2436-2438 N RIVERSIDE PL 90039
Certificate Information: 2436-2438 N RIVERSIDE PL 90039
- Application / Permit
- 10010-10006-00896
- Plan Check / Job No.
- B24LA10233
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- SUPPLEMENTAL PERMIT TO PERMIT NO. 10010 - 10000 - 00896 TO RENEW PERMIT AND CAPTURE THE NEW FLOOR LAYOUT OF THE FRONT UNIT. CORRECT STRUCTURAL INVENTORY AND SCOPE OF WORK TO: (N) TWO STORY DUPLEX W/ ATTACHED TWO CAR GARAGE CONNECTED W/ A BREEZEWAY
- Permit Issued
- Issued on 7/20/2024
- Issuing Office
- Current Status
- Permit Finaled on 11/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2024 | SERGIO GUTIERREZ |
| Corrections Issued | 6/17/2024 | SERGIO GUTIERREZ |
| Quality Review Completed | 6/26/2024 | RODOLFO ARIAS |
| Plan Check Approved | 7/19/2024 | SERGIO GUTIERREZ |
| Issued | 7/20/2024 | APPLICANT |
| Permit Finaled | 11/7/2024 | LUIS CASTRO |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 6/27/2024 | DAVID LOPEZ |
| BHO/Hillside ordinance | Cleared | 6/27/2024 | DAVID LOPEZ |
| BHO/Hillside ordinance | Cleared | 6/27/2024 | DAVID LOPEZ |
| BHO/Hillside ordinance | Cleared | 6/27/2024 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 6/27/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 6/27/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2024 | DAVID LOPEZ |
| Miscellaneous | Cleared | 7/1/2024 | DAVID URITA |
| ZA Case | Cleared | 7/1/2024 | DAVID URITA |
| GPI Written Notices | Cleared | 7/19/2024 | SERGIO GUTIERREZ |
| Grading Pre-Inspection | Cleared | 7/19/2024 | MICHAEL TEMPLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 8/2/2024 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 8/2/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 8/5/2024 | Conditional Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 8/6/2024 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 8/6/2024 | Approved | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 8/16/2024 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 8/22/2024 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 10/11/2024 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Final | 10/11/2024 | Not Ready for Inspection | LUIS CASTRO |
| PLUMBING-Final | 10/11/2024 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Final | 10/16/2024 | Approved | HAMIK HARTOUNIAN |
| HVAC-Final | 10/16/2024 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 10/16/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Service/Power Release | 10/16/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Final | 10/21/2024 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 10/29/2024 | Approved | LUIS CASTRO |
| Final | 10/29/2024 | Corrections Issued | LUIS CASTRO |
| MERV13>=Final | 10/29/2024 | Approved | LUIS CASTRO |
| MERV13>=Rough | 10/29/2024 | Approved | LUIS CASTRO |
| Service/Power Release | 10/29/2024 | Not Ready for Inspection | LUIS CASTRO |
| Verify Sprinkler Sign Off | 10/29/2024 | Approved | LUIS CASTRO |
| Service/Power Release | 10/31/2024 | Corrections Issued | LUIS CASTRO |
| Pre-Inspection | 11/4/2024 | Not Ready for Inspection | LUIS CASTRO |
| Service/Power Release | 11/4/2024 | Not Ready for Inspection | LUIS CASTRO |
| Service/Power Release | 11/6/2024 | Approved | LUIS CASTRO |