2436-2438 N RIVERSIDE PL 90039

Certificate Information: 2436-2438 N RIVERSIDE PL 90039

Application / Permit
10010-10006-00896
Plan Check / Job No.
B24LA10233
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
SUPPLEMENTAL PERMIT TO PERMIT NO. 10010 - 10000 - 00896 TO RENEW PERMIT AND CAPTURE THE NEW FLOOR LAYOUT OF THE FRONT UNIT. CORRECT STRUCTURAL INVENTORY AND SCOPE OF WORK TO: (N) TWO STORY DUPLEX W/ ATTACHED TWO CAR GARAGE CONNECTED W/ A BREEZEWAY
Permit Issued
Issued on 7/20/2024
Issuing Office
Current Status
Permit Finaled on 11/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/29/2024 APPLICANT
Assigned to Plan Check Engineer 6/13/2024 SERGIO GUTIERREZ
Corrections Issued 6/17/2024 SERGIO GUTIERREZ
Quality Review Completed 6/26/2024 RODOLFO ARIAS
Plan Check Approved 7/19/2024 SERGIO GUTIERREZ
Issued 7/20/2024 APPLICANT
Permit Finaled 11/7/2024 LUIS CASTRO

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 6/27/2024 DAVID LOPEZ
BHO/Hillside ordinance Cleared 6/27/2024 DAVID LOPEZ
BHO/Hillside ordinance Cleared 6/27/2024 DAVID LOPEZ
BHO/Hillside ordinance Cleared 6/27/2024 DAVID LOPEZ
Roof/Waste drainage to street Cleared 6/27/2024 DAVID LOPEZ
Sewer availability Cleared 6/27/2024 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 7/1/2024 DAVID LOPEZ
Miscellaneous Cleared 7/1/2024 DAVID URITA
ZA Case Cleared 7/1/2024 DAVID URITA
GPI Written Notices Cleared 7/19/2024 SERGIO GUTIERREZ
Grading Pre-Inspection Cleared 7/19/2024 MICHAEL TEMPLE

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 8/2/2024 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 8/2/2024 Corrections Issued HAMIK HARTOUNIAN
Deputy Wood Construction 8/5/2024 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/6/2024 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 8/6/2024 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 8/6/2024 Approved HAMIK HARTOUNIAN
Deputy Wood Construction 8/16/2024 Partial Approval SCOTT FINNILA
Drywall Nailing 8/22/2024 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 10/11/2024 Not Ready for Inspection LUIS CASTRO
HVAC-Final 10/11/2024 Not Ready for Inspection LUIS CASTRO
PLUMBING-Final 10/11/2024 Not Ready for Inspection LUIS CASTRO
ELECTRICAL-Final 10/16/2024 Approved HAMIK HARTOUNIAN
HVAC-Final 10/16/2024 Approved HAMIK HARTOUNIAN
PLUMBING-Final 10/16/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Service/Power Release 10/16/2024 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Final 10/21/2024 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 10/29/2024 Approved LUIS CASTRO
Final 10/29/2024 Corrections Issued LUIS CASTRO
MERV13>=Final 10/29/2024 Approved LUIS CASTRO
MERV13>=Rough 10/29/2024 Approved LUIS CASTRO
Service/Power Release 10/29/2024 Not Ready for Inspection LUIS CASTRO
Verify Sprinkler Sign Off 10/29/2024 Approved LUIS CASTRO
Service/Power Release 10/31/2024 Corrections Issued LUIS CASTRO
Pre-Inspection 11/4/2024 Not Ready for Inspection LUIS CASTRO
Service/Power Release 11/4/2024 Not Ready for Inspection LUIS CASTRO
Service/Power Release 11/6/2024 Approved LUIS CASTRO