/21/2013 Approved GOURGEN PETROSSIAN
Drywall Nailing 6/7/2013 Approved ROBERT MCDOWELL
Drywall Nailing 12/18/2013 Not Ready for Inspection EDWARD GOMEZ
Final 1/9/2014 No Access for Inspection CHARLES BOGHOSKHAN
Final 5/14/2015 Not Ready for Inspection ROBERT MCDOWELL
Final 3/1/2019 Corrections Issued PIERRE VEGA
Green Building Final 3/1/2019 Not Ready for Inspection PIERRE VEGA
SGSOV-Seismic Gas S/O Valve 3/1/2019 SGSOV Not Ready PIERRE VEGA
Smoke Detectors 3/1/2019 Not Ready for Inspection PIERRE VEGA
Final 5/29/2024 Corrections Issued RONNIE MINDANAO
Green Building Final 5/29/2024 Approved RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 5/29/2024 SGSOV Not Ready RONNIE MINDANAO
Smoke Detectors 5/29/2024 Approved RONNIE MINDANAO
Final 8/22/2024 Corrections Issued RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 8/22/2024 SGSOV Approved RONNIE MINDANAO
Final 9/13/2024 Conditional Approval RONNIE MINDANAO
Final 9/25/2024 OK to Issue CofO RONNIE MINDANAO
Special/Order Compliance 11/22/2024 Corrections Issued RONNIE MINDANAO
Final 12/2/2024 Corrections Issued JOAQUIN GREENOUGH
Pre-Inspection 12/3/2024 Approved RONNIE MINDANAO