1860 S LA BREA AVE 90019
Certificate Information: 1860 S LA BREA AVE 90019
- Application / Permit
- 10010-20000-00871
- Plan Check / Job No.
- B10VN04497
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- NEW 3-STORY COMMERCIAL BLDG V-B/ I-A ( 1ST FLOOR GARAGE / 2ND FLOOR RETAIL(2500SF) /OFFICE ( 1718SF) AND 3RD FLOOR OFFICE )
- Permit Issued
- Issued on 6/17/2011
- Issuing Office
- Valley
- Current Status
- Issued on 6/17/2011
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/11/2010 | APPLICANT |
| Disabled Access Plans Picked Up | 5/20/2010 | APPLICANT |
| Assigned to Plan Check Engineer | 5/21/2010 | GUANG MIN TUNG |
| Corrections Issued | 6/4/2010 | GUANG MIN TUNG |
| Quality Review Completed | 6/9/2010 | BINH PHAN |
| Building Plans Picked Up | 6/9/2010 | APPLICANT |
| Applicant returned to address corrections | 6/16/2010 | GUANG MIN TUNG |
| Applicant returned to address corrections | 7/2/2010 | GUANG MIN TUNG |
| Applicant returned to address corrections | 7/14/2010 | GUANG MIN TUNG |
| Applicant returned to address corrections | 2/15/2011 | GUANG MIN TUNG |
| Applicant returned to address corrections | 2/28/2011 | GUANG MIN TUNG |
| Applicant returned to address corrections | 3/9/2011 | GUANG MIN TUNG |
| Plan Check Approved | 6/3/2011 | GUANG-MIN TUNG |
| Issued | 6/17/2011 | LADBS |
Permit Application Clearance Information
| DAS Clearance | Cleared | 6/3/2010 | NORLITO MEDRANO |
| Address approval | Cleared | 6/14/2010 | HOWARD COOPER |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2010 | ROSE MARIE SMITH |
| Sewer availability | Cleared | 6/14/2010 | ROSE MARIE SMITH |
| Hydrant and Access approval | Cleared | 9/21/2010 | TERRENCE O'CONNELL |
| Project located in CRA area | Cleared | 12/6/2010 | JIM URQUHART |
| Project located in CRA area | Cleared | 12/6/2010 | JIM URQUHART |
| Internal circulation | Cleared | 12/9/2010 | TAIMOUR TANAVOLI |
| Comm Cor/Mini-Mall | Cleared | 12/10/2010 | DENNIS CHEW |
| Comm Cor/Mini-Mall | Cleared | 12/10/2010 | DENNIS CHEW |
| Comm Cor/Mini-Mall | Cleared | 12/10/2010 | RICK TORRES |
| Permit | Cleared | 12/10/2010 | CHRISTINE KEUSHGUERIAN |
| Prkng lot landscape/Water mgmt | Cleared | 12/10/2010 | RICK TORRES |
| Roof/Waste drainage to street | Cleared | 12/10/2010 | CHRISTINE KEUSHGUERIAN |
| Highway dedication | Cleared | 1/10/2011 | BERTRAM MOKLEBUST |
| Construction within easement | Cleared | 1/19/2011 | SCOTT HUNTER |
| Encroachment in public way | Cleared | 2/7/2011 | WESLEY TANIJIRI |
| Work Adjacent to Public Way | Cleared | 2/7/2011 | WESLEY TANIJIRI |
| Stormwater Pollution Mitigatn | Cleared | 2/22/2011 | AYMAN JABBOURI |
| Miscellaneous | Cleared | 3/30/2011 | GUANG-MIN TUNG |
| Miscellaneous | Cleared | 3/30/2011 | GUANG-MIN TUNG |
| Miscellaneous | Cleared | 6/3/2011 | GUANG-MIN TUNG |
Contact Information
| Architect | Skelton, Louis E; Lic. No.: C14342 | 4017 VIA LARGAVISTA PALOS VERDES ESTATES, CA 90274 |
| Contractor | Owner-Builder | , |
| Engineer | , ; Lic. No.: C72413 | , |
| Engineer | Chitchyan, Araik; Lic. No.: C54893 | 9433 VIA PATRICIA BURBANK, CA 91504 |
Inspector Information
| EDWIN GREGORYONA, (213) 482-7357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/18/2011 | Conditional Approval | MAURICE MARTINEZ |
| Footing/Foundation/Slab | 8/26/2011 | Corrections Issued | WINFIELD HINKSON |
| Reinforced Concrete Frame | 9/12/2011 | Partial Approval | WINFIELD HINKSON |
| Deputy Shotcrete | 9/13/2011 | Conditional Approval | WINFIELD HINKSON |
| Footing/Foundation/Slab | 9/21/2011 | Corrections Issued | DANIEL MC AULIFFE |
| Footing/Foundation/Slab | 11/3/2011 | Not Ready for Inspection | WINFIELD HINKSON |
| Footing/Foundation/Slab | 11/7/2011 | Not Ready for Inspection | MICHAEL KUHN |
| Footing/Foundation/Slab | 11/16/2011 | Partial Approval | MICHAEL KUHN |
| Footing/Foundation/Slab | 11/22/2011 | Not Ready for Inspection | MICHAEL KUHN |
| Deputy Reinf. Concrete | 11/23/2011 | Approved | MICHAEL KUHN |
| Excavation/Setback/Form/Re-Bar | 11/23/2011 | Partial Approval | MICHAEL KUHN |
| Footing/Foundation/Slab | 12/1/2011 | Corrections Issued | MICHAEL KUHN |
| Excavation/Setback/Form/Re-Bar | 6/12/2013 | Partial Inspection | MICHAEL KUHN |
| Special/Order Compliance | 6/20/2013 | Partial Approval | MICHAEL KUHN |
| Final | 8/7/2014 | Partial Inspection | MICHAEL KUHN |
| Special/Order Compliance | 8/16/2016 | Partial Inspection | GREGORY POMISH |
| Special/Order Compliance | 8/30/2016 | Corrections Issued | GREGORY POMISH |