8826 N WINNETKA AVE 91324

Certificate Information: 8826 N WINNETKA AVE 91324

Application / Permit
10014-20000-03121
Plan Check / Job No.
B10VN08134
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF BEDROOM & BATHROOM (11'-0" X 21'-7", 237 SF) PER ENG'R
Permit Issued
Issued on 2/25/2011
Issuing Office
Valley
Current Status
CofO Issued on 3/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/24/2010 APPLICANT
Assigned to Plan Check Engineer 8/24/2010 NILOOFAR MEHRAIN
Corrections Issued 8/24/2010 NILOOFAR MEHRAIN
Issued 2/25/2011 LADBS
CofO in Progress 3/9/2026 DAVID SCANTLIN
Permit Finaled 3/9/2026 JOHN JANSON
CofO Issued 3/9/2026 JOHN JANSON
Permit Finaled 3/9/2026 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/24/2010 JOHN LIN
Roof/Waste drainage to street Cleared 8/24/2010 JOHN LIN
Sewer availability Cleared 8/24/2010 JOHN LIN
Public Works-Highway Ded. Cleared 8/24/2010 JOHN LIN
Public Works-Open Permits Cleared 8/24/2010 JOHN LIN
Public Works-Sewers Cleared 8/24/2010 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Helou, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/19/2012 No Access for Inspection LUIS BARRALES
PLUMBING-Rough 6/19/2012 No Access for Inspection LUIS BARRALES
PLUMBING-Rough 6/20/2012 Not Ready for Inspection LUIS BARRALES
PLUMBING-Rough 6/22/2012 Partial Approval LUIS BARRALES
Footing/Foundation/Slab 6/26/2012 Approved LUIS BARRALES
Deputy Drilled-In Anchors 12/13/2012 Approved LUIS BARRALES
Wood Frame 2/1/2013 Partial Approval LUIS BARRALES
BUILDING-Rough-Frame 10/6/2014 Not Ready for Inspection WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 10/6/2014 Partial Inspection WILLIAM KUEHN
Rough-Elec/Plmb/HVAC 10/6/2014 Not Ready for Inspection WILLIAM KUEHN
BUILDING-Rough-Frame 11/6/2014 Approved WILLIAM KUEHN
Interior/Exterior Lathing 11/6/2014 Partial Inspection WILLIAM KUEHN
Rough-Elec/Plmb/HVAC 11/6/2014 Approved WILLIAM KUEHN
Insulation 11/10/2014 Approved WILLIAM KUEHN
Rough-Elec/Plmb/HVAC 11/10/2014 Approved WILLIAM KUEHN
Drywall Nailing 10/13/2015 Approved TIP WHITING
Shower Pan 1/26/2016 Approved VINCENT HANLEY
Final 2/24/2026 Corrections Issued DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 2/24/2026 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 2/24/2026 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Final 3/6/2026 Approved DAVID SCANTLIN
Final 3/6/2026 OK to Issue CofO DAVID SCANTLIN
HVAC-Final 3/6/2026 Approved DAVID SCANTLIN
PLUMBING-Final 3/6/2026 Approved DAVID SCANTLIN
Smoke Detectors 3/6/2026 Approved DAVID SCANTLIN